HomeMy WebLinkAbout08-09-1994 CITY COUNCIL AGENDASARATOGA CITY COUNCIL EXECUTIVE SUMMARY NO. �0� AGENDA ITEM MEETING DATE: AUGUST 9, 1994 CITY MGR.: ORIGINATING DEPT.: PUBLIC WORKS DEPT. HEAD: SUBJECT: 1994 Pavement Management Program, Award of Construction Contract Recommended Motion(s): 1. Move to declare E1 Camino Paving, Inc. of Sunnyvale to be the lowest responsible bidder on the project. 2. Move to award the attached construction contract to E1 Camino Paving, Inc. in the amount of $1,020,374.07. 3. Move to authorize staff to execute change orders to the contract up to $50,000. Report Summary: Sealed bids for the 1994 Pavement Management (pavement overlay) Program were opened earlier today. Six contractors submitted bids for the work and a summary of the bids received is attached. E1 Camino Paving, Inc. of Sunnyvale. submitted the lowest bid of $1,020,374.07 which is 13.7% below the Engineer's Estimate of $1,182,150.25. Staff has carefully checked the low bid and has determined that it is responsive to the Notice Inviting Sealed Bids dated July 20. Therefor, it is recommended that the Council declare E1 Camino Paving, Inca to be the lowest responsible bidder on the project and award the attached construction contract to this firm in the amount of their bid. Further, it is recommended that the Council authorize staff to execute change orders to the contract up to an amount of $50,000 to cover any unforeseen circumstances which may arise during construction, as well as for any. overages in individual item quantities which might occur on the job. Fiscal Impacts: The Pavement Management Program is largely funded by the Utility Users Tax. The current project actually combines both the 93 -94 and 94 -95 projects. You may recall that last year, staff decided to combine two annual projects into a single bi- annual project in order to reduce the administrative and technical requirements of this work, as well as to obtain more competitive prices for the City. Judging from the response to the Notice Inviting Bids, and the narrow spread of the bids received, this strategy-app ears to have paid off,,and is particularly evident in the unit prices bid for the large quantity items of work. The adopted budget contains sufficient funds in Program No. 31 (Street Maintenance), Account No. 4530 (Repair /Maintenance) to cover the cost of the base contract amount plus the recommended change order authority. Advertising, Noticing and Public Contact: Nothing additional. Consequences of Not Acting on the Recommended Motions: The Council would not declare E1 Camino Paving, Inc. to be the lowest responsible bidder and the construction contract would not be awarded to that firm. The Council may make specific findings to declare another bidder to be the lowest responsible bidder, or reject all bids and' direct staff to solicit new bids for the project. The Council has up to 30 days within which to make its decision. Follow Up Actions: The construction contract will be signed, and the Contractor will be authorized to proceed with the work. I tentatively estimate that the work will last through the middle of October. Attachments: 1. Bid Summary. 2. Construction Contract. 1894 PAVEMENT MANAGEMENT PROGRAM BID SUMMARY ITEMDESCRIPTION I QUA TRAFFIC CONTROL - 1 1/7 AC OVERLAY I 101 I� 1 10. 111. 15. i PAINTTRAFFIC STRIPE -S.D. l39A 1-720 1 LF 11 .- if] 121. I I PAINT -25' I 1 122. I I PAINT'xING � I 61 23. i PAINT'BIKE LANE• i 6 � 24. 1 PAINT'SLOW � 6 I 25 28. i PAINT 'ONLY' 1 IPAINTARROWS i 11 1I 97-1 PAINT PARKING STALLS I 41 26. 1 TYPE A PAVEMENT MARKERS i 76 29. 1TYPE DPAVEMENT MARKERS 1 7021 1' 30. 