HomeMy WebLinkAbout12-09-1981 CITY COUNCIL AGENDACI`T'Y OF SARAI IMN
A Initial:
AGENDA BILL NO. Dept. lid.
LATE: December 9, 1981
C. Att
DEP .:'TENT: City Manager C. Mgr.
SUBJECT: Renewal of Contract for City Attorney's Services
Issue Summary
In July, 1980, the City Council entered into a one -year contract for provision
of City Attorney's services with the firm of Atkinson - Farasyn. That contract
expired June 30, 1981, and has continued on a month to month basis since -then.
A new contract covering the period January 1 to December 31, 1.982, has been
prepared and submitted for your consideration. The new contract is, in substance,
identical to the previous one with minor changes in language to clarify certain
provisions. There is no change in rates from the prior agreement.
Reccmnendation
Approve the agreement as submitted for attorney's services for the period
January 1 through December 31, 1982..
Fiscal Impacts
No increase in rates for attorney's services; Council has provided budget appro-
priations for the remainder of the current fiscal year at the level of 45 Fours
per month.
E:.hibits /Attachm`nts
#1. City Manager memo to Council dated December 2, 1981
#2. Proposed contract with Atkinson - Farasyn dated
Council Action
12/16: Mallory /Clevenger moved to approve contract for one year. Passed 5 -0;
NE�2i1OO RAADt1,tiil
/ Z_ // ( ,
uguw @:T 0&U&&'9Q)0&
13777 FRUITVALE AVENUE • SARATOGA, CALIFORNIA 95070
(408) 867 -3438
TO: City Council DATE: December 2, 1981
FROM: City Manager
SUBJECT: Contract for City Attorney Services
The City's contract for Attorney Services with Atkinson - Farasyn ran
for &.one year term expiring June 30, 1981. Because the City at
that time was confronted by a number of critical issues, the matter
was not brought up.
Paul has submitted a new proposed contract to cover the period
January 1 to June 30, 1982. The terms and conditions of the new
contract are essentially the same as our current interpretation of
the previous contract. There have been some changes in language to
clarify the uncertainty over the application of the 35 hour minimum
to the work performed. Section 4 of this draft makes clear that the
retainer covers only the first 35 hours each month for all covered
services.
If the Council desires to continue the services we have been receiving
from Atkinson - Farasyn, I recommend you consider requesting the agree-
ment be set for a full year rather than six months. Renewal of the
agreement on a calendar year basis rather than fiscal year would be
more convenient for the City.
U
J . wYhe Derr tz
ck
. ..
PAUL B. SMITH
ERIC L. FARASYN
DUNHAM B. SHERER
LEONARD 1. SIEGAL
HAROLD S.TOPPEL
FRANK E. MAYO
STEVEN G. BAIRD
ATKINSON • FARASYN
ATTORNEYS AT LAW
660 WEST DANA STREET
P. O. BOX 279
MOUNTAIN VIEW, CALIFORNIA 94042
( 415) 967-6941
November 12, 1981
Mr. J. Wayne Dernetz
City Manager
13777 Fruitvale Avenue
Saratoga, CA 95070
Dear Wayne:
I. M. ATKINSON, (nenneD)
L. M. FARASYN, (1915-1979)
The enclosed letter is a new proposed arrangement which
helps to clarify the areas the Council is concerned about. Please
read it over and give me any comments you might have before you
submit it to the Council.
PBS /d
Enc.
VerWB.mith
urs,
Pau
Saratoga City Attorney
/ CITY OF SARATOGA
Initial:
AGENDA BILL NO Dept. Hd.
DATE: December 9, 1981 C. Att
DEPARTMENT City Man age r C. Mg
-------------------------------------------------------------------------- /I,/ ------------
SUBJECT: Committee on Financial Concerns
Issue Suffmary
City Council has directed staff to prepare an outline for the formation of
a citizens committee to investigate financial concerns now facing the City
government. These concerns deal essentially with an examination of our
present revenue base and determination of future revenue opportunities as
well as a look at our present expenditure patterns with the view toward
establishment of priorities and areas for possible savings. Pursuant to
your direction, the City Manager presented a report on December 2, 1981, which
outlined the purposes and organization of such a committee, and provided the
draft resolution for your consideration that would establish the committee.
Recommendation
Consider the report and recommendations; if desired
establishing the committee. If adopted, designate'
as chairman of the committee and work with Council
other interested citizens.
Fiscal Impacts
adopt the resolution
an individual to serve
in recruiting and selecting
An allocation of staff time by the City Manager and Finance Director will be
required to coordinate the activities of the committee and provide necessary
information. Additional time from clerical assistance may also be required.
