HomeMy WebLinkAbout02-02-1994 CITY COUNCIL AGENDA\1
SARATOGA CITY COUNCIL
EXECUTIVE SUMMARY NO. v �O
MEETING DATE: FEBRUARY 2, 1994
ORIGINATING DEPT.: PUBLIC WORKS 4t�
AGENDA ITEM 7
CITY MGR.
SUBJECT: Warner Hutton House Improvements, Capital Project No. 9301
- Final Acceptance and Notice of Completion
Recommended Motion(s): Move to accept the project as complete and
authorize staff to record the Notice of Completion for the project.
Report Summary: All work on the Warner Hutton House Improvements,
Capital Project No. 9301, has been completed -by the City's
contractor, Progressive Pacific, and inspected by City staff. The
final construction cost for the project was $24,318, which is 28.2%
above the awarded contract amount of $18,975. The additional costs
were primarily due to extra plumbing and electrical work arising
from unknown conditions which became exposed during the remodelling
process.
In order to close out the construction contract and begin the one
year maintenance /warranty period, it is recommended that the
Council accept the project as complete. Further, it is recommended
that the Council authorize staff to record the attached Notice of
Completion for the contract so that the requisite 30 day Stop
Notice period for the filing of claims by subcontractors or
material providers may commence.
Fiscal Impacts: The ten percent retention withheld from previous
payments to the contractor will be released 30 days after
recordation of the Notice of Completion assuming no Stop Notices
are filed with the City. The adopted budget contains sufficient
funds in Project No. 9301, Account No. 4510, to cover the cost of
the project including the executed change orders.
Follow Up Actions: Staff will record the Notice of Completion for
the contract and will release the contract sureties and retention
thirty days thereafter.
Consequences of Not Acting on the Recommended Motions: The project
would not be accepted as complete and staff would notify the
contractor of any additional work required by the City Council
before the project would be accepted as complete.
Advertising, Noticing and Public Contact: None required.
Attachments: 1. Contract Summary.
2. Notice of Completion.
CONTRACT SUMMARY
PROJECT: Warner Hutton House Improvements - C.I.P. #9301
CONTRACTOR: Progressive Pacific
CONTRACT DATE: 07 /07/93
ORIGINAL CONTRACT AMOUNT: $18,975
C.O. AUTHORITY: $5,350
CONTRACT COMPLETION DATE: 02/02/94.:
TOTAL C.O. AMOUNT: $5,343.43.
FINAL CONTRACT AMOUNT: $24,318.43
PERCENT +/- FROM ORIGINAL CONTRACT AMOUNT: +28.2%
r
SARATOGA CITY COUNCIL
EXECUTIVE SUMMARY NO. 1 AGENDA ITEM: V
MEETING DATE: February 2, 1994
CITY MGR.
ORIGINATING DEPT.: Community Development APPROVAL '
SUBJECT: DR -93 -030 & V -93 -026 - Ebrahimoun; 15170 E1 Camino Grande
Appeal of Design Review approval limiting the size of a
new two -story residence and denial of a Variance to allow
the proposed structure to exceed the site's maximum
permitted floor area. (NOTE: THIS IS A RECONSIDERATION
OF THIS APPEAL, WHICH WAS DENIED BY THE CITY COUNCIL ON
JANUARY 5, 1994.)
Recommended Motion:
Deny the appellant's request and uphold the following Planning
Commission decisions:
1. Approval of Design Review request to construct a new residence
with the condition that the size of the proposed residence be
reduced from 6,277 sq.ft. to 5,685 sq.ft. (Passed 5 -0)
2. Denial of Variance request to exceed the site's maximum
permitted floor area of 5,688 sq.ft. by 589 sq. ft. (Passed 4 -1)
Report Summar
On January 5, 1994, the City Council denied the applicant's appeal
by a 3 -2 vote (Burger,Kohler) upholding the decision of the
Planning Commission. On January 11, 1994, the applicant requested
that the City Council reconsider its denial of his appeal and
submitted a letter from his attorney substantiating his request.
The City Council voted 5 -0 to reconsider the appeal and directed
staff to readvertise. a public.hearing'for February 2, 1994..
Attached along with the complete staff report package presented to
the City Council 'at the January 5 public hearing are the minutes of
the January 5 and January 11 City Council meetings and the
applicant's letter requesting the reconsideration.
Public Noticing:
This item was readvertised for the February 2 public hearing by
notice in the Saratoga News, mailing notices to property owners
Ebrahimoun Appeal (Reconsideration)
DR-93-630.6 V -93 -026
February 2, 1994
Page 2
within 500 ft. of the project site and posting of a notice at City
Hall.
Fiscal Impacts: None. (Note: No application fees were required
for the reconsideration public hearing.)
Follow -up Actions: None.
Consequences of Not Acting on Recommended Motions:
The applicant would be permitted to construct a house larger than
allowed by City Code.
Attachments:
1. Letter requesting reconsideration, dated January 10, 1994.
2. , City Council minutes of January 5 and January 11, 1994.
3. City Council Executive Summary dated January 5, 1994.
4. Appeal Letter from Planning Commission decisions.
5. Resolutions DR -93 -030 & V -93 -026.
6. Planning Commission minutes of November 22, 1993.
7. Planning Commission minutes of December 8, 1993.
8. Staff Report dated November 22, 1993.
9. Plans, Exhibit "A ".
RMIT
Nafida
A W Y F R S
SENT BY FAX
741 -1132
January 10, 1994
Honorable Mayor and
Members of the Council
City of Saratoga
13777 Fruitvale Avenue
Saratoga, CA 95070
a �Jq nj 1994
-j
CI ,l 1'T
DICE
Re: Request for.Reconsideration
(V -93 -026; 15170 E1 Camino Grande)
Dear Mayor Tucker and Members of the Council:
Kodak Center
1740 Technology Drive
State 250,
Sat lose, CA 95110
408 441 -7800
FAX' 408 441 -7302
Norntan E. Mattconi
Allan Robert Sax,-
Margaret Ecker Natda
Peggy M. O'Laughlin
Debra L.Cauble
,Jtuh• C. Tsai
I3radlev M. Matte uni
On January 5, 1994, the Council upheld denial by the
Planning Commission of the request from Mr. and Mrs.
Ebrahimoun for a variance to allow construction of a new home
which would exceed the allowable floor area by 589 square
feet. The purpose of this letter is to request that the
Council reconsider its action and set the appeal for further
hearing.
Mr. Ebrahimoun believes that you were prevented from
receiving an accurate understanding of the facts surrounding
his variance request because of the unexpected direct.involve-
ment of a Planning Commissioner at his appeal hearing. It is
Mr. Eb'rahimoun's contention that the testimony of the Planning
Commissioner distorted the action taken by the Commission, but
without the benefit of testimony from the Commissioner who
supported his application or at least .a neutral representative
of the Commission, it was impossible for him to overcome the
presumption that the Commissioner appearing to testify was, in
fact, speaking for the entire Commission.
It is my understanding the Saratoga Zoning Ordinance
requires that appeals from Planning Commission actions be
heard de novo by the Council. Obviously, the decision of the
Planning Commission - as opposed to the views of an individual
Commissioner or Commissioners - is an important factor to be
considered by the Council in acting on an appeal. However,
I
bw
the appellant is entitled to a clean slate in terms of
presenting the merits of his or her proposal to any reviewing
body acting in a de novo capacity. The intrusion of Planning
Commissioner Kaplan into the presentation and consideration of
Mr. and Mrs. Ebrahimouns' appeal deprived them of that clean
slate.
It is respectfully requested that the Council
reconsider its action on January 5, 1994, denying the
Ebrahimoun appeal and further that you set the appeal for
further hearing at one of your meetings during February.
Because of a prior commitment, I will be unable to attend the
Council meeting on January 11, 1994, but Mr. Ebrahimoun will
be present should you have any questions regarding this
request.
i
Thank you very much.
VeerryD truly yours,
ALLAN R. SAXE
ARS:md
cc: Ms. Karen Anderson
Ms. Ann Marie Burger
Mr. William Kohler
Mr. Victor Monia
Mr. Harry Peacock
Mr. Michael Riback
Mr. and Mrs. David Ebrahimoun
City council Minutes 10 January.5, 1994
Mayor Tucker stated new and old business owners should be put on
notice regarding the City Council's decision. i
B. Ordinance amending Various Sections of.chapter 4 of the
City Code pertaining to Business Regulations and Business
License Fees (first reading and introduction)
Staff recommends that the City Council introduce the ordinance by
title only, waiving further reading.
BURGER /MONIA MOVED TO INTRODUCE THE ORDINANCE BY TITLE ONLY,
WAIVING FURTHER READING.
Councilmember Anderson noted she was approanhed by Eric - Morley who
asked that "grc�;s receipts" in the definition section be removed,
because gross receipts is no longer part of the business license.
City Manager Peacock stated if the Council want to :change the
business license or they must go through two public
hearings. He believes it does no harm to keep the definition as
is.
The above motion was carried 5 -0.
C. Appeal of design review approval limiting the size of a
new two -story residence to 5,685 sq. ft. and iienial of a
variance to allow the proposed residence to1exceed the
site's maximum allowable floor area by 589 sq. ft. (for
a total of 6,277 sq. ft. of floor area where the maximum
floor area permitted is 5,688 sq. ft.) The subject
property is approximately 51,400 sq. ft. in an R- 1- 40,000
zone district at 15170 El Camino Grande
(Appellant /applicant, Ebrahimini) (DR93- 030;!V93 -026)
Planning Director Curtis presented the staff report dated January
3, 1994 and noted the applicant initially submitted a plan that
conformed to code, but requested changes that require a variance.
He stated on November 22, 1993 the Planning Commission denied both
the variance and the design review. He stated the applicant
requested that the Planning Commission reconsider the design
review, and this was approved with the restriction on'the square
footage allowed, but did not approve the variance. He stated staff
recommended to the Planning Commission that findings could not be
made and there were no special circumstances on the lot which would
warrant the variance.
In response to Councilmembers' questions, Mr. Curtis stated the
calculations were based on the slope of the property and the second
story element' is within, code. He stated if the formula used to
calculate the slope was rounded down as opposed to rounded up, the
applicant would ,still need a variance. He pointed; out that,
although the garage is partly underground the square footage of the
garage is still counted.
Councilmember Burger noted she did visit the site.as dib the other
Councilmembers.
In response to Councilmember Anderson's question, Mr. Curtis
explained the square footage allowed if there was no slope on the
property. He noted the Heritage Preservation Commission did not
look at this property.
Mayor Tucker opened the public hearing at 11:10 p.m.
Mr. David Ebrahimini, 15170 E1 Camino Grande, stated he is
requesting the variance for the following reasons: 1) environmental
impacts, thick walls better for energy conservationC 2) slope
calculation was rounded up, and staff considers this property in
the hillside zoning, it is not in the hillsides; 3) there has been
considerable effort to design the house. He noted a large as
of the garage is underground and should be considered basement.
i
city council Minutes 11 January 5; 1994
He noted he requests the variance so his family can have a
desirable home to live in and he has full support from his
neighbors. He noted there is no visual difference between the plan
before the Council and the plan approved by the Planning
Commission. He stated the proposed design is compatible with the
neighborhood and urged approval of the plan before the,Council.
i
Ms. Mary Ellen Comport, 15242 E1 Camino Grande, statedishe looked
at the request for the variance for several reasons. :She stated
the neighborhood is going through a transition and some homes need
to be remodeled from ground up. With regards to the proposed plan,
only one tree has to be removed and the footprint is increased
because of the thicker walls. She stated the house is unobtrusive
and believes the variance should be c? ranted.. She added this is the
house of the Ebrahimini's dreams.
i
Ms. Jean Ebrahimini; 15170 E1 Camino Grande, stated she requests
approval of the variance. She noted the exterior elevation will
not be affected with the change in plans. She requested approval
for several reasons. She noted the underground two car garage is
best for the neighborhood and the environment,. even though it is
more costly. Also the neighbors are supportive of the request for
the variance and it will have no effect on the exterior elevation
which has been approved.
Mr. Maurice Camargo, 3953 Yolo Drive, San Jose, Architect, stated
the property owners occupied the house 13 years ago and have been
working to obtain their dream home. He stated they have made
compromises to reduces the square footage. He pointed out that the
walls are 12" thick for a total of 245,sq. ft, also the windows are
double pane. - I
Councilmember Monia asked if Mr. Camargo consulted with the City
code regarding the maximum square footage allowed, and if so why
design a home which does not meet the zoning regulations.
Mr. Camargo stated he did consult city codes, and submitted plans
with some compromises. He stated they originally went through the
process thinking. the square footage of the garage w uld not be
counted, as it is partially underground.
In response to Councilmember Burger's question, Mr. Camargo stated
the double pane windows will.provide the best insulation, but part
of the depth of the walls is for architecture and also fbr shading.
Mayor Tucker asked if there is a substantial increase in energy
conservation with the 12" walls as opposed to the 6" walls.
Mr. Camargo stated any insulation in the walls is good, but they
are also shading the windows.
Councilmember Anderson asked for the plan which was approved by the
Planning Commission.
Councilmember Monia stated the Planning Commission approved the
plan, presented to the Council, in concept but the size is to be
reduced.
r
Ms. Nickie Kovac, 15150 E1 Camino Senda, stated the neighbors are
concerned about the neighborhood, but do support the pr posed plan
as it will add.to the neighborhood and is compatible.
{ Ms. Betsy Mace, 15195 E1 Camino Senda, spoke in support of the
request for the variance. She noted the design is compatible with
the neighborhood and the 12" walls do add to the quality of the
homes. i
Ms. Marcia Kaplan, Planning Commissioner, speaking on behalf of
Sami.Asfour, explained the reconsideration the applicant requested
at the end of the Planning Commission meeting. Sheistated the
approved plan was to save costs with regards to submitting a new
application. She stated, as a Commissioner she goes by the rules
City Council Minutes 12 January 5, 1994
and to grant variances, findings must be made. She stated visual
impact and neighborhood support are not. legal findings bo grant the
variance.
Councilmember Monia stated it his understanding that the applicant
asked for reconsideration under oral communications and'a proposal
was made by the applicant to try to move the process forward and
approve the design review if the maximum square footage allowed was
met. `
Ms. Kaplin stated the original plans conformed and this 'is what she .
believes was approved. She noted the design was acceptable.
Mr. Camargo stated the property owner was not present at _the
Planning Commission meeting and it was his understandt7•.g tha: if
they choose to go with the application the fees forlthe review
would be continued so they asked for approval for the plan and he
would talk to the owner about this. He stated they are!now before
the Council requesting approval for the variance.
Mayor Tucker closed the public hearing at 11:40 p.m.
Councilmember Anderson stated it is compelling to approve a project
when there is full neighborhood support, but did question the
findings. I
In response to Councilmember Anderson's question, City Attorney
Riback stated the applicant has to show extraordinary circumstances
existing on the property, if not taken into consideration, would
result in hardship to the property owner. He stated the findings
must be unique circumstances that would prevent property owners
enjoying the benefit of one's property. He added the findings must
be related to a practical difficulty that would prevent the
property owner enjoying his property as other propertyjowners do.