91, 32A. 1 TYPE G PAVEMENT MARKERS BLUE PAVEMENT MARKERS 1ADJUST SANITARYMHTOGRADE 1 g 8.5 1941 33A. 34A. 35A. 36A. I ADJUST SANITARY C.O. TO GRADE I I ADJUST WATER VALVES TO GRADES I i ADJUST GAS ANODES TO GRADE 1 ADJUST TELEPHONE MH TO GRADES 2 1 g9I 6 1 , TOTAL 115.00 172.00 116.00 341.00 .00 12 1 I $3,510.001 1 $4.04 $5.001 I sm.001 I $4.04 $20.00 1 $1,70.00 1 59.09 $250.00 1 $46,500.001 $210.00 $175.01 $350.001 $185.001 $175.001 575,575..0 $150.00 $175.00 j $250.01 I $175.001 $1.500.001 1 $1,182,150.25 I $,'!50.00 1 5350.00 1 I I $1,020,374.07 1 13 .00 .30 wir.W 1 $37.001 I i 534.00 1 531000 i 566.00 1 SSM.W 1 I I I (62.00 i $496.00 $46.001 $358.001 $42.001 5336.001 $66.001 $544.00 1 $62.001 5496.001 $460.00 $1.050.00 i $,900.00 i _$1.000001 I $1,034.693.451 1 $1.076.800.761 1994 PAVEMENT MANAGEMENT PROGRAM BID SUMMARY ITEM #1 ITEMDESCRIPTION I I I QUANTITY I I UNITS II it LS I I II UNITPRICE I I N/A I I TOTAL I I $10,000.001 I UNITPRICE I I N/A I I TOTAL I I $50,000.00 I I UNITPRICE I I N/A 1 I TOTAL I I $22,870.00 I I UNITPRICE I I N/A I I TOTAL 1 1 $28,000.00 1 I 1. I TRAFFIC CONTROL 1 1 1 I I I 2. 111 12'AC OVERLAY 1 I I 19,0891 I TON 11 II $35.001 1 $668,115.001 I $32.501 I $620,392.501 I $33.051 I $630,891.451 I $35.001 I $668,115.001 I 3. 1 AC LEVELING COURSE 1 I I 3561 I TON 11 11 $37.00 1 I $13,172.00 1 I $50.00 1 I $17,800.00 1 I $33.051 I $11,765.801 I $37.00 1 I $13,172.001 I 4. I RFSS TYPE I I I I 4,029 I i SF 11 II $4.00 1 I $16,116.001 I $3.70 I I $14,907.30 1 I $3.901 I $15,713.101 I $3.601 I $14,504.40 I I 5. 1RFSS TYPE II 1 I I 15,0521 I SF 11 II $1.751 I $26,341.001 I $1.851 I $27,846.201 I $2.301 I $34,619.601 I $2.501 I $37,630.001 I 6. I WEDGECUT 1 I I 101,2831 I LF 11 11 $1.251 I $126,603.751 I $0.90 1 I $91,154.701 I $0.79 1 I $80,013.571 I $0.851 I $86,090.551 1 7. I PAVEMENT FABRIC 1 I I 223,4901 I SY 11 II $0.80 I I $178.792.001 I $0.661 I $147,503.40 1 I $0.76 I i $169,852.401 I $0.73 1 I $163.147.701 I 8. 1 ADJUST STORM MH TO GRADE 1 I I 93 I 1 EA 11 II $250.00 1 I $23250.00 1 I $200.00 I I $18,600.00 1 I $213.00 1 I $19,809.00 I I $200.00 1 I $18,600.00 1 I 9. I ADJUST MONUMENTS TO GRADE 1 I I 1721 I LF 11 11 $175.001 I $30,100.00 1 I $150.001 I $25,800.00 1 I $180.00 I I $30,960.00 1 I $140.001 I $24,080.001 1 10. 1 PAINT TRAFFIC STRIPE -S.D. #2 1 I I 2,9251 I LF 11 II $0.50 1 I $1,462.501 I $0.091 I $263.25 1 I $0.10 1 I $292.50 1 I $0.22 1 I $643.50 1 I 11. I PAINT TRAFFIC STRIPE -S.D. #22 I I I 8.5951 I LF I 1 II 1 LF 11 11 $1.001 I $0.40 1 I $8,595.001 I $760.00 1 I $0.141 I $0.11 1 I $1,203.301 I $209.00 I I $0.151 I $0.12 I I $1,289.251 I $228.00 1 I $0.44 1 I $0.22 I I $3,781.801 I $418.00 1 1 12. 1 PAINT TRAFFIC STRIPE -S.D. #27B 1 1,900 I I I 13. I PAINT TRAFFIC STRIPE -S.D. #38 1 I I 1001 I LF 11 II $0.70 1 I $70.00 1 I $0.131 I $13.00 1 I $0.14 1 I $14.00 I I $0.44 1 I $44.00 1 I 14. 1 PAINT TRAFFIC STRIPE -S.D. #39 1 I I 1,3801 I LF I I II $0.60 1 I $828.00 1 I $0.131 I $179.40 1 I $0.14 1 I $193.20 1 I $0.33 1 I $455.40 1 I 15. 1 PAINT TRAFFIC STRIPE -S.D. #39A 1 I 1 7201 I LF 11 II $0.50 1 I $360.00 1 I $0.131 I $93.60 1 I $0.14 1 I $100.80 1 I $0.33 1 I $237.60 1 1 18. 1 PAINT STOP BARS I I I 53 I I EA 11 II $25.00 1 I $1,325.00 1 I $21.00 1 I $1,113.001 i $22.05 1 I $1,168.651 I $66.00 1 I S3,498.001 I 17. 1 PAINT CROSSWALKS 1 I I 111 EA II I II $100.001 I $1,100.001 I $83.001 I $913.001 I $87.151 I $958.651 I $187.001 I $2,057.001 I 18. 1 PAINT -STOP- i I I 65 1 EA 11 I 11 $30.00 1 1 $1.950.00 1 I $62.001 I S4,030.001 I S65.101 I S4,231.501 I $44.00 1 1 $2,860.00 1 1 19. 1 PAINT -AHEAD" I I I 61 I EA 11 II EA 11 I 11 $40.00 1 I $50.001 I $240.00 I I $400.001 I $85.00 I I $102.001 I $510.00 I I $816.001 I S89.251 I $107.101 I $535.501 I $856.801 I $61.001 I $55.001 I $366.00 I I $440.001 1 20. 1PAINT "SCHOOL" 1 81 I I 21. I PAINT -25' I i I 11 EA 11 I II $15.00 I I $15.00 1 I $34.001 I $34.00 I I $35.701 I $35.70 1 I $22.00 1 I $22.00 1 1 22. 