Depending on the areas of interest for the committee, some professional techni-
cal advice may also be needed. No estimate of the cost available, at this time.
Exhibits /Attachments
Report of City Manager dated December 2, 1981
Draft resolution
Council Action
12/16: Jensen/Mallory moved to adopt resolution 1048. Passed 5 -0.
��1 E N1 OO R A N D �1 NI
09'KW @:T O&UMEXOM&
13777 FRUITVALE "AVENUE • SARATOGA, CALIFORNIA 95070
(408) 867 -3438 .
TO: The honorable City Council
FROM: J. W. Dernetz, City Manager
DATE: December 2, 1981
SUBJECT: Formation of a Citizens Committee on the City's Financial Concerns
The attached resolution for your consideration would establish a
Citizens Task Committee to explore the City's financial concerns. You
have directed me to provide this document by this date. I recommend
you review this document and consider its adoption at your next meeting.
The proposed resolution outlines the mission or purpose of the Committee,
which is to investigate the current prospects for maintaining the long
term fiscal soundness of the City government while meeting its service
requirements. Specific tasks are also listed, among which is that of
identifying opportunities for new or additional revenues.
The organization of the Committee is suggested to follow that of the
25th Anniversary Committee; i.e. the Council would first appoint a
Chairperson who would be capable of organizing and carrying out the
committee purpose. The number and selection of additional members also
would be determined by the Council following consultation with the
Chairperson and your recruitment and selection efforts. In forming the
Committee, it is suggested that the Council adhere to two precepts:
1) Keep the number of members to a reasonably small number;
actually, not more than the number needed to carry out
the tasks.
2) Solicit individuals with the necessary skills and knowledge;
people who have business, financial, legal and government
backgrounds. It is likely you will have to contact such
people individually and urge them to respond.
The scope of the work is broad and complex. Information is not readily
available in one convenient source. Assembling and compiling data and
determining available opportunities within present constraints will be
a demanding challenge. The nature of what you may expect to be accomp-
lished calls for a committee that will work effectively and deliberately
toward the objectives. I look forward to working closely with such a
committee.
i
4�
RESOLUTION NO.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SARATOGA
ESTABLISHING CITIZEN TASK FORCES FOR THE INVESTIGATION
AND RECOMMENDATION OF ALTEP.NP_TIVE POLICIES TO MAINTAIN
THE LONG TERM. FISCAL SOUNDNESS OF THE CITY GOVERNMENT
WHEREAS, there have occurred over the past few years significant
changes in the financial capabilities of local governments in California;
and
WHEREAS, there is concern that revenues for the City of
Saratoga may no longer be adequate to support the levels of service
that are desired or needed by Saratoga citizens; and
WHEREAS, a comprehensive and thorough review of the fiscal
adequacy and reliability of the City revenue base and expenditure
requirements is needed to help determine future policy directions; and
WHEREAS, there are among the residents and citizens of Saratoga
many individuals whose skills and knowledge in the field of financial
management and analysis are needed by the City to evaluate the present
and long term financial adequacy of the City financial resources;
NOW, THEREFORE BE IT RESOLVED THAT:
1. There is hereby established an ad hoc Citizens Task
Committee, the mission of which is to investigate
and report upon the current prospects for the City
government to maintain a fiscally sound condition
while continuing to meet its service requirements
and responsibilities.
2. In carrying out its mission, it is the desire of
the City Council that this Citizens Committee
accomplish the following tasks:
(i) Examine the current revenue structure of City
government, together with applicable powers
and limitations, to determine the adequacy of
available revenues to meet future needs;
(ii) Identify available opportunities for adding
new or increasing present revenues, if needed,
and outline steps necessary to accomplish
these opportunities.
(iii) Examine current expenditure allocations of the
City government and project future requirements
for maintaining adequate levels of service in
each of the principal service functions.
(iv) Identify and recon•Jnend priorities that would
be followed by the City government for meeting
service responsibilities and obligations, in-
cluding consideration of service areas that
are presently not being adequately addressed.
3. It shall be the responsibility of the City Council to
select a Chairperson of the Citizens Committee based
upon the suggestion and nomination of its members.
Such additional members of the Committee and the
appointment of each shall be determined by the City
Council following an appropriate period for the soli-
citation and evaluation of candidates. The designated
Chairperson of the Committee shall advise and assist
the City Council in this process.
• ter- _-'�.l
4. Once established, the Committee will endeavor
to complete its tasks within four months. The
Chairperson shall provide the City Council with
monthly progress reports during the course of
the Committee's efforts. All reasonable
expenses of the Committee members shall be re-
imbursed by the City, upon the approval of the
City Council. The City ?tanager shall provide
coordination of effort and any available staff
assistance, as needed to the Committee.