Councilmember Kohler stated the home is built on a slope and the
calculation was rounded up and believes this is a ponalty. He
noted the thick walls are not livable space and the ent�ance,to the
garage is underground and believes this should be co sidered as
part of a basement structure. He believes all penaltie6s add up to
500 ft.. j
KOHLER /BURGER MOVED TO APPROVE THE APPEAL BECAUSE OF!THE UNIQUE
CIRCUMSTANCES ON THE PROPERTY.
Councilmember Burger stated she would support the motion because of
the hardship imposed on the property owner such .ash the slope
calculation. She stated trees are being preserved and the
neighborhood is in full support. She stated the City is making a
mistake when penalizing the applicant for showing sensitivity to
the environment. She stated one of the findings is that. the design
is environmentally sensitive because of the thickness of the walls,
which provides insulation.. She noted the perception of bulk has
been removed by placing the garage partly underground. She stated
there-is no visual impact.
,.Councilmember Monia stated he is in support of the design and being
sensitive to. the environmental concerns are complimentary to the
neighborhood. He stated the problem is, making the tindings to
grant a variance. He noted this is a very large home a few homes
in this zoning district are this large. He believes t e property
owner is benefitting from the slope because of the ba ement etc',
but cannot make the findings to grant the variance.
City Attorney Riback stated he did review. the variance ordinance
and noted that the conditions set forth in the ordinance can take
into consideration physical conditions of the property, but the
Council can not use the applicant's design as a basis; for making
the findings or hardships. He noted conditions must be; identified
and they must be identified as to how they are icreating a
difficulty.
city council Minutes 13 January 5, 1994
Councilmember Anderson stated the only physical.difficulty is the
slope, and does not believe this is a physical constraint. She
noted she can not make legal findings to grant this var�.ance. She
also expressed concern about setting a precedent, if 1he Council
approves this project.
Mayor Tucker asked the Councilmembers who made they motion to
identify the findings.
Councilmember Kohler stated the rules and regulations of the City
are to avoid obtrusive homes. He stated in this caseione of the
findings is the underground garage and believes part of this should
be considered basement.
Mayor Tucker stated the slope density was developed :to protect
hillsides and views and noted she can not make any legal findings
to support the project.
The above motion was denied 2 -3 (Tucker, Anderson, Monia No).
i
jCity Manager Peacock stated the design review has been approved
with the condition that the house size be reduced and the applicant
can now submit plans to staff and receive approval, as long as the
square footage meets the Planning Commission's approval.
MONIA /ANDERSON MOVED TO DENY THE APPEAL: PASSED 3-2 (Burger,
Kohler No).
9. CITY COUNCIL ITEMS
A. Oral Communications (continued) and instructions to staff
regarding actions on current "oral communications - None.
B. Agency Assignment Reports
1. ABAG - Anderson
2. Cable TV Board - Monia
3. HCD Policy Committee - Tucker
4. Transportation Commission - Anderson
5. Hakone Foundation - Kohler
6. Flood Control Advisory Board - Burger
7. League of Cities Peninsula Division - Tucker
8. Water District Commission - Anderson
9. Santa Clara County Cities Association - Tucker
10. Sister City Committee - Burger
11. Traffic Authority Policy Advisory Boardi- Tucker
12. Transit Assist Board - Burger
13. Senior Coordinating Committee - Burger
14. West Valley Sanitation District - Burge
15. County Cities Assn. Legislative Task Force - Monia
16. Emergency Planning Council - Kohler
17. Congestion Management Agency Advisory Board -
Burger /Tucker
18. Local Transportation Authority Policy Advisory
I Board -Kohler/Anderson
Councilmember Burger stated the Senior Coordinating Committee is in
the process of doing their planning for their annual retreat.
Councilmember Anderson stated she received a phone call from
Michael Collishaw and they are planning another Jazz festival, but
would like to do it for three days. She noted they will be
entertaining applications from other charities or non- profit
agencies in the community who may want to benefit from the other
two days. She suggested that the Councilmembers pass this on.
C. General Council Items
1) Agenda items for January
meeting (Joint Meeting with
a. Commission's Response
11 adjourned regular
Library Commission)
to December 9 Community
MINUTES
SARATOGA CITY COUNCIL
TIME: Tuesday, January 11, 1994 - 7:30 p.m.
PLACE: City Hall Administration Meeting Room, 13777 Fruitvale
Ave.
TYPE: Adjourned Regular Meeting /Jt. Meeting with Library
Commission
1. Roll Call
The meeting was called to order at 7:35 p.m. Councilmembers
Burger, Kohler, Monia and Mayor Tricker were present; Councilmember
Anderson was absent (arrived when noted below).
2. Report of City Clerk on Posting of Agenda
Pursuant to Government Code 54954.2, the agenda for this meeting
was properly posted on January 7. The notice of adjouXnment from
the January 5 Council meeting was properly posted on ,anuary 6.
ADDED TO AGENDA:
The Council considered taking up a Request for Reconsideration
I (Ebrahimoun) - see 1/10/94 letter from Allan R. Saxe." The Council
read the letter.
j
Councilmember Anderson arrived at 7:40 p.m.
The denial was without prejudice so the applicant can reapply
iwithout paying full fees.
Councilmember Kohler felt that statements by Commissioner Kaplan
create a due process problem in his mind.
The City Attorney opined that after reviewing the comments he found
no violation of due process. Remaining question is whether her
comments, which were contrary to Council tradition, unduly
influenced the vote.
ANDERSON /KOHLER MOVED TO RECONSIDER THE APPEAL. Passe .5 -0.
3. Adoption of Urgency Ordinance to Establish Weight Limit
i Restriction for Pierce Road Bridge
BURGER /ANDERSON MOVED TO ADOPT THE ORDINANCE. Passed 5 -0.
I
4. Crossing Guard Funding
Get current .Public Safety Commission listing of recommended
crossing guard locations and current locations filled. Question is
whether City should require district schools to provide car pool
services in exchange for,crossing guard funding as recommended by
Anderson.
Burger would like to know whether schools now have the money to pay
for their own crossing guards.
Councilmember Kohler .)said schools should come to the City and offer
services or facilities in exchange for crossing guards. :He doesn't
feel requiring car pooling will work.
There was consensus to place districts on notice of Ci y's intent
to not continue funding without some consideration in eturn from
the schools.
5. Annual Joint Meeting with Library Commission
a. Commission's Response to December 9 Community Forum
SARATOGA CITY COUNCIL
EXECUTIVE SUMMARY NO. AGENDA ITEM:
MEETING DATE: January 5, 1994
CITY MGR.
ORIGINATING DEPT.: Community Development APPROVAL
SUBJECT: DR -93 -0304 V -93 -026 - Ebrahimoun; 15170 El Camino Grande
Appeal of Design Review approval limiting the si - ;e of a new
two -story residence and denial of a Variance to allow the
proposed structure to exceed the site's maximum permitted
floor area.
Recommended Motion:
Deny the appellant's request and uphold the following Planning
Commission decisions:
1. Approval of Design Review request to construct a new residence with
the condition that the size of the proposed residence be reduced
from 6,277 square feet to 5,685 square feet. (Passed 5 -0)
2. Denial of Variance request to exceed the site "s maximum permitted
floor area of 5,688 square feet by 589 square feet. (Passed 4 -1)
Report Summary:
Planning Commission Review:
This proposal for a new single - family residence at the corner of El
Camino Grande and E1 Camino Senda was presented to the Planning
Commission at the November 22, 1993 public hearing. The proposal
includes a request for Design Review approval to allow the demolition of
an existing residence and the construction of a new two -story 6,277
square foot residence. Variance approval was also requested to allow
the proposed residence to exceed the maximum permitted floor area of
5,688 square feet by 589 square feet.
Initially the Planning Commission denied the applicant's requests for
Design Review and Variance approval. The Commissioners were supportive
of the overall design of the residence and felt they could make the
necessary Design Review findings. However, since the Design Review
approval was contingent on the Variance application being approved and
the could not make the findings to support the Variance, both requests
were initially denied per staff's recommendation.
Later in the meeting under Oral Communications, the applicant's
representative requested the Planning Commission to reconsider their
decision. He stated that the applicants would like to present their
original plans to the Planning Commission, which conformed to the
maximum permitted floor area requirements and did not require Variance
approval, and move forward through the process. The Commission voted 5-
0 to reconsider the vote and again denied the Variance request (4 -1).
Ebrahimoun Appeal .
DR -93 -030 & V -93 -026
January 8, 1994
Page 2
However, the Design Review request-was approved (5 -0) with the condition
that the proposed floor area be reduced to conform with the City's
requirements.
Appeal Letter:
The applicants are now appealing the Planning Commission's decision. In
their letter dated December 7, 1993, the applicants state several
reasons why they feel they should be granted a Variance to exceed the
site's maximum permitted floor area. Each of these reasons are
summarized below followed be staff's response.
• Desire to enlarge underground garage by 225 square feet.
Staff's Response: The applicants do not feel this area should be
counted as floor area since it is not visible from the exterior of
the house. However, the ordinance requires that all underground
area be counted as floor area unless no portion of the room is more
than two feet above grade.
Desire to increase the thickness of exterior walls from six inches
to 12 inches to provide energy efficiency. This also complements
the proposed "Mediterranean" architectural style of the home.
Staff's Response: Section 15- 06.280 states that floor area shall
be measured to the outside surface of exterior walls.
Requirement to round -up the average slope calculation of 19.3 to 20
percent for the floor area slope adjustment requirement. The
applicants feel they were penalized since the average slope was
rounded up, which requires the net site area to be reduced by 30
percent versus 28 percent (if they were permitted to round down).
Staff Response: Section 15- 45.030 states where the average slope
is a fractional number, it shall be rounded up to the next .whole
number. All applications are reviewed under this provision.
Therefore, the applicants were not penalized.
• _ Fact that an adjacent property was permitted to build a larger home
than the applicants are proposing on a parcel smaller than the
applicants'.
Staff's Response: The subject residence was approved in 1983 prior
to the adoption of the current floor area standards. In addition,
the average slope of the adjacent property is less than 10 percent
which exempts it from the slope adjustment requirement.
The majority of the Commissioners felt that the applicants should have
taken into consideration the requirement for a garage and their desire
for thicker walls earlier in the planning process. The Planning
Commission could not make the findings necessary to support the
applicants' Variance request.
Fiscal Impacts: None
Follow -up Actions: None
Ebrahimoun Appeal
DR -93 -030 & V -93 -026
January 81 1994
Page 3
Conseguences of Not Acting on Recommended Motions:
The applicants would be permitted to construct a house larger than
allowed by City Code.
Attachments:
1. Appeal letter
2. Resolutions DR -93 -030 & V -93 -026
3. Planning Commission minutes date 11 /22/93
4. Staff report dated 11/22/93
5. Plans, Exhibit "A"
Date Received: '7
Hearing Date:
Fee: 450
Receipt No.:
-- APPEAL APPLICATION
Name of Appellant: Jean Ebrahimoun
Address: 15170 El Camino Grande, Saratoga, CA 95070
Telephone:
Name of Applicant (if
different from Appellant:_
Project File Number and Address: 97_0615170 R1 Camino Grande
Decision Being Appealed: yes
Grounds for Appeal (letter may be attached):
i
See Attached
i
i
I
,*Appellant's Signature
*Please do not sign until application is presented at City offices. If you
wish specific people to be notified of this appeal, please list them on a
separate sheet.
THIS APPLICATION MUST BE SUBMITTED TO THE CITY CLERK, 13777 FRUITVALE
AVENUE, SARATOGA CA 95070, BY.5:00 P.M. WITHIN FIFTEEN ( 5) CALENDAR DAYS
OF THE DATE OF THE DECISION.
I
File No.
AUTHORIZATION FOR PUBLIC NOTICING
I Ig -a-n�i )a- as appellant on the above file, hereby
authorize Engir:eering.Data Services to perform the legal fioticing on the
above file.
.r\
Date: Y���'T -t i �� 1 % 3
Signature
December 7, 1993
Honorable Mayor and Members of the City Council
City of Saratoga
13777 Fruitvale Avenue
Saratoga, CA 95070
Subject: 15170 El Camino Grande
Variance V93 -026
Honorable Mayor and Members of the City Council:
The purpose of this letter is to appeal the Variance V93 -026 by the City. Planning
Commission, although the Staff and Planning Commission highly supported the
design of the home. The reasons we and our neighbors believe we should be granted
the variance are as follows.-
Years of study and planning went into our home as.preserving all our natural
surroundings were our major concerns. We decided to invest a considerably larger
amount of money to convert an otherwise, crawl space into. a two car, underground
garage rather than having a detached, two car garage. This decision saved us from
cutting any oaks and also, reduced bulk considerably. This additional square footage
of 224.5 square feet will NOT be perceived from the exterior elevation but will provide
us with an adequate garage we can comfortably park two cars.
With a home of this size we really need to take into consideration energy efficiency.
This 238.5 square feet will NOT allow us additional liveable square area but provide
enormous energy conservation in addition, to architecturally provide deep set
fenestration typically found in our chosed "Mediterranean" architectural style. We
should not be penalized for wanting to conserve energy!
The 18" we are requesting on our bedroom wing would allow us 126 square footage.
According to mathematics a 19.3 slope should be rounded to 19 instead of 20. As a
result we were penalized 78 square feet. Again, I can only elaborate our lot is unique
and this 18" will have no impact on bulk in our special circumstance.
I have enclosed information from our immediate neighbors whom were granted
additional square footage beyond what the city ordinances allowed on, a lot size less
than ours at 51,400 sq. ft.
Our secluded and unique parcel of land with the grove of redwoods and numerous,
manicured, mature oaks provides us isolation from everywhere. There is not another
lot in Saratoga hillside like ours. Our natural environment took precedence over all
our planning and design.
Direct contact was made with ALL our neighbors whom all favored the design along
with our moderate variance. This included more than 30 supportive neighbors.
We are extremely happy to finally be able to contribute to our neighborhood by
preservation of all our natural environment, by planting mor-3 trees. and making
Saratoga a more beautiful place to live.
Thank you for your time and consideration.
Yours truly,
David & Je`an Ebrahimoun
11*�
,y.
I i� 1iS) N!i7:bl:f2i '
OFFICE: Community Development 0W.W11• \►R,\►Jt►:It44
! -*W4 1 .'R..
�V•Ih., i wv•,r
April 14, 1983 v..,,..•,��...
Mr. Michael Elder
19208 Panorama Drive
Saratoga, CA 95070
RE: Tentative Building Site Approval SDR -153S and Design
Review A -862
Dear Mr. Elder:
At its meeting of April 13, 1983, the City of Saratoga Planning
Commission gave, consideration to your request for Tortativo
Building Site Approval and Design Review Approval to construct
a second -story addition to an existing single story structure
at 19208 Panorama Drive.
After careful review of this request, the Commission granted
approval to application SDR -:535 per the Staff Report JatoJ
February 6, 1983 and Exhibit "B ". The Commission also grant.eJ
approval to application A -862 per the Staff Report and Exhibits
"B" and "C ". Copies of the Staff Report and Resolutions
SDR- 1535 -1 and A -862 -1 are enclosed for your records.