1PAINT "RING' 1 i I 61 EA 11 I II $30.001 I $240.001 I $62.001 I $496.001 I $65.101 I $520.801 I $44.001 I $352.001 I 23. (PAINT -BIKE LANE' 1 I I 81 EA 11 I it $30.001 I $240.001 I $42.001 I $336.001 I $44.101 I $352.801 I $33.001 I $264.001 I 24. PAINT -SLOW" 1 I I 81 EA 11 I II $30.001 I $240.001 I $62.001 I $496.001 I $65.101 I $520.801 I $44.001 I $352.001 I 25. I PAINT -ONLY' 1 I I 11 EA 11 I II $30.00 1 I $30.00 1 I $62.00 1 I $62.00 1 I $65.10 1 I $65.10 1 I $44.00 1 I $44.00 1 I 26. (PAINT ARROWS I I I 11 EA 11 I II $15.001 I $15.001 I $42.001 I $42.001 I $44.101 I $44.101 I $44.001 I $44.001 I 27. I PAINT PARKING STALLS 1 I I 41 EA 11 I II $15.001 I $60.001 I $18.001 I $72.001 I $18.901 I $75.601 I $28.001 I $112.001 I 28. 1 TYPE A PAVEMENT MARKERS 1 I I 781 EA 11 I II $5.00 1 I $390.00 1 I $2.00 1 I $156.00 1 I $2.10 1 I $163.80 1 I $2,651 I $208.70 1 I 29. 1 TYPE D PAVEMENT MARKERS 1 I I 702 1 EA 11 I II $5.00 1 I $3,510.001 I $4.001 I $2,808.00 1 I $4.20 1 I $2.M.401 I $2.651 I $1,860.30 I I 30. I TYPE G PAVEMENT MARKERS 1 61 EA 11 1 EA 11 I II $5.00 1 $20.00 1 I $30.00 1 $1,700.001 I $4.00 1 $9.001 I $24.00 1 $765.00 1 I $4.20 1 $9.45 1 I $25.20 1 $603.25 1 I $2.651 $11.001 I $15.90 1 $935.00 1 I 31. I BLUEPAVEMENT MARKERS 1 85 1 I 32A. I ADJUST SANITARY MH TO GRADE 1 I I 1941 EA 11 I II $250.00 1 1 $46,500.00 1 I $200.00 1 I $38.800.00 1 I $213.00 1 I $41,322.00 1 I $200.00 1 I $38,800.00 I I 33A. 1 ADJUST SANITARY C.O. TO GRADE I I I 21 EA 11 I 11 $175.001 I $350.001 I $250.001 I $500.001 I $180.001 I $360.001 I $140.001 1 $280.001 I 34A. 1ADJUST WATER VALVES TO GRADE( 891 EA 11 $175.001 $15,575.001 $150.001 $13,350.001 $168.001 $14,952.001 $140.001 $12,460.001 35A. ADJUST GAS ANODES TO GRADE I I I 11 EA 11 I II EA 11 11 $175.00 1 I $250.001 I $175.001 I $1,500.001 I $250.001 I $300.001 I $250.00 1 I $1,800.001 I $180.00 1 I $213.001 $180.001 I $1,278.001 I $140.00 1 I $300.001 I $140.00 1 I $1,800.001 1 36A 1 ADJUST TELEPHONE MH TOGRADEI 61 I I TOTAL 11 I $1,182,150.251 1 $1,083,338.651 i $1,089,811.321 1 $1,123,828.851 II I I I 1 I I I I CITY OF SARATOGA SANTA CLARA COUNTY, CALIFORNIA CONTRACT FOR PUBLIC WORKS CONSTRUCTION 1994 PAVEMENT MANAGEMENT PROGRAM THIS CONTRACT, made this 9th day of August, 1994, by and between the City of Saratoga, a Municipal Corporation, in Santa Clara County, California, hereinafter called the City, and E1 Camino Paving, Inc. hereinafter called the Contractor. WITNESSETH: WHEREAS, the City has caused to be prepared in the manner prescribed by law, plans, specifications and other contract documents, for the work herein described and shown and has approved and adopted these contract documents, specifications and plans and has caused to be published in the manner and for the time required by law, a Notice Inviting Sealed Bids for doing the work in accordance with the terms of this Contract, and WHEREAS, the Contractor in response to said Notice has submitted to the City a sealed bid proposal accompanied by a bid guaranty in an amount not less than ten percent (10 %) of the amount bid for the construction of all of the proposed work in accordance with the terms of this Contract, and WHEREAS, the City, in the manner prescribed by law, has publicly opened, examined and canvassed the bids submitted and as a result has determined and declared the Contractor to be the lowest responsible bidder and has duly awarded to the Contractor a contract for all of the work and for the sum or sums named in the bid proposal and in this Contract. NOW, THEREFORE, THE PARTIES AGREE AS FOLLOWS: ARTICLE I. WORK TO BE DONE: That the Contractor shall provide all necessary labor, machinery, tools, apparatus and other means of construction; shall furnish all materials, superintendence. and overhead expenses of whatever nature necessary to construct all of the improvements for the City of Saratoga in conformity with the plans, specifications and other contract documents and according to such instructions as may be given by the Saratoga Director of Public Works or his authorized agent. 