5. It is the further intent of the City Council that
the findings and recommendations of the Citizens
Committee regarding the financial structure of
the City government be as broadly descriptive
and explanatory as feasible to better inform
Saratoga's residents and citizens on this issue.
The above
and foregoing resolution was passed and adopted at a
regular
meeting of the City Council of the City of Saratoga held
on the
day of 1981, by the following
vote:
s ,�sv';z+�a,,r _ Y _.i= ....+fi'.:3r ate, f. •'..,. Cf
AYES:
NOES:
ABSENT:
MAYOR
ATTEST:
CITY CLERK
AGENDA BILL NO.
DATE: 12/9/81
CITY OF SARATOGA
Initial:
Dept. Hd
C. Atty.
DEPARTMENT:--Planning
---------------------------------------------------------------------------------------
& Policy Analysis
C.
Mgr.
SUBJECr.
Authorization for City Manager
to Sign for State
Subvention Funds
Issue Summary Under the provision of the California Administrative Code,
and E overnment Code, the City is required to approve a Resolution
giving one person the authority to sign for State subvention funds for
Williamson Act Lands. The position of City Manager has traditionally
signed for all subvention funds for Williamson Act Lands.
Recommendation Approve the attached Resolution giving the position of City
Manager authority to sign for State subvention funds.
Fiscal Impacts None
Exhibits /Attachments
Council Action
Resolution
12/16: Mallory/ Watson moved approval. Passed 5 -0.
RESOLUTION NO.
RESOLUTION AUTHORIZING THE CITY MANAGER
OF THE CITY OF SARATOGA TO SIGN FOR
STATE SUBVENTION FUNDS
WHEREAS, the State of California requires that each City
entitled to Williamson Act subvention funds, appoint one person
with the authority to sign all subvention fund applications and
WHEREAS, the City Council finds it appropriate to authorize
the City Manager to sign for State subvention funds,
NOW, THEREFORE BE IT RESOLVED that the City Council does
hereby ordain by the following vote:
AYES:
NOES:
ABSTAIN:
MAYOR
ATTEST:
CITY CLERK
1
• CITY OF SARATOGA
J
AGENDA BILL No. r -74 Initial: Dept. Hd..
DATE: 12/9/81 C. Atty.
DEPARTMENT. Planning & Policy Analysis C. Mgr.
---------------------------------------------------------------------------------------
SUBJECT: 19 81- 82 Capital Improvement Budget
Issue Summary The Council reviewed the Capital Improvement Program (projects
for 1 -3 years) at a study session and indicated those projects which they
wished to see completed this year. Staff reviewed the projects and then
completed a Needs Assessment for each major item. In accord with State
law, the Planning Commission has reviewed the Capital Improvement Program and
has found it consistent with the General Plan.
` Reconmendation Approve the attached Resolution 1. after reviewing the
Capital Improvement Budget. The total Capital Improvement Budget is
$1,608,943.
Fiscal Impacts $1,608,943
Exhibits /Attachments
1. Capital Improvement Budget FY 1981 -82
2. Resolution adopting above
Council Action
12/16: Continued to 1/6.
Qq 1X0&
kk�
i
�'
4 w84 •':ir
o
REPORT TO MAYOR AND
CITY COUNCIL
DATE: 12/30/81
COUNCIL MEETING: 1/6/82
SUBJECT Capital Improvement Budget - FY 81 -82
The total Capital Improvement Budget is $10,000 higher than
originally submitted due to the following changes:
1. Deletion of $4,000 for Santa Clara County Information
Referral Service.
2. The addition of $14,000 for a 1 Ton Dump Truck.
The County of Santa Clara is not funding Information Referral,
therefore, the program will not need local support.
The additional $14,000 is to replace a 1 Ton Dump Truck which
was damaged as a result of a theft. (Please see Director of
Maintenance Service Report, page 26 of the Capital Improvement
Budget.)
4S.Rlbinson, Jr.
Director of Planning & Policy Analysis
INDEX
Page
Resolution No. -
Approving Capital Improvement
Budget
1
Current Revenues as
of 6/30/81
2
Projected Revenues
vs. Proposed Expenditure
3
Park Projects
4
Street and Drainage
Projects
5
Civic Building Projects
6
Capital Purchases
7-8
Community Activity
Support
9
City -wide Projects
9
NEEDS ASSESSMENT ANALYSIS
Park Projects
10
Street and Drainage
Projects
11 -13
Civic Building
14 -16
Capital Purchases
17-22
Community Activity
Support
23 -24
City -wide
25
CHART 1 - CURRENT REVENUES
The following is a list of fund balances utilized to support
the Capital Improvement and Capital Outlay Budget. These figures
are as of June 30, 1981 plus estimated projections.