These decisions arc subject to a 10•Jav (calendar) appeal porlod,
during which time you may appeal, and a 1S -d3y appeal perioJ
during which the City Council may appeal the decisions, The
Tentative Building Site Approval for SDR -lS3S is valid for •ightwoe.
(18) months. Before a buildin ermit can he issued Final A ror
of the ma must e o tame from the- 1tv r�-` i
the ouncil or inal Approval can a ma dc w cn have no the
Td
conditions established "by the Planning Commiss.lon�uora%honet th•
posted the necessary bond or cash deposit with the City o you Asly
that the conditions will be met. Y g�.tsote•
If you have any questions concerning this matter, ples.o Jo @jot
hesitate to contact our office.
Very truly you• s ,
`L
obert S. Shook
Director of Community Development
RSS:cd
Enclosures - cc:" Oscar Sohns, 2S3 klmendr2 Ave., Los "too, CA 9f13#
RESOLUTIdt �. A - A 6 : • 1
CITY OF SAR %t=% CQ'rIISSICI
STATZ-OF CALL OXNLIl
the City of Saratoga Planning CaCaission has rweivW an aR►iltalleM
:..for Design Review Approval of a second .torn .0,11 t (an to ,� o• .� � � �
story -structure at 19208 Panorama Drive (near l'in ('nl ina j (n t„� �
-1- zoning district `
MEREAS, the applicant (has) (k= =t) not the burdem of •
-support his said Pte- *�� �
application.,
M"' hIE UORE, BE TT RFSOL'M that after careful oonsiciatt;tion of &10 sit*
'-plan, architectural drnrings, landscape pleas and other exhibits suWttwi•Lc OW&J",
•- tion with this matter, the application of MICHAEL 1:1.111:8 •
-.for Design Review Approval be and the same is hereby (!,ranted
) (jsat0i,) MA)mCt tv
the following conditions:
I . I
Per Staff Report dated April G, 1.153 and I.x1jil1116 -p- ,ed ••r..
�pSSID AI ADOPTED by the City of Saratoga P2
anning Ccesai ss ion. Su w K
= California, this 13th day of April by Ow
follo• -•ing roll call vote:
AM: Commissioners hllava, Mc GoIdrick, Xelli%.
-NOES: None
.A>iSEN7: Commissioners Bolger and CI'Owther
1 :1t1, �•71t� s��M
7
creLlr) , aIL'i1:IL Q::LI115�1On
RESOLUTION NO.. DR -93 -030
CITY OF SARATOGA PLANNING COMMISSION
STATE OF CALIFORNIA
.Ebrahimoun; 15170 E1 Camino Grande
WHEREAS, the, City of Saratoga Planning Commission has received
an application for Design Review approval to construct a new 6,277
sq. ft. two -story home ar.d pool and demolish an existing residence;
and --
WHEREAS, the Planning Commission held a duly noticed public
hearing at which time all interested parties were given a full
opportunity to be heard and to present evidence; and
WHEREAS, the associated. Variance application to exceed the
allowable floor area was denied and the Design Review approved with
a condition that the floor area not exceed 5,685 sq. ft.; and
WHEREAS, the applicant has met the burden of proof required to
support said application, and the following findings have been
determined:
-The height, elevations and placement on the site of the proposed
main or accessory structure, when considered with reference to: (i)
the nature and location of residential structures on adjacent lots
and within the neighborhoods; and (ii) community view sheds will
avoid unreasonable interference with views and privacy, in that the
design of the proposed residence utilizes varied roof heights and
lines to minimize the building areas of maximum height and bulk.
-The natural landscape will be preserved insofar as practicable by
designing structures to follow the natural contours of the site and
minimizing tree and soil removal; grade changes will be minimized
and will be in keeping with the general appearance of neighboring
developed areas. and undeveloped areas, in that the applicant's are
providing replacement trees for the trees proposed to be removed
per the City Arborist's recommendation and the proposed grading
will not impact. any of the surrounding properties due to the
isolation of the subject property.
-The proposed main or accessory structure in relation to structures
on adjacent lots, and to the surrounding region, will minimize the
perception of excessive bulk and will be integrated into the
natural environment, in that the design of this residence is well
massed and articulated to avoid the perception of excessive mass.
-The proposed main or accessory structure will be compatible in
terms of bulk and height with (i) existing residential structures
on adjacent lots and those within the immediate neighborhood and
within the same zoning district; and (ii) the natural environment;
and shall not (i) unreasonably impair the light and air of adjacent
properties nor (ii) unreasonably impair the ability of adjacent
DR -93 -030; 15170 E1 Camino Grande
properties to utilize solar energy, in that the areas of maximum
roof height ate' limited. and ar-e- stepped back well in excess of the
minimum required setbacks and the structure is located a signifi-
cant distance from the nearest adjacent residence.
-The proposed site development or grading plan incorporates current
grading and erosion control standards used by the City.
-The proposed main or accessory structure will conform to each of
the applicable design policies and techniques set forth in the
Residential Design Handbook and as required by Section 15- 45.055.
-The proposed two -story residence is located within a neighborhood
where there is a predominance of two -story structures which
supports the request for an exception to the floor area reduction
requirement.
NOW, THEREFORE, the Planning Commission of the City of Saratoga
.does hereby resolve as follows:
Section 1. After careful consideration of the site plan,
architectural drawings, plans and other exhibits submitted in
connection with this matter, the application of EBRAHIMOUN for
Design Review approval be and the same is hereby granted subject to
the following conditions:
1. The development shall be located and designed as shown on
Exhibit "A ", incorporated by reference. Prior to issuance of
a Zoning Clearance, revised plans shall be submitted for
Community Development Director approval indicating that the
floor area has been reduced to no more than 5,685 sq.,ft. No
additional floor area shall be permitted unless a Variance
application is approved to do so.
2. Prior to submittal for building permit or grading permit, the
following shall be submitted to Planning Department staff in
order to issue a Zoning Clearance:
a. Three (3) sets of complete construction plans incorporat-
ing this Resolution as a separate plan page.
b. One (1) set of engineered grading and drainage plans
(including erosion control measures), also incorporating
this Resolution as a separate plan page.
C. All applicable requirements /conditions of the Resolution
(e.g. modifications to plans) and requirements/ conditions
of the City Arborist (e.g. tree protective fencing) shall
be noted on the plans.
DR -93 -030; 15170 El Camino Grande
3. No retaining wall shall have a height that. exceeds 5 ft.
measured from either the -existing natural grade or the finish
grade,. whichever is greater. In addition, no fence or wall
shall exceed six (6) feet in height and no fence or wall
located within any required front yard or within any required
exterior side yard of a reversed corner lot shall exceed three
(3) feet in height.
4. No structure shall be permitted in any easement.
5. No ordinance size tree shall be removed without first obtain-
ing a Tree Removal Permit except for tree #2, #12, #13, and
#18 as described in the City Arborist Report dated 8/31/93.
6. All requirements of the City Arborist's Report dated 8/31/93
shall be met. This includes, but is not limited to:
a. Provide supplemental. irrigation as described in the above
referenced report. Four weeks prior to the start of
grading all trees in the vicinity of construction shall
be irrigated weekly. Verification that this has been
completed shall be submitted to the Planning Department
prior to the issuance.of a grading permit.
b. Install chain link protective fencing around each tree
that is to be retained as described in the above
referenced report. Planning staff shall inspect all
fencing prior to the issuance of any permit.
C. Prior to zone clearance, the locations for trenching
required to install any utilities line shall be indicated
on the site plan. Trenching must be. planned to avoid
travelling beneath tree canopies.
d. Sub - surface fertilize on -site trees per the direction of
the City Arborist prior to the issuance of a zone
clearance.
e. Remove the paving surrounding tree #4 prior to. issuance
of a building permit. Verification that this has been
completed shall be submitted to the Planning Department.
f. Install pervious' paving in the area indicated on the City
Arborist's exhibit near tree #9 and #10. - This shall
consist of either interlocking pavers or bricks on gravel
and sand. Prior to zone clearance, this shall be
indicated on the site plan.
7. Prior to zone clearance, the applicant shall submit to the
City in a form acceptable to the Community Development
Director security in an amount of $6,500 pursuant to the City
DR -93 -030; 15170 E1 Camino Grande
Arborist's report. The security will be released to the
applicant once construction is completed and a final
inspection by the City Arborist has been conducted and it is
determined that the protective procedures outlined in the
Arborist report and the above conditions have been followed.
8. Landscapinq per the Landscape Plan in Exhibit A and irrigation
shall be installed prior to final occupancy.
9. All driveways have a 14 ft. minimum width plus one ft.
shoulders.
10. Provide automatic fire sprinkler protection throughout per the
Uniform Fire Code and Central Fire District's requirements.
11. Early Warning Fire Alarm System shall be installed and
maintained in accordance with the provisions of Article 16 -60
City of Saratoga.
12. Early Warning Fire Alarm System shall have documentation
relative to the proposed installation and shall be submitted
to the Fire District for approval, prior to issuance of a
building permit.
13. Driveways: All driveways have a 14 ft. minimum width plus one
ft. shoulders.
a. Slopes from 114; to 15% shall b surfaced using 2.5 inches
of A. C. or better on a 6 inch aggregate base from a
public street to the proposed dwelling.
b. Slopes from 15% to 17% shall be surfaced using a 4 inch
PCC concrete rough surfaces on a 4 inch aggregate base
from a public street to the proposed dwelling.
14. Applicant agrees to hold City harmless from all costs and
expenses, including attorney's fees, incurred by the City or
held to be the liability of City in connection with City's
defense of its actions in any proceeding brought in any State
or Federal Court, challenging the City's action with respect
to the applicant's project.
15. Noncompliance with any of the conditions of this permit shall
constitute a violation of. the permit. Because it is impossi-
ble to estimate damages the City. could incur due to the
violation, liquidated damages of $250 shall be payable.to this
City per each day of the violation.
Section 2: Applicant shall sign the agreement to these`
conditions within 30 days of the passage of this resolution or said
resolution shall be void.
DR -93 -030; 15170 El Camino Grande
Section 3. Construction must be commenced within 24 months or
approval will expire. --
Section 4. All applicable requirements of the State, County,
City and other Governmental entities must be met.
Section S. The applicant sbet1l affix a copy of this re .olution
to each bet of construction plans which will be submitted to the
Building Division when applying for a building permit.
Section 6. Unless appealed pursuant to the requirements of
Article 15 -90 of the. Saratoga City Code, this Resolution shall
become effective fifteen (15) days from the date of adoption.
PASSED AND ADOPTED by the City of Saratoga Planning Commis-
sion, State of California, this 22nd day of November, 1993 by the
following roll call vote:
AYES: Asfour, Caldwell, Jacobs, Kaplan & Wolfe
NOES: None
ABSENT:
ABSTAIN: Moran & Murakami
Chairperson, lannin Commission
ATTEST:
Secretary, Planning Commission
The foregoing conditions are hereby accepted.
Signature of Applicant Date
RESOLUTION NO. V-93 -026
CITY OF SARATOGA PLANNING COMMISSION
STATE OF CALIFORNIA
Ebrahimoun; 15170 El Camino Grande
WHEREAS, the City of Saratoga Planning Commission has received
an application for the Variance approval to allow the proposed
residence to exceed the site's maximum allowable floor area of
5,688 squara feet. by '589 square feet.
WHEREAS, the Planning Commission has conducted a duly noticed
public hearing at which time all interested parties were given a
full opportunity to be heard and to present evidence; and
WHEREAS, the applicant has not met the burden of proof
required to support his said application, and the Planning
Commission makes the following findings:
(a) Special circumstances applicable to the property,
including size, shape, topography, location or surroundings do not
exist which would deprive the applicant of privileges enjoyed by
the owners of other properties in the vicinity and classified in
the same zoning district in that the applicant's own desire to
build a larger house then permitted does not constitute a special
circumstance.
(b) That the granting of the variance would constitute a
grant of special privilege inconsistent with the limitations on
other properties in the vicinity and classified in the same zoning
district in that no special physical circumstances exist applicable
to the property to support a Variance and the floor area formula
specifically takes into account the size and topography of each
parcel.
NOW, THEREFORE, the Planning Commission of the City of
Saratoga does hereby resolve as. follows:
Section 1. After careful consideration of the site plan,
architectural drawings, plans and other exhibits submitted in
connection with this matter, the application of Ebrahimoun for
Variance approval be and the same is hereby denied.
Section 2. Unless appealed pursuant to the requirements of
Article 15 -90 of the Saratoga City Code, this resolution shall
become effective fifteen (15) days from the date of adoption.
PASSED AND ADOPTED by the City of Saratoga Planning Commis-
sion, State of California, this 22nd day of November, 1993 by the
following vote
AYES: Commissioners Asfour, Caldwell, Jacobs and Kaplan
File No. V -93 -026; 15170 E1 Camino Grande
NOES: Commissioner Wolfe
ABSENT: Commissioner Moran and Mur
Chairpe on, Planning Commission
ATTEST:
Secretary, Planning Commission
Planning Commission Minutes
Meeting of November 22, 1993
Page 5
JACOBS /CALDWELL MOVED TO CLOSE THE PUBLIC HEARING AT 7:49 P.M.
PASSED 5-0. `
JACOBS /KAPLAN MOVED TO APPROVE DR- 93-006 PER THE
RECOMMENDATIONS OF THE STAFF REPORT INCLUDING THE NEWLY ADDED
CONDITION #8.
Commissioner Caldwell explained that even though she was not present for the
August 11, 1993, review of this project, she had reviewed the initial staff report, visited
the site, reviewed the minutes of the last public hearing and is prepared to vote on the
application.
Chairperson Asfour thanked the applicant and architect for following the direction, of
the Commission during the last review of the project.
THE MOTION PASSED 5-0.
mom
3. DR-93-030'- Ebrahimoun; 15170 Ell Camino Grande, request for
V -93 -026 - Design Review approval to construct a new two-
story 6,277 sq. ft. residence. and a swimming pool per Chapter 15
of the City Code. The existing residence is proposed to be
demolished. Variance approval is also requested to allow the
proposed residence to exceed the site's maximum allowable floor
area of 5,688 sq. ft. by 589 sq. ft. The subject property is
approximately 51,400 sq. ft. and is located in an R -1- 40,000 zone
district (cont. from 11/10/93 at the applicant's request; application
expires 3/29/94).
Planner Walgren presented the Report dated November 22, 1993, and answered
questions with regard to the project.
ACTING CHAIRPERSON ASFOUR OPENED THE PUBLIC HEARING AT 7:52 P.M.
Gene Zambetti, representing the applicant, stated that the applicant had -not yet arrived
and asked if the Commission could move on to the next application and then come.
back to this application when the applicant arrives.
At this time the applicant arrived and Mr. Zambetti was requested to proceed with his
.presentation.