17 ARTICLE II. CONTRACT PRICES Except as provided in Section IV B of the Specifications ( "Changes and Extra Work "), the City shall pay the Contractor according to the prices stated in the bid proposal submitted by the Contractor, which shall include all applicable taxes, for complete performance of the work. The Contractor hereby agrees to accept such payment as full compensation for all materials and appliances necessary to complete the work; for all loss or damage arising from the work or from action of the elements, or from any unforeseen obstruction or difficulties which may be encountered in the prosecution of the work; incurred in and in consequence of the suspension or discontinuance of the work; as hereby specified; for all liabili- ties and other insurance; for all fees or royalties or other ex- penses on account of any patent or patents; for all overhead and other expenses incident to the work and expected profits; and for well and faithfully performing and completing the work within the time frame specified in the Notice to Proceed, all according to the contract plans and specifications, the details and instructions, and the requirements of the City. ARTICLE III. PARTS OF THE CONTRACT: That the complete contract document consists of the following: 1. Notice Inviting Sealed Bids 6. Performance Bond 2. Bid Proposal 7. Labor and Material Bond 3. Bidder's Bond or Bid Guaranty 8. Plans 4. Contract for Public Works 9. Specifications Construction 10. Insurance Certificates 5. Hold Harmless Clause 11. Prevailing Wage Rate In case of any conflict between this Contract and any other part of the contract, this Contract shall be binding. IN WITNESS WHEREOF, the City has caused its corporate name to be hereunto subscribed and its corporate seal to be hereunto affixed by its City Manager and its City Clerk thereunto duly authorized and the Contractor has executed these presents the day and year hereinabove written. 18 J AWARDED BY CITY COUNCIL: Date : August 9, 1994 ATTEST: City Clerk The foregoing Contract is approved as to form this day of , 19 City Attorney 19 CITY OF SARATOGA: CONTRACTOR: By Title License No. Tax ID or SSN SARATOGA CITY COUNCIL EXECUTIVE SUMMARY NO. �`C� ( AGENDA ITEM MEETING DATE: AUGUST 9, 1994 CITY MGR.: ORIGINATING DEPT.: PUBLIC WORKS DEPT. HEAD: p SUBJECT: 1994 Street Maintenance Program, Award of Construction . Contract Recommended Motion(s): 1. Move to declare Valley Slurry Seal Co. of West Sacramento to be the lowest responsible bidder on the project. 2. Move to award the attached construction contract to Valley Slurry Seal Co. in the amount of $204,324.27. 3. Move to authorize staff to execute change orders to the contract up to $15,000. Report Summary: Sealed bids for the 1994 Street Maintenance (slurry seal) Program were opened earlier today. Four. contractors submitted bids for the work and a summary of the bids received is attached. Valley Slurry Seal Co. of West Sacramento submitted the lowest bid of $204,324.27 which is 24.1% below the Engineer's Estimate of $269,.299.85. Staff has carefully checked the low bid and has determined that it is responsive to the Notice Inviting Sealed Bids dated July 20. Therefor, it is recommended that the Council declare Valley Slurry Seal Co. to be the lowest responsible bidder on the project and award the attached construction contract to this firm in the amount of their bid. Further, it is recommended that the Council authorize staff to execute change orders to the contract up to an amount of $15,000 to cover any unforeseen circumstances which may arise during construction, as well as for any overages in individual item quantities which might occur on the job. Fiscal Impacts: The Street Maintenance Program is largely funded by the Utility Users Tax. The current project actually combines both the 93 -94 and 94 -95 projects. You may recall that last year, staff decided to combine two annual projects into a single bi- annual project in order to reduce the administrative and technical requirements of this work, as well as to obtain more competitive prices for the City. - Judging from the - response to the Notice Inviting Bids, and the narrow spread of the bids received, this strategy appears to have paid