Fund
30 Revenue Sharing
45 -46 Gas Tax Matching
87 Storm Drainage
55 Park Development
55 Roberti- Z'Berg
State Bond Act (Parks)
50 Replacement Fund
35 HCDA
TDA
Sunland Park
TOTAL
Total fund dependent on development activity for the remainder of
this fiscal year.
9
81 -82
6/30/81
Projected
Balance
Revenue
Total
487,701
$ 146,779
$ 634,480
739,224
357,300
1,096,524
344,041
70,000
414,041
364,085
100,000
4641085*
7,434
7,434
131,000
131,000
216,110
216,110
14,195
348,222
362,417
623
52,800
53,423
27,000
27,000
2,192,979
1,213,535
3,406,514
Total fund dependent on development activity for the remainder of
this fiscal year.
9
CHART II - PROJECTED REVENUES VS.
PROPOSED CAPITAL EXPENDITURES
The following is a comparison by fund . of revenues and proposed
expenditures.
Fund
Proposed Capital
Improvement Projects
30
Revenue Sharing
45 -45
Gas Tax Matching
87
Storm Drainage
55
Park Development
55
Roberti- Z'Berg
131,000
State Bond Act (Parks)
50
Replacement Fund
35
HCDA
53,423
TDA
27,000
Sunland Park
TOTAL
Projected
Fund Balance
Proposed Capital
Improvement Projects
$ 634,480
$ 269,221
1,096,524
511,500
414,041
27,000
464,085
.242,000
7,434
131,000
131,000
216,110
362,417
348,422
53,423
52,800
27,000
27,000
$ 3,406,514
$ 1,608,943
I -.
1981-82 PRELIMINARY CAPITAL IMPROVEMENT BUDGET
FUND ACCOUNT
AMDUNi' REVENUE PARK STATE RMERTI STORM GAS TAX
P%UECP DESCRIPTION PRIORITY REQUESTED SHARING DEVELOPP2W PARK BOND Z -BERG DRAIN MATCHING
I. Park Projects
Blaney Lights - -
Conversion 3,000 3,000
E1 Quito Park
Acquisition (Partial 320;000 189,000 131,000
Only)
Hakone Driveway 50,000 .50,000
TOTAL $ 373,000
$ 242, 000 $ 131,000
HCDA SCNLAND PARK
Cat
i�
L �
{L .
n
v
5i
r`r -
4
. •rs
rY
HCDA SCNLAND PARK
Cat
i�
L �
{L .
n
v
5i
r`r -
tY
HCDA SCNLAND PARK
Cat
i�
L �
{L .
n
v
5i
r`r -
• to
1981 -82 PRELIMINARY CAPITAL IMPROVEMENT BUDGET
FUND ACCOUNT
MUUNT REVENUE PARK STATE RBERTI STORM GAS TAX SPECIAL
PRC1JECP DESCRIPTION PRIORITY REQUESTED SHARING DEVELOPtENT PARK BCND Z -BERG DRAIN MATCHING TDA HCDA SUNIAND PAW
II.
Streets
Bike Lanes
1.
Fruitvale Ave.-
32,800
2.
Quito Road
20,000
Storn Drain System
1.
Bank Mill (completed)
15,000
.2.
Cordwood Court
12,000
Street Improvement
1,
Prospect - Scully
to Plumas
30,000
2.
Prospect - Jamestown
to Saratoga- Sunnyvale Rd.
5,500
3.
Annual Resurfacing
250,000
4.
Allendale /Cox
Reconstruction
200,000
5.
City Hall /Allendale Ave.
18,000
6.
Prospect /Miller
Traffic Control
8,000
7.
McCoy /Quito (underway)
27,000
8.
Paul Street.