Planning Commission Minutes
Meeting of November 22, 1993
Page 6
Gene Zambetti, representing the applicant, spoke in favor of the application. He
submitted pictures of the subject lot and used a transparency to aid in his,
presentation. Mr. Zambetti explained that the lot has a 19.3% slope,, but when
calculating the allowable floor area the code requires the slope of the lot to be
rounded u�) to 20 %. He explained that floor area was lost due to this code
requirement and presents the applicant with an undue hardship. He stated that there
are other homes in the area built on a sloping lot and exceeding the allowable floor
area. Mr. Zambetti explained that the structure would have 12 inch walls opposed to
the standard 6 -inch walls. He stated that the floor area calculation is taken from the
outside of the walls and not from the inside. He stated that this also reduces the floor
area and that the thickness of.the walls takes up some of this allowable floor area. He
noted that the neighbors are in support of this project and have written letters
expressing their support and the absence of any concern with regard to potential
impacts of the project on their properties. He also stated that the neighbors do not
feel that granting'the variance would be a granting of a special privilege. Mr. Zambetti
explained that the lot is well screened and is unique because of its slope and because
of the location of the proposed home (on the lot) due to the existing gorge on the
property. He discussed the placement of the garage in the basement and other
architectural /design features of the proposed home. He urged the Commission to
approve the project and answered questions from the Commission with regard to the
project.
Planner Walgren, in response to questions from the Commission, explained. that the.
requirement to round -up the slope percentage was consistent with the code
requirement. implemented in 1987. He also explained that the square footage of the
garage is required by code to be counted.in with the allowable floor area. He stated
that all applicants are subject to this regulation.
Planner. Walgren stated that another letter was received this evening from Mr. and Mrs.
Comport supporting the applicant's request.
Jean Ebrahimoun, applicant, spoke in favor of the applications. She stated that the
design process has taken three times as long as expected. She explained that they
had many issues to address such as bulk and that the garage was purposely placed
underground to lessen any perception of bulk. She stated that she and her family
were interested in maintaining a one story home and retaining much of the existing
vegetation. With regard to the extra thick walls, she explained that these were chosen
for their energy- efficiency. She stated that she feels the lot is unique and noted that
the neighbors are in support of the project.
Dave Ebrahimoun, applicant, urged the Commission to approve the applications. He
explained that many different options /design were looked at and, in consideration of
the City codes and the needs of his family, the design proposed is
Planning Commission Minutes
Meeting of November 22, 1993
Page 7
the one which best meets these needs and is within the spirit of the code. He
explained that much effort had been spent on trying to minimize mass and bulk. He
explained that due to the requirement to round the slope of the lot up to 20% he is
penalized. He stated that because of this r -.quirement, he would be forced to reduce
the size of the master bedroom and reduce the thickness of the walls. He stated that
he feels the lot is unique and that the variance would not adversely impact anyone in
the vicinity.
Maurice Camargo, project architect, 3953 Yellow Drive, stated that in designing the
proposed structure he tried to balance the owners wishes while working with the City
codes. He explained that he had tried to design a suitable home without the need for
a variance, but because of the uniqueness of the lot was unsuccessful. He discussed
various features such as the thickness of the walls, the proposed square footage, and
the underground garage. He explained that originally the house was designed with
only a carport,but due to the City's requirements for two fully enclosed parking areas
the applicant was forced to add a garage. He explained that the garage was added
underground. He again urged the Commission to approve the applications and
stated that the lot is fairly isolated and the granting of the variance would not impact
other residents in the area. Mr. Camargo also answered questions from the
Commission.
Ann Bogan, 12228 Morelia Drive, stated that she is a local real estate agent and spoke
in favor of the application claiming that the new structure would enhance the area.
She stated that the easement would not be visible to anyone in the area.
Gene Zambetti, stated that all the neighbors were in support of the application and
that the granting of the variance would not grant the applicants a special privilege.
There was no one else wishing to speak.
CALDWELL /KAPLAN .MOVED TO CLOSE THE PUBLIC HEARING AT 8:23 P.M.
PASSED 5 -0.
Commissioner Caldwell verified that there was no easement on the subject property.
Planner Walgren stated that there was no easement on the property which effects the
proposal.
Planning Commission Minutes
Meeting of November 22, 1993
Page 8
Commissioner Caldwell noted that the Commissioners had been given some written
information (the same diagrams /transparencies presented by Mr. Zambetti during his
presentation) when they had visited the site earlier in the. day. She asked if
Commissioner Jacobs had also been given this information.
Commissioner Jacobs thanked Commissioner Caldwell and stated that he had visited
the site on his own and had indeed received the written information.
Commissioner Caldwell stated that she felt, staff did an excellent job on the staff report
and that she agrees with staff's recommendation. She stated that she could not make
the variance findings. She stated that the applicants should have taken into
consideration the requirement for a garage and their desire for thicker walls earlier in
the planning process. She stated that'she could find no special circumstance that
would warrant the need for a variance. She stated that she would not be voting in
favor of the applications.
Commissioner Wolfe stated that he was impressed by the out pour of letters from the
neighbors in support of this application. He noted that the neighbors found nothing
wrong with the design. He stated that the fact that the house was designed.with
energy saving walls is environmentally conscious and saves energy. He stated that
the variance is no more than about 5% of what would be allowed on the property
when the "peculiar" calculation (of the slope and floor area) is not taken into
consideration. He stated that he found the design acceptable and the variance
request reasonable.
WOLFE MOVED TO DIRECT STAFF TO DRAFT A RESOLUTION FOR APPROVAL
OF DR -93 -030 AND V -93 -026 AS PROPOSED.
COMMISSIONER JACOBS SECONDED THE MOTION SO THE ISSUE COULD BE
BROUGHT TO A VOTE.
Acting Chairperson Asfour stated that he would like to continue discussions on the
application before voting. He explained that a vote could be taken at this point or
discussions could continue and Commissioner Jacobs could withdraw his second so
the motion would die for lack of a second.
COMMISSIONER JACOBS WITHDREW HIS SECOND. THE MOTION DIED FOR
LACK OF A SECOND.
Commissioner Jacobs stated that on one hand he is in agreement with Commissioner
Wolfe - he feels the design is an excellent design. Commissioner Jacobs explained
that although he liked the design, he could not support the
Planning Commission Minutes
Meeting of November 22, 1993
Page 9
variance because he could not make the findings. Commissioner Jacobs stated that
he did not feel that the square footage allowed for this lot deprives the applicants of
enjoyment of the lot. He read the required variance findings aloud and stated that the
site would be an empty site and he does not find any physical constraints that would
force the applicant to build a. house which exceeds the -allowable � floor area. He
explained that there is nothing topographical about the lot itself which warrants a
variance. He explained that if the variance was granted based on -the fact that the
design is nice and because everyone likes it, the Planning Commission would be
violating the code. He stated that he feels he has no choice but to vote against it.
Commissioner Kaplan stated that she seconded the comments made by
Commissioner Jacobs.
Acting Chairperson Asfour commended the applicants and the architect on the design.
He stated that even though the design is excellent, it does not change the
requirements of the code. He stated that the applicants should have taken into
consideration the special design features (thicker walls and etc.) earlier in the planning
process. He stated that he could not make the necessary findings and therefore
would not be supporting the applications.
KAPLAN /CALDWELL MOVED TO ADOPT RESOLUTION DR -93 -030 TO DENY THE
APPLICATION. PASSED 4 -1 (WOLFE OPPOSED).
Commissioner Caldwell asked about a motion regarding the variance application.
Acting Chairperson Asfour stated that he thought the applications were to be voted on
together.
KAPLAN /CALDWELL AMENDED THEIR MOTION (ABOVE) TO INCLUDE BOTH
DR -93 -030 AND V -93 -026 - ADOPTION OF RESOLUTIONS DR -93 -030 AND V -93-
.026 FOR DENIAL. THE VOTE WAS THEN RETAKEN AND PASSED 4 -1 (WOLFE
OPPOSED).
Mr. Zambetti asked about the time line for resubmitting plans for another design
review.
Commissioner Caldwell stated that it is her recommendation that the denial be without
prejudice.
Planning Commission Minutes
Meeting of November 22, 1993
Page 10
COMMISSIONER KAPLAN INDICATED THAT A DENIAL OF THE DESIGN REVIEW
APPLICATION WAS ACCEPTABLE TO HER. COMMISSIONER CALDWELL, AS
SECONDER OF THE MOTION, STATED THAT DENIAL WITHOUT PREJUDICE.
WOULD ALSO BE HER PREFERENCE. THE OTHER COMMISSIONERS FOUND
THIS TO BE ACCEPTABLE.
4. V -93 -023 - Orin; 13770 Beaumont Dr., request for Variance approval to
allow a six foot high fence to be constructed on top of a two foot
high retaining wall, effectively creating an eight foot tall fence.
Chapter 15 of the City Code limits fences and walls to six feet in
maximum height. The subject property is approximately 12,000
sq. ft. and is located within an R -1- 10,000 zone district.
Planner Walgren presented the Report dated November 22, 1993. Planner Walgren
announced that staff had received a letter from the adjoining property owner to the
south requesting that the hearing on this issue be continued until the first meeting of
December so that the neighboring property owner can be present. Planner Walgren
explained that the applicant had been informed of this request. Planner Walgren
explained that the Planning Commission could either open the public hearing, take
testimony and act on the application or open the public hearing, take testimony and
then continue action on the item until the 1st meeting in December when the adjoining
property owner can be present. Planner Walgren also answered questions from the
Commission with regard to the application.
Acting Chairperson Asfour and Commissioners Kaplan and Wolfe expressed a desire
to proceed with the application and resolve the issue at the current meeting. Acting
Chairperson Asfour and Commissioner Kaplan stated that they felt that the adjoining
property owner(s) had been given enough time to at least submit a written detail
expressing their concerns.
Commissioners Jacobs and Caldwell expressed their preference to continue the
application to the 1st Planning Commission meeting in December so that the adjoining
property owner could be present.
THE PUBLIC HEARING WAS OPENED AT 8:40 P.M. BY ACTING CHAIRPERSON
ASFOUR:
Planning Commission Minutes
Meeting of November 22, 1993
Page 15
Commissioner Caldwell stated that she would check with the City Attorney with regard
to the use of the language she suggested (and used on two of the variance approvals)
therefore, pending the City Attorneys opinion on the use of this language there may
not need to be a discussion at a worksession. Commissioner Caldwell stated that if
the City Attorney agrees that this language should be ussd,- the _language car. - simply
be incorporated into the standard "boiler plate" language used when approving
variances. The Commission agreed with Commissioner Caldwell's suggestion.
COMMUNICATIONS
Written
1. Notices for the 12/8/93 public hearing
Oral
Gene Zambetti, 14510 Big Basin Way, representing the Ebrahimouns, applicants - DR-
93 -030 and V- 93 -026, stated that in talking with the applicants, they expressed a desire
to take their original plans that were previously placed on the consent calendar (prior
to making the modifications which were reviewed earlier in the evening) and moving
those plans through the process. He asked if this evening's denial without prejudice
would allow the applicants to take the original plans back through the process without
having to re -pay the application fee.
Planner Walgren explained that. technically the denial closed out the original application
and therefore a new application would need to be made and another application fee
would need to be paid.
Commissioner Caldwell asked if the Planning Commission could re- consider
applications at the q3MXneeting at which the application had ' originally been voted
on.
Planner Walgren stated that he thought that re- consideration could only take place
when there is a tied vote. He stated that he would look at the code to make sure his.
understanding was correct.
Commissioner Caldwell stated that if the applicant wishes to have the Commission
review the design (as it was prior to {Waking the modifications which required the
variance), she feels that it would be within the Planning Commission's capacity to
approve the design review with the condition that it conform to the original design or
that the applicants remove the three elements that require the variance.
Planning Commission Minutes
Meeting of November 22, 1993
Page 16
She stated that a reconsideration would be a simple matter instead of having the
applicant re- submit the same design, re -pay an application fee, and then wait until the
new application can come up on the Planning Commission agenda.
Commissioner Kaplan expressed agreement with the comments made by
Commissioner Caldwell.
Acting Chairperson Asfour stated that he did not know whether the Planning
Commission could re- consider the item.
Planner Walgren suggested that the Commission take a brief break to allow him time
to check the Code to see if the Commission could re- consider the action taken.
AT 9:07 P.M. ACTING CHAIRPERSON ASFOUR RECESSED THE MEETING. THE
MEETING WAS THEN RECONVENED AT 9:14 P.M.
CALDWELL / KAPLAN MOVED TO RECONSIDER THE VOTE TAKEN ON DR -93-
030 AND V -93 -026. PASSED 5 -0.
KAPLAN /JACOBS MOVED TO ADOPT RESOLUTION V -93 -026 (DENIAL OF
VARIANCE REQUEST) PASSED 4 -1 (WOLFE OPPOSED).
ASFOUR / KAPLAN MOVED TO APPROVE DR -93 -030 WITH THE CONDITION
THAT THE DESIGN BE MODIFIED TO MEET THE CITY REQUIREMENTS AND
ELIMINATE THE NEED FOR A VARIANCE, BUT THAT THE NEW DESIGN BE IN
SUBSTANTIAL CONFORMANCE TO THE DESIGN PRESENTED THIS EVENING.
THE MOTION PASSED 5 -0.
Planner Walgren asked if the Design Review Resolution was being adopted based on
the design review findings that were expressed during the original discussion in
support of the design.
Commissioner. Caldwell explained that the Design Review Resolution was indeed being
adopted based on the design review findings expressed during the original discussion
in support of-the design and on the findings made in the staff report.
Commissioner Caldwell explained that normally the Planning Commission would move
to direct staff to draft a resolution for approval of the design review application and
that resolution would then come back before the Planning Commission at the next
public hearing on the consent calendar.
Planning, Commission Minutes
Meeting of November 22, 1993
Page 17
Planner Walgren stated that he felt that the Commission should take this action
(explained by Commission Caldwell above) instead of trying to provide language to
make all the necessary findings this evening.
AS�OUR /KAPLAN MODIFIED THE MOTION AS FOLLOWS: THAT THE PLANNING
COMMISSION DIRECT STAFF TO DRAFT A RESOLUTION TO BE PLACED ON
THE DECEMBER 8, 1993 CONSENT CALENDAR TO APPROVE DR -93 -030 WITH
THE CONDITIONS THAT THE DESIGN BE MODIFIED IN R A WAY WHEREAS TO
A VARIANCE AND
MEET THE CITY CODES AND ELIMINATE THE NEED FOR
STILL BE IN SUBSTANTIAL CONFORMANCE TO THE DESIGN PRESENTED THIS
EVENING.. THE MOTION PASSED 5 -0.
COMMUNICATIONS (continued)
City -Council
ADJOURNMENT
At 9:20 p.m., Acting Chairperson Asfour adjourned the meeting to 7:30 p.m. on
December 7, 1993, in the Senior Day Care Center, 19655 Allendale Ave., Saratoga,
CA.
Andrea ' M. Chelemengos
Minutes Clerk.
Planning Commission Minutes
Meeting of December 8, 1993
Page 2
ORAL COMMUNICATIONS
T'iere was no one wishing to speak.
REPORT OF POSTING AGENDA
Pursuant to Government Code 54954.2, the agenda for this meeting was properly
posted on December 3, 1993.
TECHNICAL CORRECTIONS TO PACKET
There were two technical corrections.
Planner Walgren announced that staff had removed Item #1 from the Consent
Calendar and placed it. under the Public Hearing section for discussion.
With regard to Item #2, Planner Walgren explained that a draft arborist report had
been sent out with the packet and that the final arborist report has been distributed
(this evening) to the Commissioners for reference. He noted that there were no
substantive changes from the draft report to the final report.