off, and is particularly evident in the unit prices bid for the large quantity items of work. The adopted budget contains sufficient funds in Program No. 31 (Street Maintenance), Account No. 4530 (Repair /Maintenance) to cover the cost of the base contract amount plus the recommended change order authority. Advertising, Noticing and Public Contact: Nothing additional. Consequences of Not Acting on the Recommended Motions: The Council would not declare Valley Slurry Seal Co. to be the lowest responsible bidder and the construction contract would not be awarded to that firm. The Council may make specific findings to declare another bidder to be the lowest responsible bidder, or reject all. bids and direct staff to solicit new bids for the project. The Council has up to 30 days within which to make its decision.. Follow Up Actions: The construction contract will be signed, and the Contractor will be authorized to proceed with the work. I tentatively estimate that the work will last through the end of September. ttachments: 1. Bid Summary. 2. Construction Contract. 1994 STREET MAINTENANCE PROGRAM BID SUMMARY TOTAL 11. I TRAFFIC CONTROL I i I I 1 1 LS I I II WA 1 I $10,000.00 I WA 1 $11,150.00 I WA 1 $5,000.00 I N/A 1 $5,000.00 I WA 1 $5,000.00 1 12. 1 SLURRY SEAL 1 I I I I 517,741 1 I SY 1 1 II $0.451 I I $232,983.45 1 I I $0.3287 1 I I $170,181.47 1 I I $0.361 I I $186,386.76 1 I I $0.39 1 I I $201,918.99 1 I I $0.513 1 I I $265,601.13 1 I 13. 1 PAINT TRAFFIC STRIPE-SD. #1 1 I I I 1,2001 I LF 11 II $0.501 I $600.001 I $0.151 I $180.001 I $0.16 1 I $192.001 I $0.21 1 I $252.001 I $0.21 1 I $252.001 I 14. 1 PAINT TRAFFIC STRIPE -SD. #2 1 I I I 200 1 I LF 11 II $0.501 I $100.00 1 I $0.40 1 I $80.00 1 I $0.44 1 I $88.00 1 $0.32 1 $64.001 $0.32 1 $64.001 15. 1 PAINT TRAFFIC STRIPE-S.D. #9 1 I I I 440 1 I LF 1 1 II $0.501 I $220.00 1 I $0.401 I $176.00 1 $0.44 1 I I $193.601 I $0.35 1 I $154.001 I $0.32 1 I $140.80 1 16. 1 PAINT TRAFFIC STRIPE-S.D. #22 1 I I I 16,0251 I LF 1 1 II $0.501 I S8.012.501 I $0.42 1 I I $6,730.50 1 $0.44 1 I I $7.051.001 I $0.54 1 I $8,653.501 I $0.53 1 I $8,493.25 I 17. 1 PAINT TRAFFIC STRIPE -S.D. #27B 1 I i I 540 1 1 LF 11 II $1.001 I $540.00 1 I $0.15 1 I I $81.00 1 I $0.16 1 I I $86.40 1 I I $0.431 I I $232.20 1 i I $0.32 1 i I $172.801 I 18. I PAINT TRAFFIC STRIPE -SD. #38 1 I I 4401 LF 1 1 $0.401 $176.00 1 $0.20 1 $88.00 1 $0.22 1 $96.80 1 $0.52 1 $228.80 1 $0.531 $233.201 I 19. 1 PAINT TRAFFIC STRIPE -S.D. #39 1 I 1 I I 1,7401 I II LF 1 1 II I $0.70 1 I I $1,218.001 I I $0.20 1 I I $348.001 I I $0.22 1 I I $382.80 1 I I $0.43 1 I I $748.20 1 I I $0.421 I I $730.80 1 I 110. 1 PAINT TRAFFIC STRIPE-S.D. #39A 1 I I 824 1 LF 1 1 $0.60 1 $494.40 1 $0.20 1 $164.801 $0.22 1 $181.28 1 $0.43 1 $354.32 1 $0.42 1 $346.08 1 I 111. 1 PAINT STOP BARS 1 I I I I 81 I I II EA 1 1 II I $0.501 I I $40,501 I I $1.50 1 I I $121.50 1 I I $1.651 I I $133.65 1 I I $41.42 1 I I $3,355.02 1 I I $42.00 1 I I $3,402.00 1 I 112. 1 PAINT CROSSWALKS I I I f 291 I EA 11 II $25.001 I $725.001 I $170.001 I $4,930.001 I $187.001 I $5,423.001 I $107.001 I $3,103.001 I $105.001 I $3,045.001 i 113. 1PAINT STOP" 1 I I 791 EA I I $100.001 $7,900.001 $40.001 $3,160.001 $44.001 $3,476.001 $32.001 $2,528.001 $31.501 $2,488.501 I 114. 1PAINT'AHEAD" 1 I I I I 101 I II EA I I II I $30.001 I I $300.001 I I $50.001 I I $500.001 I I $55.001 I I $560.001 I I $42.001 I I $420.001 I I $42.001 I I $420.001 I 115. 1 PAINT "YIELD" 1 I I 4 1 EA 11 $40.00 1 $160.001 $50.00 1 $2()0.001 $55.00 1 $220.00 1 $42.00 1 $168.00 1 $42.00 1 $168.001 I 116. 1 PAINT "SCHOOL' I I I I 21 I II EA 11 I $40.001 I $840.001 I $50.001 I $1,050.001 I $55.001 I $1,155.001 I $42.001 I $882.001 I $42.001 I $882.001 I 117. 1 PAINT "25' 1 I I 3 1 II EA 1 1 I $50.00 1 I $150.00 1 I $25A0 1 I $75.00 1 I $27.50 1 I $82.50 1 I $22.00 1 I $66.00 1 I $21.00 1 I $63.00 1 I I 118. 1 PAINT 'XING" 1 I I I I 211 I II EA 11 II I $15.001 I $315.001 I $50.001 I $1,050.001 I $55.001 I $1,155.001 I $40.001 I $840.001 i $42.001 I $882.001 119. 