94,700
Improvements
TOTAL $
713,000
15,000
12,000
30,000
5,500
250,000
200,000
18,000
8,000
32,800
20,000
94,700
27,000
$27,000 511,500 52,800 94,700 27,000
mr)UNT
PROJECT DESCRIPTION -
III.Buildings
Civic Theatre &
Community Center
1981 -82 PRELIMINARY CAPITAL IMPROVEMENT BUDGET
FUND ACCOUNT
REVENUE PARK STATE RCBERTI STORM GAS TAX SPECIAL
SHARING DEVEIAPDIIW PARK BCND Z -BERG DRAIN MATCHING TDA HCDA SLN11ND PARK
Carpet Replacement 3,700 3,700 rJ k
c �-
Civic Theatre Water Jbi�,�iLevl�u��
Cooling Tower 2,500 2,500 <y
Repaint McWilliams a
House 2,000 2 000 ✓�" C "G "i�/l /��' "v
City Hall Remodel 5 2, 722 40 , 000 '��'�' l/ " 12,722
Senior Citizen Center
(Underway) 241,000 241,000
TOTAL $ 301,922 $.48,200
$ 253,722
re
C
r
ti:
^
Z, Y
Nd
PROJECT DESCRIPTION
ik
A; J. fi
C
1981 -82 PRELIMINARY CAPITAL IMPROVEMENT BUDGET
FUND ACCOUNT
ADDUNT REVEN[JE PARK STATE RMERTI STOMI GAS TAX SPECIAL
EOUESTED SHARING DEVELOP= PARK BCND Z -BERG DRAIN MATCHING TDA HCDA SUNIAND PARK
IV. Capital Purchases
Radio for Truck 1,300 1,300
Gas Power Hedge
Trimmer, Snapper
Mower: Echo Blower
Purchase of Three (3)
1,285
18,000
1,285
18,000
�ry
—ke-f
0
Admin. Vehicles
Saratoga Village
Sign
2,500
2,500
Blaney Plaza
Purchase of Two (2)
Speed Buffers
1,200
1,200
Replace 1/2 Ton
Pickup
8,500
8,500
Purchase of New Power
Street Sweep
25,000
25,000
Replacement of 8 Ton
Dump Truck (Patch Truck)
30,000
30,000
Computer/Word Processor
P
25,000
25,000
07./
Discharge Deck for Toro
Motor
2,150
2,150
1 Ton Dump Truck
14,000
14,000
Total
$128,935
$128,935
*See Report Director of
Maintenance
Service, page 26.
7
�
l
7.
4
t{
t,
,
41
try
1981 -82
PRELIMINARY CAPITAL IMPROVEMENT BUDGET
FUND ACCOUNT
AMJUNT
REVENUE
PARK STATE ROBERTI STORM
GAS TAX
SPECIAL
PPDJECr DESCRIPTION PRIORITY REQUESTED
SHARING
DEVELOPMENT PARK BOND Z -BERG DRAIN
MATCHING TDA
HCDA SUNLAND PARK
IBM Typewriter-
Commununitit Center
Community
995
995
/
Purchase of Twelve .
(12) New Tables
(Community Center)
350
350
Replacement of
1,450
1,450
Regulation Pool
Table (Senior Citizen
Request)
TOTAL
$ 2,795
$ 2,795
8
:t
PROJECT DESCRIPTION PRIORITY
V. Community Activity
Support
Saratoga Chamber of
Commerce
Civic Theatre Lighting
Booth (Saratoga Drama
Group)
Saratoga Community
Garden Sustaining
Saratoga Community
Garden, Irr. System
Santa Clara County
Information & Referral
Service
Youth Science Institute
Central Counties Safety
Catholic Social Service
VI.City Wide Project
MIDUNT
1,000
2,700
1,000
1,500
4.7699
1,500
1,000
1,691
981-82 PRELIMINARY CAPITAL I?4PROVEPIENT BUDGET
L
FUND ACCOUNT
REVENUE PAI'd< STATE PCEERTI STORM GAS TAX SPECIAL
SHARING DEVELOP= PAW BOND Z-BERG DRAIN MATCHING TDA HCDA SUNLAND PARK
1,000 Oro
2,700
(NotOunded by County
1,000
0
1,500
Program
47959
(NotOunded by County
1,500
0
Program
14
Yt
1,000
Financial Forecast Committee
1,691
1) 0
Community Service Officer
30,000
30,000
Program
14
Yt
Financial Forecast Committee
2,500
2,500
Solar Utilities Study
1,400
1,400
Purchase of City Phone
M-/Ij
System
45,000
45,000
41?jji.1"
TOTAL
$ 9,291
89,291
9
14
Yt
NEEDS ASSESSMENT ANALYSIS
FOR CAPITAL IMPROVEMENT BUDGET PROJECTS 1981 - 1982
PARK PROJECTS
Conversion of Lights at Blaney Plaza
1. Description: Convert the lights at Blaney Plaza from gas to electrical source
of power. Cost - $3,000, recommended Revenue Sharing Funds.
2. Need: The project is necessary if we are to maintain lighting in Blaney Plaza,
P,G & E has notified us that effective January 1st, 1982, gas may not be used for
decorative lighting, and the gas will be cut to these lights. If we do not
re -wire electrically, there will be no lighting in Blaney Plaza.
3. Cost of Operation: It is not anticipated there will be any increased cost of
operation.
4. Cost of Maintenance: It is anticipated the cost of electricity for the lights
will be similiar to that of the cost of gas.
El Quito Park Acquisition
1. Description: Acquistion of E1 Quito Park from Moreland School District.
Estimated cost - unknown, request funds to be reserved $131,000 from 1976 and 1980
State Park Bond Funds, $189,00 from Park Development Fees, for downpayment.