PUBLIC HEARING CONSENT CALENDAR
As announced previously Item #1 was moved to the Public Hearing section for
discussion.
PUBLIC HEARINGS
1. DR -93 -030 - Ebrahimoun; 15170 El Camino Grande, request for Design
Review approval to construct a new two -story 5,685 sq. ft.
residence and a swimming pool per Chapter 15 of the City Code.
The existing residence is proposed to be demolished. The
subject property is approximately 51,400 sq. ft. and is located in
an R -1- 40,000 zone district (cont. from 11/22/93 to revise the
plans and prepare and adopt an approval Resolution; application
expires 3/29/94).
--------------------------------------------------------------
Community Development Director Curtis explained that at the November 22, 1993,
Planning Commission meeting the Commission denied the variance application (V-
Planning Commission Minutes
Meeting of December 8, 1993
Page 3
93 -026) that was filed along with this design review application. He further explained
that the Commission had directed staff to prepare a Resolution for approval of the
design review application with the condition that the design be modified to conform
with the requirements of the code. Director Curtis explained that since that meeting,
the applicant has decic'ed to proceed with the plans for the larger house (for which a
variance is need) and has appealed the variance denial. Director Curtis explained that
the design review and the variance .application are essentially tied together. He
explained that procedurally, because of the applicants desire to pursue approval for
the larger house, staff recommends that the Commission adopt a resolution for denial
of the design review application. Director Curtis further explained that a denial would
allow the applicant to appeal the decisions made on both applications and, thus, the
two applications could be kept together as a package.
Commissioner Jacobs stated that at the November 22, 1993 meeting, the Commission
had approved the design review application with the condition that the plans be
modified to meet the relative codes. He further explained that the applicants had
expressed a desire to modify the plans to meet code so the design plans could be
approved. Commissioner Jacobs stated that the Commission then re- considered the
original motion to deny the design review and as a result of the applicant's testimony
that they would modify the plans to.eliminate the need for a variance the Commission
then approved the design review.
Community Development Director Curtis stated that he understood that the application
was continued to tonight's meeting where the Planning - Commission would act on the
resolution to approve the design review with the condition that the plans be modified
to meet the code.
There was discussion among the Commission and the staff with regard to the
Commission's action on this item at the November 22, 1993 Planning Commission
meeting. There was consensus among the Commissioners that a decision had been
made at the November 22, 1993, meeting to approve the' design with modifications to
the plans which would eliminate the need for the variance. The commission also
agreed that this action was taken per the applicant's expressed desire to modify the
plans so they could be approved and so the applicants could proceed with the
project. The Commissioners referred to the minutes (Specifically Pages 15, 16 and 17)
of the November 22 meeting and explained that they had unanimously approved (5 -0)
the design (with the condition that the plans be modified to eliminate the need for a
variance). They (the Commissioners) stated that the application had not been
continued, but that staff had been directed to prepare an appropriately worded
resolution to be placed on the December 8th Planning Commission Consent calendar
and that it was the language of the
resolution that was to be reviewed and approved - the decision to approve the design
had been made on November 22, 1993.
Planning Commission Minutes
Meeting of December 8, 1993
Page 4
There was further discussion and question from the Commission with regard to
procedural matters. The Commissioners maintained that at the November 22, 19.93
Planning Commission meeting, the applicant had offered to modify the plans to
eliminate the need for a variance, requested the Commission to re- consider the
original motion to deny the design application, and urged the Commission to move for
approval of the design review application with a condition that the plans be modified to
meet the code. Commissioner Caldwell stated that she did not feel as if the
Commission should have to reverse their decision because the applicants had since
that time changed their mind about modifying the plans. She (Commissioner Caldwell)
stated that the applicant could just as easily appeal the conditional approval of the
design review application as they could a design review denial.
Community Development Director Curtis agreed with Commissioner Caldwell with
regard to the applicants' ability to appeal the design review approval. He explained
the staff had misunderstood the actions that took place at the November 22, 1993
Planning Commission meeting. He noted that the date on the resolution for approval
(of a 5,685 square foot house) would need to be changed to November 22, 1993 and,
that staff and the applicant could meet the next day to add the design review approval
to the appeal.
Chairperson Moran noted that she had been absent on November 22, 1993, but that
her understanding of the action and interpretation of the minutes concurred with the
explanation of events offered (above) by the Commissioners. She stated that she
would be abstaining from voting on this matter, but that she understands that the vote
would be just an affirmation of the action taken at the November 22, 1993 meeting to
adopt a resolution for approval of the design for a 5,685 square, foot house.
At this point the applicant was allowed to address the Commission.
Gene Zambetti, 14510 Big Basin Way,, representing the applicant, stated that the
applicants agree with Director Curtis with regard to having the Commission re- confirm
approval of the smaller house plan so the applicants can have the opportunity to
appeal the application to the City Council along with the variance application.
Commissioner Asfour explained to Mr. Zambetti that the Planning Commission was
under the understanding that it was the applicants' desire to modify the plans to
eliminate the variance and. that the applicants were receptive to the necessary
modifications,. which they offered to make, and would not pursue an appeal. He
stated that if the Commission had known that the applicants intended on ,appealing the
approval of the modified design, the Commission would not have re- considered the
original motion and would have left the design denial in place.
Planning Commission Minutes
Meeting of December 8, 1993
Page 5
Gene Zambetti stated that when he had asked for the separation, it was his
understanding that the applicant was not going to appeal the decision and that
construction of the house would then proceed. He thanked the staff for the amount
time spent on clarification of this issue.
Commissioner Wolfe commended staff for the time spent and the work done on this
application and apologized for any confusion with regard to the Planning Commissions
actions.
Mr. Ebrahimoun, applicant, thanked the staff and the Commission for the time spent
on this application and explained that after further consideration it was clear that a
larger house was needed. He stated that if the Commission had no problems with the
larger house. then an approval should be granted tonight.
Director Curtis stated that the Commission really did not need to vote on the resolution
because the resolution had actually been adopted on November 22, 1993. He
explained that all that was really needed was a concurrence that the resolution is
correct.
Commissioner Caldwell pointed out that the Council takes this type of opportunity to
have another vote on the issue.
Their was brief discussion with regard to whether the Commission should or should
not vote again on this issue. Director Curtis stated that the Commission could take a
vote that this resolution reflects the Commission's decision.
ASFOUR /JACOBS MOVED TO APPROVE RESOLUTION DR -93 -030.
Commissioner Kaplan inquired if items /conditions 9 and 13 are the same.
Planner Walgren stated that the two conditions are basically the same except that
Condition 13 provides for more detail.
Chairperson Moran suggested that the two Conditions be left in for now and that the
duplicate condition (if it appears) could be removed from the next application.
THE MOTION PASSED 5 -0 -2 (MORAN AND MURAKAMI ABSTAINED).
I
d cn
;w-
z:P:,:
b
b
b
A
A
�
ko
09<
°a
(D
ct
s
z
c,
5
1
o
OD
r
R
�.
N
p
W
e+�
.
b
0
m
rt
W
O
p
H
~
to
m
m
to
`A,
rt
H
:3:
a
c
,
O
�r
z
w
N•
o
LA)
x
a
o
C
Lo .
L
Z
o
N
01
P..q
y
I-'
Ml
•
Ln
I-�
n
J
O
I-'
P--4
cn
't7 .
n
a
c
O
e
�J
o
Z
(7)
a
w
m
File No. DR -93 -030 V -93 -026; 15170 El Camino Grande
EXECUTIVE SUIIIaRY
CASE HISTORY:
Application filed:
08/17/93
Application complete:
09/29/93
Notice published:
11/10/93
Mailing completed:
11/11/93
Posting completed:
11/04/93
PROJECT DESCRIPTION:
Request for Design Review approval to construct a new 6,277 square
foot two -story residence and a swimming pool per Chapter 15 of the
City Code. The existing residence is proposed to be demolished.
Variance approval is also requested to allow the proposed residence
to.,exceed the .site's maximum allowable floor area of 5,688 sq. ft.
by 589 square feet. The property is approximately 51,400 square
feet and is located within the R -1- 40,000 zone district.
STAFF RECOMMENDATION:
Deny the Design Review and Variance requests by adopting Resolu-
tions DR -93 -030 and V -93 -026.
ATTACHMENTS:
1. Staff Analysis
2. Resolutions DR -93 -030 and V -93 -026
3. Correspondence
4. Arborist Report dated 8/31/93
5. Plans, Exhibit "A"
z
File No. DR -93 -030 & V -93 -026; 15170 El Camino Grande
STAFF ANALYSIS
ZONING: R -1- 40,000
GENERAL PLAN DESIGNATION: Residential Very Low Density (RVLD)
PARCEL SIZE: 1511400 sq. ft.
AVERAGE SITE SLOPE: 19.3%
GRADING REOUIRED:
CUT
FILL
House
307
cu.
yds.
0
cu.
yds.
Driveway
546
cu.
yds.
177
cu.
yds.
Landscape
233
cu.
yds.
508
cu.
yds.
TOTAL
1,086
cu.
yds.
685
cu.
yds.
Maximum Depth
7
ft.
(basement)
5
ft.
MATERIALS AND COLORS PROPOSED: Exterior plaster finish with a
clay tile roof and cast stone balustrades per the submitted
material board. The material board includes three different color
schemes all of which are acceptable to staff.
LENGTH OF STRUCTURE: 130 ft. (including the carport /terrace)
WIDTH OF STRUCTURE:
LOT COVERAGE:
HEIGHT:
SIZE OF
STRUCTURE:
55 ft.
Garage:
1st Floor:
2nd Floor:
TOTAL:
PROPOSAL
24% (12,379 s.f.)
26 ft.
576 sq. ft.
4,128 sq. ft.
1,573 sq. ft.
6,277 sq. ft.
CODE REQUIREMENT/
ALLOWANCE
30%
26 ft.
5,688 sq. ft.*
Basement: 1,391 sq. ft. (not included in floor area)
Carport: 880 sq. ft. (not included in floor area)
* This is the allowable floor if the exception to the floor area
reduction requirement for structures over 18 feet in height is
granted by the Planning Commission per Section 15- 45.030 of the
City Code.
File Rio. DR -93 -030 6 V -93 -026; 15170 El Camino Grande
PROPOSAL CODE REQUIREMENT/
.ALLOWANCE
SETBACKS: Front:
50
ft.
Front:
30
ft.
Rear:
33
ft.
Rear:
20
ft.
Exterior Side:
25
ft.
Exterior Side:
25
ft.
Interior Side:
115
ft.
Interior Side:
20
ft.
PROJECT DISCUSSION:
Site Characteristics: The subject property is located on El Camino
Grande at the corner of E1 Camino Senda. There is an existing
mediterranean style house on the property which is proposed to be
demolished. The site has a moderate slope downhill towards the
rear of the property.. There are several ordinance size trees on-
site as well as other mature vegetation. Due to the. site's
topography and the amount of existing vegetation the property is
well screened from surrounding properties.
Design Review: The applicants are requesting Design Review
approval to demolish an existing two -story home to construct a
larger two -story residence in its place. The proposed residence is
6,277 sq. ft. The design includes a full basement, a carport, and
several terraces which are not included in the floor area calcula-
tions.
Staff's initial review of the proposal revealed that the proposed
design satisfied the required Design Review findings in terms of
being.compatible with the neighborhood, minimizing the perception
of bulk and mass, and not impacting the views and /or privacy of
surrounding properties. The proposed design of the residence is
also consistent with the design policies and techniques outlined in
the Residential Design Handbook.
During the initial review of the project staff was concerned with
the following items:
Amount of grading proposed for the new driveway that
accesses.the carport and garage.
• Number of areas, such as the carport and patio terraces,
which contribute to the mass and bulk of the building,
but are exempt from the floor area calculations.
• Proposed removal of six trees.
However, after visiting the site and seeing the amount of mature
vegetation and the orientation of the property in relation to
surrounding properties, staff's concerns were minimized. In
File No. DR -93 -030 6 V -93 -026;
15170 B1 Camino Grande
addition, the City Arborist visited the site and evaluated all of
the significant trees. He stated that only two of the trees
proposed to be removed had a dollar value higher than zero and
recommended that six trees (two each of 36" box, 24" box, and 15
gallon) be planted to provide replacement value for the two trees
in good health. These replacement trees are included on the
proposed landscape plan. He also recommended the standard tree
preservation measures and a preservation bond for the existing
trees to remain.
VARIANCE REVIEW:
Background: Just prior to the previous public hearing, which this
item was scheduled for, the applicant submitted a request to
increase the proposed floor area to 6,277 which exceeds the
allowable floor area by 589 sq. ft. Therefore, the item was
continued and the applicant submitted the Variance fee and
application and the item was renoticed as a request for Variance
and Design Review approval. The applicant's reasons for the
additional square footage include the following (see the attached
letter) :
Desire to enlarge the garage by 225 square feet. The appli-
cant's do not feel this area should be counted as floor area
since it would not be visible from the exterior of the house.
However, the ordinance requires that all underground areas be
counted as floor area unless no portion of.the room is more
than two feet above the natural grade.
Increase all exterior walls with openings from 6 inches to .12
inches thick to complement the proposed "Mediterranean"
architectural style. This would require and additional 245
sq. ft. without impacting the proposed living space.
Add.18 inches to the bedroom wing of the house.
Variance Findings: These revisions did not significantly change
the appearance of the house. However, since these changes did make
the proposal. exceed the site's maximum allowable floor area, staff
cannot be supportive of these revisions and recommends denial of
the Variance based on the findings in Section 15- 70.060 of the City
Code.
No special circumstance applicable to the property exists
which would support the granting of a Variance to the maximum
permitted floor area.
Granting of the Variance would constitute a grant of special
privilege inconsistent with limitations on other properties in
File No. DR -93 -030 i V -93 -026; 15170 El Camino Grande
the vicinity and classified in the same zone district in that
the.formula for calculating the maximum permitted floor area
is based on the size and slope of each individual parcel.
Staff has encouraged the applicant to reduce the proposed floor
area, so that a Variance'would not be necessary.. The Variance
findings were explained to tt:e applicants and they were told that
staff would not support their request since the all of the Variance
findings could not be made.
Summary: Staff believes the Design Review findings can be made to
support the proposed residence. The project complies with all
applicable. zoning regulations with regard to allowable structure
height, required setbacks, grading and maximum permitted lot
coverage. However, since the Design Review approval is dependent
on the Variance application being approved, and the applicant has
not met the burden of proof required to support the Variance, staff
recommends denial of both the Design Review and Variance requests.
RECOMMENDATION:
Deny the Design Review and Variance requests by adopting Resolu-
tions DR -93 -030 and V -93 -026.
BARRIE D. C" kTE
and ASSOCIA'.
Horticultural Consultants
408- 353 -1052
23535 Summit Road., Los Gatos, CA 95030
TREE SURVEY AT THE EBRAHIMOUN PROPERTY
15170 EL CAMINO GRANDE
SARATOGA
On August 31, 1993, our firm surveyed the trees at the Ebrahimoun residence, 15170 El
Camino Grande, Saratoga. A new home is proposed to be constructed, to replace the existing
home which will be tom down.