1 PAINT 'BIKE LANE' 1 I I I 31 I EA II II I $30.001 I I $90.001 I I $60.001 I I $180.001 I I $66.001 I I $198.001 I I $32.001 I I $96.001 I I $31.501 I I $94.501 I 120. 1 PAINT 'SLOW" 1 I 201 EA 11 $30.001 $600.001 $50.001 $1,000.001 $55.001 $1,100.001 $42.001 $840.001 $42.001 $&10.001 I I 121, 1PAINT'ONLY' 1 I I I 31 II EA 11 I $30.001 I $90.001 I $50.001 I $150.001 I $55.001 I $165.001 I $45.001 I $135.001 I $42.001 I $126.001 I 122. 1 PAINT 'PED" 1 I I I I 1 I I II EA 11 II I $15.001 I I $15.001 I I $50.001 I I $50.001 I I $55.001 I I $55.001 I I $35.001 I I $35.001 I I $31.501 I I $31.501 I 123. 1 PAINT "RXR' I I I I 1 1 I EA 1 1 II $30.00 1 I $30.00 1 I $100.00 1 I $100.00 1 I $110.001 I $110.00 1 I $55.001 I $55.001 I $52.50 1 I $52.50 1 I 124. 1PAINTARROWS 1 I I 101 EA 11 $25.001 $250.001 $50.001 $500.001 $55.001 $550.001 $35.001 $350.001 $31.501 $315.001 I 125. 1 PAINT PARKING STALLS 1 I I I I 2161 I II EA 11 II I $15.001 I I $3,240.001 I I $8.001 I I $1,728.001 I I $8.801 I I $1,900.801 I I $5.501 i I $1,188.001 I I $5.251 I I $1,134.001 I 126. 1 PAINT HANDICAP PARKING STALLS 1 I I I 7 1 I EA 1 1 II $30.00 1 I $210.00 1 I $50.00 1 I $350.00 1 I $55.001 I $385.00 1 I $55.00 1 I $385.001 I $52.50 1 I $367.50 1 I I 1 TOTAL I II I I I I I 1 I I $269,299•85 1 I I 1 I I $204,324.27 1 I I 1 I 1 $216,317.59 1 I I 1 I I $232,052.03 I I I I $295,345.56 1 CITY OF SARATOGA . SANTA CLARA COUNTY, CALIFORNIA CONTRACT FOR PUBLIC WORKS CONSTRUCTION 1994 STREET MAINTENANCE PROGRAM THIS CONTRACT, made this 9th day of August, 1994, by and between the City of Saratoga, a Municipal Corporation, in Santa Clara County, California, hereinafter called the City, and Valley Slurry Seal Co. hereinafter called.the Contractor. WITNESSETH: WHEREAS, the City has caused to be prepared in the manner prescribed by law, plans, specifications and other contract documents, for the work herein described and shown and has approved and adopted these contract documents, specifications and plans. and has caused to be published in the manner and for the time required by law, a Notice Inviting Sealed Bids for doing the work in accordance with the terms of this Contract, and WHEREAS, the Contractor in response to said Notice has submitted to the City a sealed bid proposal accompanied by a bid guaranty in an amount not less than ten percent (10 %) of the amount bid for the construction of all of the proposed work in accordance with the terms of this Contract, and WHEREAS, the City, in the manner prescribed by law, has publicly opened, examined and canvassed the bids submitted and as a result has determined and declared the Contractor -to be the lowest responsible bidder and has duly awarded to. the Contractor a contract for all of the work and for the sum or sums named in the bid proposal and in this Contract. NOW, THEREFORE, THE PARTIES AGREE AS FOLLOWS: ARTICLE I. WORK TO BE DONE: That the Contractor shall provide all necessary labor, machinery, tools, apparatus and other means of construction; shall furnish all materials, superintendence and overhead expenses of whatever nature necessary to construct all of the improvements for the City of Saratoga in conformity with the plans, specifications and other contract documents and according to such instructions as may be given by the Saratoga Director of Public Works or his authorized agent 17 ARTICLE II. CONTRACT PRICES Except as provided in Section IV B of the Specifications ( "Changes and Extra Work "), the City shall pay the Contractor according to the prices stated in the bid proposal submitted by the Contractor, which shall include all applicable taxes, for complete performance of the work. The Contractor hereby agrees to accept such payment as full compensation for all materials and.appliances necessary to complete the work; for all loss or damage arising from the work or from action of the elements, or from any unforeseen