2. Need: The City currently leases approximately seven acres from the Moreland School
District, the lease does not expire until 1992 and the City has first right of
purchase. The School District Board of Directors has not yet recommended sale,
but may declare the property surplus if the County lease for the building portion
ends. The City should consider this purchase to protect approximately $250,000
of developed park, which currently is the only open space in the entire residential
area. The Council has authorized the City Manager to begin negotiations.
3. Cost of Operation: No increase in cost of operation is to be expected.
4. Cost of Maintenance: No increase in cost of maintenance is to be expected above
and beyond what currently.exists.
Hakone Driveway
1. Description: Major repair to'slope and support of upper one -third of Hakone
roadway going into Hakone Gardens. Non - engineers estimate $50,000, recommended
from Park Development Fees.
2. Need: This portion of the access road to Hakone is in very bad condition. The
hillside below the road must have additional support for erosion and to prevent
cave -in, the roadway itself should be widened to eliminate the almost hairpin
curve and the road surface re -done.
3. Cost of Operation: It is anticipated there will be no increased cost but it is
likely there could be a decrease in annual cost of constantly trying to patch
this area of roadway.
4. Cost of Maintenance: No change.
A
STREET AND DRAINAGE PROJECTS
Cordwood Court Drainage Improvement
1. Description: Repave the intersection of Cordwood Court and Old Wood Road
and install storm drains to properly dispose of storm water. The project will
cost approximately $12,000 which will come from the Storm Drain Fund.
2. Need: Because of an improper design the pavement at this intersection is
falling apart. Storm water is allowed to run uncontrolled across the intersection.
This not only caused the pavement failure, but is also messy and unsightly.
3. Cost of Current Operation: If pavement deterioration is allowed to continue,
structural failure will occur which will be much more costly to correct.
Prospect /Miller Traffic Signal Controller Replacement
1. Description: Replace the malfunctioning non - serviceable traffic signal
controller. This is a joint project with the City of San Jose San Jose is
willing to act as the lead agency.
2. Need: The existing controller is malfunctioning. The controller is no longer
in production and the company which manufactured it is no longer making traffic
controllers. Parts are not available, therefore, it is not serviceable.
Allendale Avenue /City Hall Frontage Improvements
1. Description: This project will complete the improvement of Allendale Avenue
between Fruitvale Avenue and the Community Center. Concrete curb, gutters and
sidewalks will be constructed on both sides of Allendale with the cost being
prorated with the U.S. Postal Service. The project will also provide a left
turn lane at the intersection with Fruitvale Avenue and will close the
frontage road which runs in front of the Civic Theatre to motor vehicle traffic.
The City's share of these improvements is estimated to be $18,000 which will come
from Gas Tax.
2. Need: The overall project is required to comply with the mitigation recommendations
called for in the Post Office's E.I.R. The City is improving its frontage road
in conjunction with the Postal Service's project.
Fruitvale Avenue Bike Path /Lane - Quito Road Bike Path /Lane
1. Description: Fruitvale Avenue Bicycle Path /Lane
(Saratoga Avenue to Saratoga -Los Gatos Road) Cost $32,800
Quito Road Bicycle Path /Lane
(Yorkton Drive to Allendale Avenue)
ii
Cost $20,000
Source T.D.A.
Source T.D.A.
Fruitvale Avenue Bike Path /Lane - Quito Road Bike Path /Lane (continued)
2. Need: Both projects are intended to increase bicyclist safety on high volume
streets by providing bike lanes or paths. At these locations, both streets are
currently and have little or no shoulders on which to ride.
3. Cost of Current Operation: During the past ten or so years, bicycle travel has
increased markedly. Along with this increase in travel, bicycle accidents
have skyrocketed. To correct this situation, Federal and State Funds have been
available to local agencies.
4. Estimated Cost of Maintaining a New System: The only cost involved in the two
projects to the City is that of maintenance. To qualify for these funds, the
City must agree to maintain the completed improvements. The City presently spends
very little money in maintaining its bicycle facilities. These projects will add
approximately five miles of bicycle lanes /paths to the City's existing system
which should add approximately to our maintenance costs.
Prospect Road Improvements, Allendale Avenue and Cox Avenue Improvements, McCoy
Avenue Overlay, Annual Street Resurfacing Project
1. Description:
1. Prospect Road Cost $ 30,000 Source Gas Tax
(Plumas Drive to Scully Avenue)
2. Allendale Avenue Cost $200,000 Source Gas Tax
( Fruitvale Avenue to East of Dolphin)
and Cox Avenue
(Northerly side just east of Saratoga Avenue)
3. McCoy Avenue Cost ..$ 27000 Source Special
(Quito Road to Villanova) Assessment
4. Annual Street Resurfacing Cost $250,000 Source Gax Tax
2. Needs: These various projects all are needed to either resurface, repair or
reconstruct portions of City streets. Streets are designed to have a finite life
assuming maintenance procedures are preformed on both a routine and cyclical basis.