Six trees are proposed to be removed. Four of these trees are in poor condition, and should be
removed. Only tree #6, a Spanish Fir, i s inp sapo, and tree #18, a Coast Live Oak, Quercus
rifoli , were given a dollar value higher than zero. The total value of these trees is
$3,750.00. The equivalent dollar value of nursery stock should be planted to replace it:
(2) 36" box trees
(2) 24" box trees
(2) 15 gallon trees
A tree protection bond in the amount of $6,500.00 is recommended (see enclosed worksheet).
All trees on site which were over 12 inches at two feet above grade, or 10 inches at 2 feet above
grade if a'Quercus species, and which will be affected by construction activities, were numbered
and tagged. Trunk locations were already located on the plot plan which was provided to us. The
species of each was identified, and D.B.H., height and spread were estimated. Health and
structure were rated. All of this information was recorded on the enclosed map and charts. In
addition, text was used for further clarification.
GENERAL COMMENTS
Irrigation Before and After Root Destruction
Any tree which has had excavation occur within its dripiine, or portions of its rootzone covered,
should be assumed to be stressed. This stress can be reduced by providing supplemental
irrigation to the rootzone which is still intact.
Irrigation is best provided using 'ooze" -type soaker hoses. They are easily available at
hardware suppliers such as Orchard Supply Hardware, and Home Depot. These hoses dribble
-1-
TREE SURVEY AT THE EHRAHIMOUN PROPERTY
15170 Et CAMINO GRANDE
SARATOGA
water into the ground, providing deep watering wherever they are laid down. Where the
rootzone is intact, the soaker hose should be placed at the dripline.. Where root destruction has
occurred, it should be placed over the cut ends of the roots. If left on over night, enough + later
should easily be provided to penetrate 24 inches deep. Depth of penetration should be checked
with a soil probe or shovel.
Starting four weeks before any grading will occur near the tree, it should be irrigated weekly to
a depth of 24 inches, using soaker hoses as described above. Monthly irrigations during the dry
season should occur until one year after construction is completed.
Fencing Rootzones During Construction
A temporary construction period fence should be erected around each tree which is to be
retained in the final landscape. This fence should be erected at the dripline of each tree. If
groves of trees, are to be protected, one common fence can be erected around the entire grove.
Where construction intrudes into rootzones, this fence should be erected 24 inches from the
limits of that construction. It should consist of portable cyclone fencing, or wire mesh securely
attached to metal posts driven into the ground. It should not be easy for construction workers to
move, or take down.
This fencing should be erected before any construction machinery enters the site, and should not
be removed until final landscape grading is completed.
It cannot be emphasized enough how important these fences are. From our experience, soil
compaction and trenching through rootzones are the number one causes of tree stress in the post
construction period. It should be explained clearly to all contractors and workers on site that
these fences are sacred. If for any reason it becomes necessary for any machinery to enter the
fenced -in rootzone of a tree, an International Society of Arboriculture Certified Arborist should
be consulted first.
Trenching of any sort must be planned to avoid traveling beneath tree canopies. This should
include planning.for P.G. &E., sewer lines, electrical power, cable T.V., and irrigation. Plans
should show specific locations of trenches, if possible.
No chemicals, solvents, paints, etc. should be dumped on site. No concrete residue should be
-2-
TREE SURVEY AT THE EBRAHIMOUN PROPERTY
15170 EL CAMINO GRANDE
SARATOGA
washed into the soil within 20 feet of a rootzone. All trash and debris should be removed from
the site, rather than dumped or buried where it might affect roots.
Fertllization
Where sub - surface fertilization has been recommended, it should occur between May and
September, 1993, unless otherwise stated. A solution of 4 Ibs of Romeo Fertilizer's Greenbelt
22 -14 -14 per 100 gallons of water should be injected at the rate of 10 gallons per inch of
diameter at breast height (DBH). This fertilizer provides slow - release nitrogen fertilization,
as well as trace elements such as iron, zinc, etc.
SPECIFIC TREES
Tree #1, Blue Oak, Quercus douglasit
This tree should be relatively undisturbed, assuming that this section of driveway is not
removed and replaced. It should receive supplemental irrigation and be fertilized as described
under "General Comments ", because of its low vigor.
Trees #2 & 3, Douglas Fir, Pseudotsu4a menziesil
These two trees have very sparse canopies, and are in poor health. They should be removed, to
lessen the competition with neighboring trees.
Tree #4, Blue Oak
This tree's trunk is surrounded by paving. The paving should be removed immediately around
the trunk, to a distance of 12 inches, and any fill soil which may have been placed against the
trunk should be removed carefully with hand tools.
Tree #5, Coast Live Oak, Duercus agrifolia
This is a large healthy tree in good condition. This tree should be relatively undisturbed,
assuming that this section of driveway is not removed and replaced..
Tree #6, Spanish. Fir, A i s - ginsapo
This is a mature specimen of this species. Unfortunately, specimens of this species are not very
attractive, not matching our expectations of what a coniferous tree should look like.
-3-
TREE SURVEY AT THE EBRAHIMOUN PROPERTY
15170 EL CAMINO GRANDE
SARATOGA
It has been proposed for removal. A dollar value has been placed on this tree on the enclosed
charts.
Tree #7, Valley Oak, Quercus flobata
This healthy tree Is growing to the west of the grove of Redwoods (see #8). It should be
relatively unaffected by construction activities.
Tree #8, Coast Redwood, Sequoia sempervirens
This grove of Redwoods will have minor impact on its rootzone on the east side. It should receive
supplemental irrigation as described under "General Comments."
Trees #9 &10, Coast Live Oak
Pervious paving should be installed in the area shown on the enclosed map, to reduce the root
destruction within the driplines of these two trees (see enclosed detail).
Where paving will cover more than 30% of the area within the dripline of a tree, it should be
composed of pervious paving within the dripline. This could consist of brick or interlocking
pavers on gravel and sand. The soil beneath the pervious paving should be compacted to no more
than 80% compaction.
Tree #11, Blue Oak
Approximately 25% of the area within the dripline of this tree will be covered with paving
when the driveway is constructed. This tree should receive supplemental irrigation.
Tree #12, Coast Live Oak
This tree is in fair health, and has a poor structure. It should be removed.
Tree #13, Incense Cedar, Calocedrus decurrens
This tree is in very poor health, and should be.removed. It has died back over the years as a
result of infection from Botryosphaeria fungi.
Tree #14, Coast Live Oak
This tree is in good condition. A retaining wall will be. installed on the west side of the tree. A
temporary construction period fence should be erected at the location shown on the enclosed
map.
10
TREE SURVEY AT THE EBRAHIMOUN PROPERTY
15170 EL CAMINO GRANDE
SARATOGA
Trees #15 & 16, Blue Oak
This tree is in good condition. A retaining wall will be installed on the west side of the tree. A
temporary construction period fence should be erected at the location shown on the enclosed
map.
Tree #17, Monterey Pine
This tree is in fair condition. It should receive supplemental irrigation, and be fertilized, as
described under "General Comments."
Tree #18, Coast Live Oak
This is a young Coast Live Oak, in good health, but with only a fair structure. It is proposed to
be removed. Its value has been assessed on the enclosed chart, and replacements have been
recommended under "General Comments."
Please call our office if you have further questions.
TEW:Ia
Enclosures: Pervious .Paving Detail
Evaluation Chart
Bond Chart
Map
-5-
Sincerely,
Terence E. Welch, Associate
Barrie D. Coate & Associates
BARRIE D. COATE & ASSOCIATES
Z
_
o
^
T
❑
�
�
>-
F-
5 a =$36.00
Horticultural Consultants
w
p
uv
*-
—
z
w
3
¢ ,;,
Q
,.
�n
z
w
❑
_,
H-
ac
w
O
¢
p
15- gal =$120
24box --$420
(408)353 -1052
w
w
to
m
¢
,-
w
¢
z
=
O
z
v
4
U
w
p
�,
LU
w
w¢
I-
Q
o
z
¢
a
36'box= $1,320
qu
c~n
G
w
F-
❑
V
N
w
w¢
�C
F-
Q cn
N
(n
y
z
48"box= $5.000
S
o
=
w
—
uaJ
¢
-r
a
❑
tY
❑
w
z�
F- w
O>
w
rn
w w
w.�
❑
w
❑
❑
w
❑
w
z
g�g
O o
U 1
o
2
z
52 box = $7,000
72 ' box= $151000
Key
Plant Name
o
p
O N_
v=
c~n
z
p
U
z
r¢¢
n¢.
COMMENTS
Sparse canopy.
20
28
45135
3
3
1
3
Leader removed
1
@ 3' above grad
sq.in X $27 sgAn = $ x sp. class O _ $ x cond Q = $ x loc O _
Final Value
r)rwtgla,q Fir
14
16
55204
3
1
11 X
2
sq.in X $27 sq/ln = $ x sp. class ( %) = $ x cond %) _ $ x loc ( 0/6) = 0
Final Value $
I
1 13
1 35
1 15
4
1 .3
1
1
X
3
sq.in X $27 sq/in = $ x sp. class () _ $ x cond 0 = $ x loc () = 0
Final Value $
Surrounded by
Rhip Oak
9
X
7
7
15
35
30
3
3
pavement.
4
sq.in X $27 sq.in = $ x sp. class ( %) _ $ x cond ( %) _ $ ._ !oC ( %)=$
Final Value $
22
28
40
55
1
1 2
5
sq.in X $27 sq /in = $ x sp. class ( %) _ $ x cond ( %) = $ x loc ( %)=$
Final Value $
10 I
I
I
1
12
1 40
12
2
1 2
6
sq.in 78 X $27 sq /in = $2,120 x sp. class ( 60 %) _ $1,272 x cond (70 %) _ $890.40 X1 04/b = b-JU.UU
Final Value $
JOB TITLE: Ebrahimoun/EI Camino Grande
JOB # 08- 93-277
DATE: 8/31/93
Sq. in. is determined with e formula
Sq. in= ( OW2sr
2
Page 1 of 4
1=bW 5--worst
Total Value
This Sheet= $890.00
BARRIE D. COATE & ASSOCIATES
►n
Z
�_
p
>
5- ga1�36.00
Horticultural Consultants
D
r
Z
w
o
rt u
Q
Z
`'
O
p
w
�=-
w
¢O
cc
15- gal =$120
24"box =$420
(408) 353 -1052
.-.
W
t
.-.
a
r?=
t11
z
z
W
T
--
U
pw
�
�-
r
3
O
O
W
w
I, -
Q
o
w J
�
a
a
36'90x=$1,320
41
t
0
En
c
w
x
D
a
2
I--
F-
v
►
cn
w
O W
U
�C
►-
¢ W
cn
3
tL
cn
m Q
>>
Q
0
z
48box= $5.000
1
F
v
Co
c
=
Co
>
�
ve
z
W cc
E
J
=
o:
to
z
>
0
cc
¢
I-- w
°�
z
U
W
z
U,4
W W
p
o
w
J
D
z
00
cr cc�
O
z
a
52 box--$7,000
7COMMENTS
Key
Plant Name
o
cn
U
U
z
VallAV Oak
20
22
35
30
2
2
7
sq.in X $27 sq/in = $ x sp. class () _ $ x cond () _ $ x loc () _
Final Value
14-
17/
135
20
1
1
a v. gr .
40,18,21,24,28
35
40
60
23,32,17 inches
8
sq.in X $27 sqf n = x sp. class ( %) _ $ x cond %) _ $ x loc ( %) _
(35,16,19,20,24,20,29,14 inches) Final Value $
11
13
25
22
2
1
9
sq.in X $27 sq/in = $ x sp. class () _ $ x cond Q = $ x loc () _
Final Value $
rn.q.qt 1. Oak
11
X
9
15
30
30
1
1
=clearance.
10
sq.in X $27 sgAn = $ x sp. class ( %) _ $ x cond ( %) _ $ x loc ( %)=$
Final Value $
alts present
19
X
14
30
45
50
3
2
n major limbs.
11
sq.in X $27 sglln = $ x sp. class ( %) _ $ x cond ( %) _ $ x loc ( %).$
Final Value $
15
17
22
20
3
4
4
X
12
sq.in X $27 sq/in = $ x sp. class ( %) _ $ x cond ( %) _ $ x loc
Final. Value $
JOB TITLE: Ebrahimoun Property /15170 El Camino Grande
JOB # 08 -93 -277
DATE: 8131/'93
Sq. in. is determined wnn the iormuia:
Sq. in = ( 12D 2a
2
Page 2 of 3
1=best 5—worst
Total Value
This Sheet=
BARRIE D. COATE & ASSOCIATES
Horticultural Consultants
(408)353-1052
41'
m
v
_
CO
w
v~i
F
D
.-.
m
_�
m
o
m
S
�-
o—
w
¢
w
>
Q
N
F-
=
U
w
z
o
Q
w
a
•-
-'
w
z
�n
w
cc
U
z
Z
z
i
~
to
w
z
c=.7
3
o
z;
w°
w
>
m
a¢
Q r
.,
°w
v Q
f- w
p p
U
Q
U
w
z
¢
I--
;
N
~
w
rn
z
,�,
z r
3 rn
a
U
w w
w cn
°
to
O
w
o
p
D
w
w
-Q
m
0
�,
I=-
+
cn
LU
z
W
F-
Q
to
z
p
z
a
g>
O
v
cc cc
p
c¢
a
s
>
O
2
cc
�
a
?
z
a
5- ga��36.00
15- gakS120
24box-$420
36box= $1,320
48bo $5,000
52' box=$7,000
72' box�15,000
COMMENTS
Key
Plant Name
20
21
5012014
3
X
Very tine
canopy.
13
sq.in X $27 sq/in = $ x sp. class O _ $ x cond p = $ x loc
Final Value
18
18
1151
25
1
1 1
14
sq.in X $27 sq/in = $ x sp. class ( %) _ $ x cond%) = $ x loc ( %) _
Final Value $
Rh ip Oak
14
1 X
6
1
24
1161
35
1
1
15
sq.in X $27 sgfin = $ x sp. class {) _ $ x cond 0 = $ x loc () _
Final Value $
1
1 1
15 1
16
20
1
1
113
16
sq.in X $27 sq /in = $ x sp. class ( %)=$ x cond ( %) = $ x loc
- Final Value $
ne-sided
18
20
50
30
3
2
2
4
canopy
17
sq.in X $27 sgAn = $ x sp. class ( %) _ $ x cond ( %) = $ x loc
Final Value $
15
15
15
20
1
3
18
sq.in 176 X $27 sgfin = $ 4,771 x sp. class (100%) = $4,771 x cond ( 60% %) = $2,862 x loc ( 100 %) _ $ 2,860
Final Value $
JOB TITLE: Ebrahimoun/15170 El Grande
JOB # 08-93 -277
DATE: 8131/93
sq. in. is determined with the formula:
Sq. in = ( pfl.Hl2ir
2
Page 3 of 3
1 west 5=worst
Total Value
This Sheet= $2,860
BARRIE D. COATE & ASSOCIATES ISA EVALUATION CITY OF 6ARATOGA .