obstruction or difficulties which may be encountered in the prosecution of the work; incurred in and in consequence of the suspension or discontinuance of the work; as hereby specified; for all liabili- ties and other insurance; for all fees or royalties or other ex- penses on account of any patent or patents; for all overhead and other expenses incident to the work and expected profits; and for well and faithfully performing and completing the work within the time frame specified in the Notice to Proceed, all according to the contract plans and specifications, the details and instructions, and the requirements of the City. ARTICLE III. PARTS OF THE CONTRACT: That the complete contract document consists of the following: 1. Notice Inviting Sealed Bids 6. Performance Bond 2. Bid Proposal 7. Labor and Material Bond 3. Bidder's Bond or Bid Guaranty 8. Plans 4. Contract for Public Works 9. Specifications Construction 10. Insurance Certificates 5. Hold Harmless Clause 11. Prevailing Wage Rate In case of any conflict between this Contract and any other part of the contract, this Contract shall be binding. IN WITNESS WHEREOF, the City has caused its corporate name to be hereunto subscribed and its corporate seal to be hereunto affixed by its City Manager and its City Clerk thereunto duly authorized and the Contractor has executed these presents the day and year hereinabove written. 18 AWARDED BY CITY COUNCIL: Date : August 9, 1994 ATTEST: City Clerk The foregoing Contract is approved as to form this day of , 19 City Attorney 19 CITY OF SARATOGA: CONTRACTOR: By Title License No. Tax ID or SSN SARATOGA CITY COUNCIL EXECUTIVE SUMMARY NO. 2-4e? MEETING DATE: AUGUST 9, 1994 ORIGINATING DEPT.: PUBLIC WORKS AGENDA ITEM CITY MGR.: DEPT. HEAD: SUBJECT: 1994 Minor Concrete Repair Program, Award of Construction Contract Recommended Motion(s): 1. Move to declare Valley Concrete, Inc. of San Jose to be the lowest responsible bidder on the project. 2. Move to award a standard construction contract to Valley Concrete, Inc. in the amount of $10,540. 3. Move to authorize staff to execute change orders to the contract up to $4,460. Report Summary: Bids for the 1994 Minor Concrete Repair Program were solicited utilizing the informal bidding procedures contained in Article 12 -15 of the Municipal Code. Only two contractors responded to the City's solicitation, and copies of the bids received are attached. Valley Concrete, Inc. of San Jose submitted the lowest bid of $10,540, and staff has determined that this bid is responsive to the solicitation for bids. Therefor, it is recommended that the Council declare Valley Concrete, Inc. to be the lowest responsible bidder on the project and award a standard construction contract to this firm in the amount of their bid. Further, it is recommended that the Council authorize staff to execute change orders to the contract up to an amount of $4,460 to allow for additional work to be done and which may not yet have been identified by staff. Fiscal Impacts: Funds for the Minor Concrete Repair Program are budgeted in Program No. 32 (Sidewalks and Trails) , Account No. 4530 (Repair /Maintenance) . Sufficient funds are budgeted in the adopted budget to cover the base contract amount and,the requested change order authority. Advertising, Noticing and Public Contact: Nothing additional. Consequences of Not Acting on the Recommended Motions: The Council would not declare Valley Concrete, Inc. to be the lowest responsible bidder and a construction contract would not be awarded to that firm. The Council may make specific findings to declare the other bidder to be the lowest responsible bidder, or reject both bids and direct staff to solicit new bids for the project. The Council has up to 30 days within which to make its, decision. Follow Up Actions: A standard construction contract will be signed, and the Contractor will be authorized to proceed with the work. The work will be closely coordinated with both the Pavement Management and Street Maintenance projects and should be complete by the middle of September.. Attachments: 1. Bids from Valley Concrete, Inc. dated July 9, and Jos. J. Albanese, Inc. dated July 15. f 1020 RUFF DRIVE \ STATE LIC. #60307! SAN JOSE, R 8E ` IN BUSINESS SINCE 1971 oncrete, �nc. SOURCE Brim Meg -W-een (408) 267.809f • FAX (408) 287 -8095 INVOICE uU$fllM6R . HM PHONE City of Saratoga w" "O'4' 867 -3438 Ex. 245 AmxAF.SS 19700 Allendale c "r Saratoga ar aT� 7 -9 -94 TRACTOR AND TRUCK EF NO DIAGRAM 4 19320 Melinda Circle - 22' X 4' S/W - $ 554.00 2. 