Without these maintenance procedures the City's streets will soon become unusable
and much more costly to re- build.
2. Cost of Current Operation: It is unfortunate that throughout the State, the cost
of street maintenance is being underfunded. The current City reserve of
unexpended Gas Tax together with its yearly Gas Tax allocation and the additional
allocation provided by S.B. 215 (Foran) will allow expenditures at this level
for the next two or three years, at the end of which time new revenue sources
must be found.
i?
Paul Avenue Improvement Project
1. Description: Widen, repave and install storm drainage system including
A.C. berms along both sides of Paul Avenue. This project is estimated
to cost $94,700 which will be funded through the H.C.D.A.
2. Need: Paul Avenue is a narrow, poorly defined roadway. Its lack of
definition is caused by random width and spot improvements. Storm water is
allowed to run off the pavement and onto private property. Lack of storm
water control has created puddling and roadside lakes during and after
rains.
3. Cost of Maintaining a New System: The proposed improvements will
substantially reduce maintenance costs of Paul Avenue.
t
13
BUILDINGS
CITY HALL REMODEL
I. Project Description - Remodeling of City Hall to accommodate
the recent City reorganization and to provide adequate
conference rooms for Council and Commission. The estimated
cost of the project is $40,000. The removal of archi-
tectual barriers, enlarging public bathrooms, providing hand
rails and some improved signage is estimated at $12,722.
II. Needs Assessment - The current design of City Hall is
inadequate to meet the City's needs. There is sufficient
area within the structure to accommodate all employees,
Council and staff conference rooms and a large Community
Development counter if the interior spaces were redesigned.
This current arrangement results in a loss of productive
hours due to inadequate design. In summary, the interior
spaces must be changed to meet the needs of the City.
III. Cost of Current Operation - There will be no change in
costs associated with the remodeling. There could be some
savings due to the redesign, by making the structure more
energy efficient.
IV. Estimated Cost of Maintaining a New System - Maintenance
for the building would not increase. The most significant
savings would be dependent upon how many of energy conserva-
tion measures were added to the building. The return on
the initial investment would vary with each piece of equip-
ment. The most significant cost savings is the increase in
productivity of the employees through the creation of an
acceptable environment.
Removal of architectural barriers, involves larger bathrooms,
and does represent a new cost.
Civic Theatre Water Cooling Tower
1. Description: Replace the water cooling tower for the Civic Theatre air
conditioning unit, estimated cost - $4,500, suggested source of funds Revenue
Sharing.
2. Need: The tower which cools the water which eventually provides air conditioning
for the Civic Theatre is malfunctioning and cannot be repaired. The motor which
operates the fan is on its last legs, the water cooling tower base which contains
the water is leaking, which causes new water to come into the unit constantly which
14
Civic Theatre Water Coolinq Tower (continued)
constant use of chemicals to eliminate the hardness of the water and therefore
eliminate build -up in the pipes. This malfunction is due primarily due old age
and the beating that the water cooling tower has taken since it was installed in
1968. We cannot operate the air conditioning of the Civic Theatre at normal
cooling capacity, there is a tremendous increase in energy used in order to operate
what cooling we have, and it is very likely with the next high level of need that
the water cooling tower will completely shut down and we will have no air conditioning
whatsoever. The air conditioning for the Civic Theatre is needed all year long
because of the use of the Theatre and the number of people who use it, and therefore
it is not strictly a summer or warm weather need.
3. Cost of Operation: We are currently expending good money after bad in attempting to
keep the water cooling tower repaired, the constant influx of fresh water is
causing hardened chemicals to build up inside the pipes of the entire cooling
system, which can cause exceedingly costly major repair. The metal pan which
holds the water in the tower cannot be repaired and it is leaking badly.
4. Cost of Maintenance: It is anticipated that cost and time of maintenance will be
reduced if a new system is installed.
Civic Theatre and Community Center Carpet Replacement
1. Description: Replace the carpet in the aisle ways of the Civic Theatre and the
lobby of the Community Center. Estimated cost - $3,700, suggested source of funds
Revenue Sharing.
2. Need: The carpet in the Civic Theatre, which was installed when the building was
constructed in 1968, can no longer be cleaned because of age and spots. The staff
has tried cleaning with steam, shampoo and chemicals to no avail. The carpet in
the Community Center lobby is extremely spotty, there are massive tears at the
entrance to the multi - purpose room doors and because it was layed over the old carpet
it is very difficult to clean because we are still getting dirt from the old carpet.