Horticultural Consultants VALUE OF TREES WHICH WILL BE AFFECTED BY CONSTRUCTION
(408) 353 -1052 Adjustments
sq/ " Value per Basic
BH (7r, r2� sq. inch Value Species .Condition t.ocation Total
Key #
Genus/species/class
$27.00
1
Blue Oak
20
314
$27.00
$8,482
100%
40%
100%
$3,390
4
7/
7
102
$27.00
$2,754
100%
40%
100%
$1,100
5
Criag I ivp 02k
22
380
$27.00
$10,263
1000/0
800/0
100%
$8,210
g
11
95
$27.00
$2,565
1000/0
800/0
1000/o
$2,050
10
Coast I ive Oak
11/
9
126
$27.00
$3,423
100%
90%
100%
$3,080
11
Blue ak
19/
14
360
$27.00
$9,730
1000/0
500/0
100%
$4,865
.14
Coast Live Oak
18
254
$27.00
$6,870
1000/0
900/0
100%
$6,180
15
Sh ip nak
14
168
$27.00
$4,536
1000/0
900/0
100%
$4,080
JOB TITLE: Ebrahlmoun /15170 El Camino Grande
TOTAL VALUE THIS PAGE $32,955
JOB #: 09-93 -277
SUGGESTED BOND $6,500
DATE: 8131193
Pg1of 1
October 26, 1993
CITY OF SARATOGA
PLANNING COMMISSION
Attn. Lynette Dias, Assist. Planner
13777 Fruitvale Avenue
Saratoga, Ca. 95070
Re: Design Review 93 -030; 15170 El Camino Grande
Honorable Planning Commissioners,
We are formally requesting minor modification to our above submitted Design Review
application, as follows:
Enlarge underground garage from 19.5'x 19.0'( 351.5 sq. ft.) to 24.0' x 24.0'
(576.0 sq. ft. ) or add 224.5 sq. ft.
Add 6" to all exterior walls with openings which are now a nominal 6" wall in
order to have 12" thick exterior walls. This will require an additional 245 sq. ft.
Add 18" to the bedroom wing of the house to enlarge the rooms to our desired
size without compromising the other living areas of the house. This will require an
additional 126 sq. ft.
Our allowable square footage is 5688 sq. ft. and we are requiring an additional 595.5
square feet as per above or a total of 6283.5 sq. ft.
Please note that counting 12" thick walls as 6" walls will allow us to retain the living space
as designed, but architecturally will provide for deep set fenestration typically found in our
chosen "Mediterranean" architectural style.
In addition, we would also like to enlarge the underground garage without penalty of
deduction to living space square footage as proposed. Its enlargement will clearly not be
perceived in the exterior.
Please be also aware that we have lived in our Home in Saratoga for the last 13 years and
have planned to build this Home for the past 7 years. During this time the City Ordinances
have reduced the allowable square footage's. Our current submittal compromises the sizes
of the Master bedroom and bath as well as our children's bedrooms from our original
design.
Please find attached a list of signatures we have gathered from our neighbors who support
our proposed additional square footage design proposal. Our property is hardly visible
from any of our neighbors. We are located towards the end of El Camino Grande Road
which has very little traffic.
We have submitted our plans to meet the. current ordinance and followed up with this
letter in order to best demonstrate our requirements and to stay on schedule to start
construction in the spring of 1994. We appreciate your consideration for these minor
modifications and suggest a "special study" of our Project's abo- ie mentioned additional
proposed requirements.
If you have any questions please do not hesitate to call us, or our Architect, Maurice
Camargo, AIA.
Sincerely yours_, J
�; Jean and David Ebrahimoun
November 16, 1993
City of Saratoga
13777 Fruitvale Ave.
Saratoga, CA 95070
Subject: Design Review 93 -030, Ebrahimoun Residence
15170 El Camino Grande, Saratoga
Honorable Planning Commissioners:
Enclosed please find an additional list of neighbors correspondence. We have
received approval from more than 30 supportive neighbors and only positive.
comments regarding the variance.
Many years went into planning for this home to accommodate our needs as well as
complying with our neighborhood. We have been' a resident for 13 years, and under
our special circumstances, the parcel itself is only surrounded by beautiful, mature
trees which allows us total isolation from everyone.
All we are asking is to remain comparable with our neighborhood. We trust that after
visiting our property you will be convinced about the uniqueness of this special parcel
and will justify your approval of this modest variance.
Thank you for all your time and your consideration.
Yours truly,
-� C,
David & Jean Ebrahimoun
EBRAHIMOUN RESIDENCE
15170 EL CAMINO GRANDE
Monday, November 1, 1993
We the undersigned have reviewed the proposed design plan exhibits dated June, 1993
and the attached letter dated October 26,1993 and support the approval of this Project.
PRINT NAME
ADDRESS
SIG TURF
�C�IYI o rV
CalrrN!�
-
MJQtt %n/ .O-�Y .rc�/
l > I G CL CiJ c - G � /�'
i
� ti ; " •t-r' .
�s
I 0
�iKa
C Gw
L2.- .
f1A
AIJ°
gho !�
sw���
EBRAHIMOUN RESIDENCE
15170 EL CAMINO GRANDE
Monday, November 1, 1993
We the undersigned have reviewed the proposed design plan exhibits dated June, 1993
and the attached letter dated October 26,1993 and support the approval of this Project.
PRINT NAME
ADDRESS
SIGNATURE
Ilk
-7
QI �-
e, r r
C-. L CAW, 4� G P` io- tx:7
t.
Also fuym'l gel
toler
I--,-
EBRAHIMOUN RESIDENCE
15170 EL CAMINO GRANDE
Monday, November 1, 1993
We the undersigned have reviewed the proposed design plan exhibits dated June, 1993
and the attached letter dated October 26,1993 and support the approval of this Project.
PRINT NAME
ADDRESS
SIGNATURE
0
S
cc
CITY OF SARATOGA
13777 Fruitvale Avenue
Saratoga, CA 95070
Planning
Re: Design Review 93-030,15170 El Camino Grande
Ebrahimoun Residence - Variance
Dear Planning Commissioners:
November 15, 1993
We are residents at 15280 El Camino Grande. We have reviewed their plan, in
addition to their variance and it complies with our neighborhood.
We are very much in favor of this neighborhood improvement.
A60
Yours truly,
Tv,
Mr. & Mrs. Dixon
November 11, 1993
CITY OF SARATOGA
PLANNING COMMISSION
Attn: Lynette Dias, Assist. Planner
13777 Fruitvale Avenue
Saratoga, CA 95070
Re: Ebrahimoun Residence, 15170 E1 Camino Grande
Dear Planning Commissioners:
We have reviewed the Ebrahimoun's plans dated June 1993 along with
their variance of an additional 595.5 square feet. We are in
support of their variance.
This is a great neighborhood improvement!
Yours truly,
Mr. & rs. Reid
Residents of
15125 Via Colina
November 5, 1993
CITY OF SARATOGA
PLANNING COMMISSION
Attn: Lynette Dias, Assist. Planner.
13777 Fruitvale Avenue
Saratoga, CA 95070
Re: Design Review 93-030,15170 El Camino Grande
Ebrahimoun Residence
Honorable Planning Commissioners:
We have reviewed and formally given our approval of the Ebrahimouns's new home.
We feet this lot is exceptional because it is not visible from neighbors and
the mature oaks and redwoods camouflage the home. The home was designed
to compliment the area using the topography of the land.
We are in favor of this positive neighborhood improvement.
Yours truly,
R c;2�
Kay & Martin Thompson
* 4(jf) ��4 �e4'�4v�
November 11, 1993
City of Saratoga
13777 Fruitvale Ave.
Saratoga, CA 95070
.
Attn: Planning Commission
Dear Commissioners:
We are neighbors of the Ebrahimoun's and reside at 15100 El Camino Grande. We
have reviewed their plans and are very supportive of their variance.
There are exceptions to all. rules and in this circumstance to request additional square
footage is not a special privilege when many homes in our area exceed 6,200 square
feet. It's great to see design in which massiveness has been eliminated using
underground parking and also this home will be perceived as a one story home from
the exterior.
What a great neighborhood improvement.
Yours truly,
Mr. & Mrs. Tsai
November 5, 1993
CITY OF SARATOGA
PLANNING COMMISSION
Attn: Lynette Dias, Assist. Planner
13777 Fruitvale Avenue
Saratoga, CA 95070
J
Re: Design Review 93-030,15170 El Camino Grande
Ebrahimoun Residence
Honorable Planning Commissioners:
We have reviewed and formally given our approval of the Ebrahimouns's new home.
We feel this lot is exceptional because it is not visible from neighbors and
the mature oaks and redwoods camouflage the home. The home was designed
to compliment the area using the topography of the land.
We are in favor of this positive neighborhood .improvement.
Nso � re4'
Your ruly,
Mr. & Mrs. Moore
November 15, 1993
CITY OF SARATOGA
PLANNING COMMISSION
Attn: Lynette Dias, Assist. Planner
13777 Fruitvale Avenue
Saratoga, CA 95070
Re: Design Review 93-030, 15170 El Camino Grande
Ebrahi.moun Residence
Honorable Planning Commissioners:
we are neighbors to the Ebrahimoun's at 15042 El Camino Senda.
They have been in the neighborhood for well over 13 years and have
been planning their new home for many years.
They are very isolated in their corner lot with all the mature
trees and the way the topography of the land exists. Many large
estates exist in this neighborhood well over 6,000 square feet.
we are in favor of the variance and this will greatly improve our
neighborhood.
Yours truly,
/-Y� e Mr. & Mrs . .Clayman
November 21, 1993
CITY OF SARATOGA
PLANNING COMMISSION
Attn: Lynette Dias, Assist. Planner
13777 Fruitvale Avenue
Saratoga, CA 95070
Re: Design Review 93 -030, V -93 -026
Ebrahimoun Residence, 15170 El Camino Grande
Honorable Planning Commissioners:
We are neighbors to the Ebrahimoun's and reside at 15242 E1 Camino
Grande. They have been-in the neighborhood for 13 years and have
been planning their new home for many years.
The variance will have no impact visually on their design. This
exceptional lot is unique in that it has total isolation from
everyone around.
We are extremely happy preservation of their trees were a major
priority to the Ebrahimoun's. Conservation of energy was also
taken into consideration by requesting 12" thickness of exterior
walls.
We are in favor of the variance which will greatly improve our
neighborhood.
Yours truly,
Bill & Mary E 1e eaZ
Matteoril
Saxe
Nan
A W Y E R
Kodak Center
1740 Technology Drive
Suite 250
San Jose, CA 95110
February 2, 1994
408 441 -7800
FAX 408 441 -7302
Honorable Mayor and Members of the Council
City of Saratoga NomutnE.MrtSaxe
AUanRobe
13777 Fruitvale Avenue
Saratoga CA 95070 Margaret EckerNanda
anand
, Peggy M. O'Laughlin
Debra L.Cauble
Re : Ebrahimoun, 15170 El Camino Grande Judy C. Tsai
(DR 9 3 - 0 3 0, V-93-026) Bradley M. Matteoni
Dear Mayor Tucker and Members of the Council:
Thank you for your willingness to reconsider the
appeal of Mr. and Mrs. Ebrahimoun from denial by the Planning
Commission of their request for a variance which would allow
their new home to exceed the permitted floor area of 5,688
square feet by an additional 589 square feet.
There are three features which comprise the 589
square feet. The first of these involves utilizing approxi-
mately 224.5 square feet of available underground space as a
part of their two -car garage. This space will exist whether
or not the variance is granted. The only issue is whether it
must be walled off and used for storage or some other purpose
or whether it can be utilized by the family for garage
purposes. The issue has nothing whatsoever to do with the
size of the home, but turns on a technicality under the
ordinance. If it is separated from the garage and left as
dead space or utilized for interior storage, such as a cellar,
the area is not counted for purposes of determining permitted
floor area. However, if the space is considered to be a part
of the garage, it is counted as a part of the floor area.
The second component of the 589 square feet results
from utilizing walls having a 12 -inch thickness. The previous
staff report describes the variance request as reflecting a
desire to increase the thickness of the exterior walls from 6
inches to 12 inches for energy efficiency and in keeping with
the Mediterranean architectural style of the home. In fact,
the 12 -inch walls were a part of the plan from the outset. It
An Association Including a Professional Cmp.
City of Saratoga February 2, 1994
Page 2
was only when Mr. and Mrs. Ebrahimoun discovered that the
underground garage was, in fact, counted as a part of
permitted floor area that they attempted to modify the home
through changes designed to reduce square footage. The
purpose of this aspect of the variance is to allow them to
build the home as originally designed with 12 -inch walls
rather than changing the design to walls with 6 -inch
thickness. It is not, as appears from the staff report, an
afterthought to increase the thickness of the walls from 6
inches to 12 inches. The net effect of building the home
originally designed with the thicker walls is to add 238.5
square feet.
The third component of the additional square footage
would add 18 inches on the easterly end of the home. As with
the wall issue, this is a matter of building the house as
originally designed. This 18 -inch strip was proposed to be
eliminated in order to reduce the overall square footage of
the home. However, the purpose of the variance is to allow
the home to be built as designed.
From my review of the videotaped proceedings when
this matter was heard on January 5, 1994, there appeared
uncertainty concerning the findings necessary for granting a
variance as well as discussion concerning the nature and
purpose of a variance. One of the leading legal authorities
on land use law in California describes a variance as follows:
"Rather, variances sanction deviations
from regulations applicable to such
physical standards as lot sizes, floor
area ratios for buildings, and off street
parking requirements. The concept is
that the basic zoning provisions are not
being changed, but that the property
owner is allowed to use his property in a
manner basically consistent with the
established regulations with such minor
variations as will place him in parody
with other property owners in the same
zone." (Longtin's California Land Use,
2nd Ed., p. 349 -350.)
City of Saratoga
February 2, 1994
Page 3
Variances are authorized under the State Planning
Law (Government Code §65906) and implemented by local
ordinance, in this case, through Article 15 -70 of the Saratoga
Zoning Ordinance. Section 15- 70.060 sets forth, in a manner
consistent with Government Code §65906, the findings required
for granting an ordinance. In this instance, there are three
findings required.
The first finding is set forth in Section 15-
70.060(a) as follows:
"That because of special circumstances
applicable to the property, including
size, shape, topography, location, or
surroundings, strict enforcement of the
specified regulation would deprive the
applicant of the privileges enjoyed by
the owners of other properties in the
vicinity and classified in the same
zoning district."
In the Ebrahimoun case, this finding can be made on
the basis of the unique topography of the lot, which has the
effect of distorting computation of the average slope which,
in turn, is utilized to determine allowable floor area. One
unusable corner of the lot comprising approximately 28% of the
entire parcel drops precipitously some 40 feet down to a creek
bed. None of that area is affected in any way by the project.
Since the hearing on January 5, the engineer for Mr. and Mrs.
Ebrahimoun has computed the average slope for that portion of
the parcel and determined it to be 30.44 %. The average slope
for the balance of the property is 14.84 %, and the slope of
the area utilized for the home, driveway, and outdoor living
areas is actually 12.8 %. Mr. and Mrs. Ebrahimoun could
probably solve the problem by simply giving, through a lot
line adjustment, a few feet of the steep creek bank to their
neighbor. However, it is this very type of terrain constraint
unique to this parcel which can be utilized in making the
finding under subsection (a).