19128 Brookviev Dr. 25' C/G = JACKHAMMER (Y' NO DISPOSAL LOAD 12403 Fredricks Burg Dr. 79' X 4 NO CONCRETE SAWING S/W NO FACE OF STEPS EXPOSED YES NO EXPANSION JOINT YES NO TYPE DEEP Burg Ct. 2.5' X 4' REDWOOD YES NO TYPE / SIZE 3.5' S/W = FINISH YES NO ROCK YES NO TYPE / SIZE 9- 20424 Glasgow 10' C/C = CONCRETE MIX ES NO SACK 27' X 6' S/W = LAMP BLACK 11. NO NO. PINTS PER YARD 13. 14098 Loan Rio 27' C/C - WIRE MESH YES NO OTHER INSTRUCTIONS: One CROSS, STREETS 4 19320 Melinda Circle - 22' X 4' S/W - $ 554.00 2. 19128 Brookviev Dr. 25' C/G = 625 -00 3. 20120 Seagull Wy. 20' C/G 500.00 4. 12403 Fredricks Burg Dr. 79' X 4 S/W 1991.00 5. Small Patch Job intersection of Fredricks Burg Dr. + Fredricks Burg Ct. 2.5' X 4' 63.00 6. Via Real at Bridge 8' C/G + 8' X 3.5' S/W = 376.00 7. 19712 Glen Brae 40' C/G 1000.00 S. 20207 Glasgow 1' Curb patch 35.00 9- 20424 Glasgow 10' C/C = 250.00 10. 12297 Via Ron Cole By the R.R Tracks 27' X 6' S/W = 1021.00 11. 20210 Herrick Dr. 75' C/G B S R 1875.00 13. 14098 Loan Rio 27' C/C - 675.00 14. 18965 Allcott 63' C/G = 1575.00 NOT RESPONSIBLE FOR ANY IN GROUND UTILITIES /IRRIGATION LINES ** Not Responsible Cracks * AUTHORIZATION TO START WORK DATE TO START (WEATHER PERMITTING) APPROVAL # 10, sy0 Total $ FOR JOB SCHEDULING OR TOTAL BALANCE _ ANY OTHER QUESTIONS CALL 287. W91 EXTRA CHAME FOR CONCRETE REMOVAL DOYM PAYMENTS THICKER THAN 4" OR STEEL REINFORCED *COD BALANCE DAY OF POUR • `V (Jos. J. Albanese, Inc. 1��Ifl� V CONTRACTORS WCENSE N0.29MM 840.70 PARKER ST. P.O. BOX 667 SANTA CI,ARA, CA 95052.0667 July 15, 1994 City of Saratoga 1:3777 rruitvale Avenue Saratoga, CA. 95070 Attn: Mr. Bryan D, M(:Wijeen Re: Curb, Gutter and, Sidewalk Itrpair,6 Saratoga, CA. Dear Bryan: M 727 -5700 FAX ig 727 -0366 We am pleased to i,ubmit ottr uuot.a,t.ion on the c-•oric:rel,e work for the curb, gutter and ,idnwnil, je�,ttir.s 7 „•c�.je.:<t locY;,ez�l ir) Saraatoga. Please note our scoper US' woIr.•k, qunLific_nL.ions,, o Cli.l5ion5 and price. Supply labor, innt.eri a 1 rlrici r'ct�1 i pm�: n.t t. r_, c�oral> r:� i,c t.11G t'c�].1 ow i rig items: 1. Remove rind rCPiRr_•e c.ir -cm ge(j ci.ti•b, guL1.rr, sidewalk acid pavemeriL a(. v :r•i c,ias loc.a,Lions as dct.ttiled on the attached sheet,. Qualific:at,.ions: 1 • nur scone of wo.r•k i etc; ludes : s nwc :'i t:t, i. ng , demo i. i t, i on , dump fees, r•es;r•rid i rig, formwork; Sut.�I� I pla.r_e aria' I i n i sh ready mix c:oncrrotc, cUrirrg comPound, 6” AC t)Kt,r.:h in. front of curb and gutter-,' and c: f na,n up, 2 • f avcment ref,)a i r is based on h inches or' deep li i'L aL the IiP of gut-tcr and 3 inc he s of.' AU 01" 6 itic h"s of aggregate base in all o0ier locations. Exclusions: 1. Pnrmits, bonds and testing, 2 • Engineering acid s t.ak i r-tg . 3. Any other work nOt. [toted iri t.l.i i � yi,�c7 ?a.tlnti. Comfi,inte for the .4um or- ........ ,$20,826.00 This Price is Leased or). ?, JOh'.." Itp 111t:!c! proposal May be withdr,,,.iwrj ty t 1 T1 J 1) 1 Y Phis N f ivc.' ( 45 ) days J.f not j.! C with in for,t,h- Thn-yik you for the oppoi,j.j,,jj.j.)- (-)f project T hopi!� we. mn -1 z' �4kjC)tL-1t,i0l, or, 1, his f Uture,' ,v, L)t. (1j, SOME, to Yf.)14 j.11 the near* JOS. J. ALBANKSE, INC. D-�` David P. Olivas DO/nm,.). 4.4455 ACCEPTANCP�, OF PROPOSAI, - 1,ho above. conditions are af)(j sire lor)LI, and authorized to (3c) I.,fle wc)r-�: re You a.Z,L. v(l Amount Ac•eptnd, DMI-F, of