TI
City of Saratoga February 2, 1994
Page 4
The second finding applicable to this variance is
set forth in Section 15- 70.060(b) as follows: "That the
granting of the variance will not constitute a grant of
special privilege inconsistent with the limitations on other
properties in the vicinity and classified in the same zoning
district." It was not disputed in the staff report or at the
hearing on January 5 that other neighboring property owners
enjoy homes larger than would be permitted under the current
slope area requirements. The staff explanation was that the
current floor area standard were adopted subsequent to the
approval of those homes. However, that is the normal
situation in the case of a variance. The very function of a
variance is to allow something to happen which would otherwise
not be permitted under current standards. In this instance,
the effect of granting the variance requested by Mr. and Mrs.
Ebrahimoun is not to grant them a special privilege not
enjoyed by their neighbors, but instead to allow construction
of a home compatible with those of the neighbors. It is
interesting that this variance request is supported uniformly
by the neighborhood. Deliberating on a variance is a very
subjective exercise. It is important how the request is
received by neighbors because the reaction of the neighborhood
bears directly on whether there is a perception that the
applicant is requesting some special privilege or whether
there are, in fact, special circumstances surrounding the
request. Longtin comments in his book on this aspect of
considering a variance:
"Local agencies and the courts on
judicial review have not been altogether
consistent in determinations as to
whether or not special circumstances
justify the grant of a variance. As a
matter of practice, where significant
opposition exists to a variance
application, it is wise to thoroughly
justify, with appropriate findings,
sufficient special circumstances to meet
the GovC 65906 criteria. On the other
hand, where no opposition to the variance
application exists, local agencies can be
more lax in justifying their need to meet
City of Saratoga
February 2, 1994
Page 5
statutory special circumstance criteria."
(Longtin's California Land Use, 2nd
Ed.,p. 355)
The final finding required under Section 15- 70.060
is set forth in subparagraph (c) as follows: "That the
granting of the variance will not be detrimental to the public
health, safety or welfare, or materially injurious to
properties or improvements in the vicinity." There has never
been any suggestion that Mr. and Mrs. Ebrahimouns' proposed
new home would be detrimental in any way to the public health,
safety or welfare. To the contrary, the design and planning
which went into the home have been complimented not only by
the neighborhood but by staff. In short, the finding under
subparagraph (c) is not in dispute.
Again, thank you very much for your further
consideration of this matter.
Very truly yours,
ALLAN R. SAXE
ARS:md
cc: Mr. and Mrs. David Ebrahimoun
SARATOGA CITY COUNCIL
EXECUTIVE SUMMARY NO. ';� T C) F AGENDA ITEM
MEETING DATE: _February 2, 1994 CITY MGR.
ORIGINATING DEPT. City Manager
4s(s
SUBJECT: Third Amendment to Countywide Household Haza dous Waste
Agreement I . t
Recommended Motion(s):
Approve amendment.
Report Summary:
The Program Manager of the County Office of Toxics and
Management has requested that the City Council approve
agreement.
Solid Waste
:he subject
Apparently this amendment was first sent to the City on August 18,
1992, but for unknown reasons was not forwarded to the Council.
Although the agreement would have been in effect only from
September 30, 1992, to June 30, 1993, it would still be timely to
pass it. The County is applying for a federal grant for this
program, and the grant procedures require proof that the agreement
has been approved. If the Council approves this amendment now, for
their purposes it would be as though it had been in effect
continuously.
Fiscal Impacts•
None.
Advertising, Noticing and Public Contact:
None.
Consequences.of Not Acting on the Recommended Motions:
Follow Up Actions:
None for City.
SARATOGA CITY COUNCIL
EXECUTIVE SUMMARY NO. � 40 9 AGENDA ITEM 8/T
MEETING DATE: February 2 1994 CITY MGR.
ORIGINATING DEPT: City Manager's Office C36r
SUBJECT: Allocations for FY 1.994/95 :Housing and Community
Development Act Funds and Human Services Grants
:Recommended Motion(s1:
1. Conduct Public Hearing
2. Make allocations for approximately $159,500 for FY 94/95 HCDA
project funds as determined
3. Make allocations for Human Services grants from other revenue
sources according to Council policy
Report Summ
The City Council is requested to conduct a Public Hearing to receive comments and
recommendations on projects proposed for 1994/95 Housing and Community Development Act
(HCDA) funds and other funding as available: Council is further requested to make a
determination regarding the allocation of federal HCDA monies anticipated to be approximately
$159,500. Availability of Block Grant funds has been publicized and proposals solicited from
the community, previous recipients, and city staff. Following determination of the allocation of
1994/95 HCDA funds by Council, proposals will be submitted to the County for final approval
by the Board of Supervisors. Proposals for human services not funded through the Block Grant
may be considered for grants from general revenue sources.
Fiscal Impacts:
The City will receive an HCDA allocation of approximately $159,500 for project costs plus
$15,000 for staff administrative costs for 1994/95. Council policy limits spending for human
services programs to 1.3%. of projected general revenues, approximately $92,200.
Approximately $40,000 of this amount will come from CDBG funds. Human Services funding
recommendations from staff are 15% below the maximum and total $78,000, the same as
Council allocations last year.
Advertising. Noticing and Public Contact:
1. Letter announcing schedule and inviting proposals sent to interested parties, Commission
Chairs, and City staff, November, 1993 .
2. Display ad announcing hearing and inviting proposals, Saratoga News, December 8, 1 993
3. Legal Notice of Public Hearing, Saratoga News, January 19, 1994
Consequences of Not Acting on the Recommended Motions:
The HCDA allocation will remain with the County and the supplementary funding for human
services will remain in the City's general fund.
Follow Up Actions:
Forward HCDA funding recommendations to the County; execute agreements with agencies
receiving funding.
Attachments:
1. Report to Council from Assistant to the City Manager
2. Project Proposals
o:lexec.sum (rev.] /11/94)
C o oxo
13777 FRUITVALE AVENUE SARATOGA, CALIFORNIA 95070 •-(408)867=3438,
COUNCIL'MEMBERS. .. .
Karen Anderson
Ann Mane Burger "
Willem Kohler
Date February 2,.� 1994 vicforMoriia
Karen Tucker
To: city•Council
From:" Assistant "to_the City Manager.
• Subject 'Allocation- of . the FY" 1994/95 Housing "_ and" -Community "
Development'Act',Funds and,. Human,Services- Grants.:
RECOMMENDED. ACTION ":'
1. Conduct Public, Hearing`.
...2'6'. Make !allocations for approximately ,$15.9 ", 500 for FY 94./95 �'cCDBG
funds: as determin "ed
'3;. Make allocations for.Human Services "grants from. other revenue';
sources a'ccording.to. Council, policy and /or• budget constraints
Back4round Cornmiunity Development Block Grant Program
.The :. City, of .. •Saratoga, ' nine" other.` "nonentitl,ement'.' . cities
(populati.on.under 50,000) within Santa Clara County,,,and the County
,tsel'f'r6ceive federal - Housing and. Community Development.Act (HCDA)'
Community Development Block Grant (CDBG) funds;:,,which 'are
adininiste'red by-'the, Department of -Housing,: and- Urban'-Development
(HUD") for: 'eligible projects and-activities. "By, 'regulation;,'
n'onentitleinerit_ ,cities receive funds through a cooperative 'Agreement
with,,the . Urban county of .,,Safita ,Clara. (the' locally responsible gr'an't
recipient)..
Therefore, expenditure.:-of. these' "funds "is. restricted not ,only' by
".federal regulations, but.Yiy "any .additional `guidel nes imposed.by,
the County.as' . well
,.,'.The .total, amount of HCDA aftocatiorf to the County. for 1994/95 ',. is .
expected` to be` approximately $3 , 262 ", 0.00. O.f `!the total . grant',
twenty: ,percent will be used for administratioh' costs., . of .which. -,the-
C.t'y'of Saratoga will receive $15,:OQO_- iri.additi.on;, to'the project:
allocation; Forty percent of the ., remainder,, "will go to the
Countywide•.competitive pool, where funds are prioritized for
% .,projects /activ.itiesi that contribute"to..ncreasing: the supply 'of
Printed on recycled paper.
2 - Allocation of the FY 1994 /95 Housing and Community Development
Act Funds and Human Services Grants
affordable housing in the County. The other sixty percent of the
total grant will go to the nonentitlement cities and the County for
direct allocation for any HCDA eligible activity. Saratoga's
project share.is expected to be approximately $159,500.
In general, to be eligible for CDBG funds, proposals must primarily
benefit those of very low or low income (e.g. family of four -
$39,700).
A maximum of fifteen percent of the total County grant may be used
for human services activities. We estimate that we will be able to
use $40,000 of our grant funds for human services in 1994/95.
Background - Human Services Grants:
Council policy provides for the use of general funds in making some
grants to human services agencies because of the constraint on
using Block Grant money for this purpose, i.e. the number of
proposals which the City receives each year for providing necessary
services to low income, elderly and disabled residents. The policy
also provides that proposals for both Block Grant funds and general
revenues will be considered at one hearing. The policy sets a
maximum dollar amount to be allocated annually for human services
grants at 1.30 of the City's projected general revenues
(approximately $92,200 for 94/95).
Last year, because of projected loss of revenue, the Council
reduced the maximum dollar amount for human services grants by
approximately 15 %, to a maximum of $78,000. Funds have been
budgeted in the adopted City budget for 94/95 at the same level of
funding as for 93/94.
(Summary of proposals on following page)
18— Jan -94 SUMMARY OF HCDA AND.HUMAN SERVICES GRANT PROPOSALS
94/95 Amount Amount
Agency Project Request Recommend.
Capital Projects Saratoga ADA Access 125000 119500
Sub —total 125000 119500
Other CDBG EHC shelter rehab
EHC temp hous rehab
Sub —total
Sub —total projects
Human Services EHC
shelter sery
Fam Sery
case mgmt
Food Bank
brown bags
LTC
ombudsman
Project Mtch
senior match
SA,SCC
Day care
SASCC
operations
TC
teen counsel
Trans Asst
paratransit
Womans Housing.
shelter sery
WVC
reentry prog
WVC
senior sery
Sub —total
Total Proposals
Funding Source HCDA 159500
genJund 38000
Total 197500
Amount
Approved
93/94
125000 .
125000
Amount
Approved m
92/93 W
i
25000
25000
rehab fund
12000
12000.
37000
from rehab fund
162000
119500
125000
3000.
0
0
3000
1000
1000
3000
1000
1000
2655
0
0
2300
1000
1000
27810
27400
27195
38110
35000
35215
5000
0
0
15000
12600
12590
4500
0
0
12500
0
0
16000
0
0
132875
78000
78000
294875
197500
203000
2500
3000
2500
2100
27000
37000
15000
2000
Page 4 - Allocation of the FY 1994/95 Housing and Community
Development Act Funds and Human Services Grants
RECOM[M[ENDATTONS
1. Capital projects Recommended Funding $119,500
The only project proposal recommended for funding in this category
is from the City Public Works Director for continuation of
compliance with ADA (Americans with Disabilities Act) access
requirements. We are using 93/94 CDBG funding to hire a consultant
who is developing a list of modifications which need to be made to
City facilities, and the high priority items will be funded from
this allocation.
We estimate that we will be able to use $40,000 of the total
available for CDBG projects for 94/95 ($159,500) for human
services. In order to set aside that amount, the recommendation
for this proposal is for $119,500 rather than the requested
$125,000. We anticipate supplementing the ADA Access program by
reprogramming approximately $100,000 in unobligated CDBG funds from
previous years.
2. Other CDBG Recommended Funding $37,000
The Emergency Housing Consortium has submitted two proposals for
rehabilitation projects: $25,000 for the new regional emergency
shelter, and $12,00.0 for one of the temporary housing sites.
During FY 91/92 and 93/94, the City Council, made grants totaling
approximately $20,000 for rehabilitation of the EHC Family Living
Shelter, which have come from the City's revolving rehabilitation
loan fund. Funding for requests of this type can come either from
the "new" 94/95 CDBG money or from the City's housing
rehabilitation loan program. Staff recommends using the loan fund
again for these proposals since there has not been much activity
lately in the City's housing rehabilitation program (SHARP), and
there is a balance of $145,000 in the fund at this time. As in the
past, staff further recommends that funding be contingent on the
Emergency Housing Consortium securing administrative support from
the County or another City to monitor the proposed projects for
Davis -Bacon (labor standards) requirements.
3. Human Services Recommended Funding $78,000
Twelve proposals were received in this category, totalling
$132,875. Last year, only SASCC- operations, SASCC -day care,
Transit Assist, Project Match, Food Bank, and the Family Services
case management program were funded. (The case management program
was transferred from the now - defunct Los Gatos Senior Coordinating
Council last year to the Family Services Association). Staff is
recommending funding in this category at the budgeted level which
Page 5 - Allocation of the FY 1994/95 Housing and Community
Development Act.Funds and Human Services Grants
was used last year, $78,000. The total allowed under the human
services funding policy is a maximum of $92,200. $78,000 is 58.7%
of the total requested, and $92,200 is 69 %. Funding at $78,000
requires $38,000 of general fund money, and the maximum level,
$52,200.
Council has adopted funding criteria for the Human Services Grants.
program which includes consideration of the benefit to Saratoga;
the need for the service provided; financial need of applicant
agency; and provision of essential services to Saratoga's low
income, elderly, and /or disabled residents. Assigning funding
priority based on financial need is difficult because Saratoga's
portion of services in most cases is so low in comparison to other
cities that these services make up a small portion of most
agencies' organization and program budget. The exceptions are
SASCC and Transit Assist where services to targeted Saratoga
residents are a primary objective and the City of Saratoga has had
a long -term relationship in policy direction as well as funding.
This year we received several new proposals in addition to-those
from agencies previously funded for services in Saratoga. West
Valley College is requesting $12,500 for establishing a
mentorship /re -entry program for mature students, and $16,000 to
facilitate establishment of an Older Adults Institute for
activity /instructional programs for senior residents. Although
these are worthwhile programs, staff doesn't consider them to be at
the same level of priority as the more essential services to, low
income residents. Last year West Valley requested funds for
improving disabled access and the City is incorporating their
requests in our CDBG funded sidewalk /curb cut project.
The Emergency Housing Consortium submitted a request for $3,000 in
support services for'the homeless in their shelters. Since EHC's
other proposals can be funded from the construction category rather
than the more limited human services category of CDBG funds, staff
is recommending continued funding to EHC for their rehabilitation
projects, and not for the funding services proposal.
If the Council wishes to consider going beyond the budgeted $78,000
for human services support for the next fiscal year, staff
recommends either a higher level of funding for Food Bank and
Family Services case management, and /or funding again for the Long
Term Ombudsman program. These recommendations are based upon the
criteria listed above.
.s
Page 6 - Allocation of the FY 1994 /95 Housing and Community
Development Act Funds and Human Services Grants
riM�4._i
If Council chooses to follow staff recommendations for allocation
of the 1994/95 CDBG funds and general funds, the allocation will be
as follows:
CDBG
ADA Access
SASCC
$119,500
$ 40,000
GENERAL FUNDS
All grants to outside agencies plus
supplemental to SASCC's CDBG allocation
as required
Carolyn King
Assistant to the City Manager
Total: $159,500
Total: $ 38,000
O: \HCDrept CBR:mc