It can no longer be spot treated and the appearance of both carpets is unacceptable.
3. Cost of Operation: We are currently attempting to clean these carpets on an every
other month basis in order to keep them in some assemblance of decent appearance.
This is very time consuming and costly for the chemicals that we use to clean
carpets. The anticipated installation of commercial grade three carpet will reduce
the problems tremendously.
4. Cost of Maintenance: The cost of maintaining the commercial grade class three
considerably reduces our present cost of maintenance, the commercial carpet can be
spot cleaned easily by eliminating the need for complete cleaning, and it is
estimated that considerable hours will reduced since the new carpet will be cleaned
every three to six months rather than every other month.
15
McWilliams House Repainting
1. Description: Repaint the McWillaims House located in Historical Park.
Estimated cost - $2,000, suggested source of funds, Revenue Sharing.
2. Need: The McWillaims House was saved from destruction and placed in Historical
Park in 1976, at the same time it was painted by volunteers, with donated paint.
The paint has literally worn off in some areas, chipped and peeling in others
and bare wood siding is now exposed. Not only does this cause a bad appearance
but continual exposure to'inclement weather will create the need to replace the
damaged siding.
3. Cost of Operation: The Agreement with the Chamber of Commerce, signed when the
building was moved, indicates the Chamber of Commerce will be responsible for minor
repair ($100 or less) and the City would be responsible for other repairs. No
major expenditures have been made on this building since the placement in 1976.
4. Cost of Maintenance: Maintenance cost could escalate unless surface is properly
protected.
16
CAPITAL PURCHASES
Power Sweeper for Street Sweeping
1. Description: Acquisition of a new power sweeper for street sweeping, a sweeper is
mainly used in the bike lanes, along edges of major thoroughfares, parking lots, etc.
Cost - $25,500, with $15,000 to come from replacement and $10,500 from Revenue
Sharing.
2. Need: The current power sweeper, vehicle number 24, is a 1971 TenantSweeper.
Use of sweeper is recorded in hours not miles and the total number of hours used
of this sweeper is unavailable since records were not kept in the early years. This
vehicle has required constant repair due to the type of work that it does and the
dirt and dust being - ground into the mechanical parts of the unit. The City has
spent 62% of the original cost on repair and the down time is causing a considerable
problem since parts are available from the East Coast only and it takes more than
seven days in order to obtain parts. Also, the present sweeper moves at only five
to ten miles per hour and takes a great deal of time to get from place to place,
it is anticipated the new sweeper can be driven at a maximum of 20 miles per hour,
has a larger box for holding trash and therefore reduces number of trips needed for
dumping.
3. Cost of Operation: The present sweeper is costing considerable money for repair
as well as extensive down time while parts are being obtained and repairs accomplished.
In additional, because the vehicle moves at only five to ten miles per hour, staff
time necessary to run the sweeper could be cut in half if the new power sweeper were
purchased.
4. Cost of Maintenance: It is estimated that the cost of maintaining a new sweeper
would be considerably reduced from our present cost,in addition the new sweeper
is designed in such a fashion to eliminate part of the problems that we have been
experiencing with dirt and dust-getting in to the mechanical portion of the unit.
Replacement Eight Ton Dump Truck (patch truck)
1.. Descrition: Acquistion of a new eight ton dump truck with oiler for asphalt patching
projects. Cost - $30,000, with $25,000 from Replacement and $5,000 from Revenue
Sharing fund.
2. Need: The current eight ton dump truck with oiler which is used for patching
asphalt is a 1973 International, it has 75,000 miles on the odometer and approximately
97,000 on the engine since the engine runs 90% of the time in order to pump the oil
and lift the truck bed. This vehicle replacement meets both warrants of the truck
being more than five years old with more than 50,000 as well as meeting the warrant
of spending more than 75% of the original cost since we have spent 114% of the original
cost on repairs.
3. Cost of Operation: In the eight years the City has owned this eight ton dump truck
we have spent over $14,000 on repair, the repair is becoming exceedingly costly,
down time as a result of need for repair has also posed problems for our patching
crews. It is estimated that the cost of operating a new eight ton dump truck will
be reduced slightly from the current vehicle because of increased gas mileage,
and we would not anticipate major repair within the first several years of owning
the vehicle. The initial request made by the Street Supervisor was for a diesel
truck at a cost of $47,250, the Street Supervisor has reviewed the needs and
determined that we could continue using a gas powered truck for this purpose and
the gas powered truck is approximately $17,000 less. Although the diesel truck
17
Replacement of Eight Ton Dump Truck (continued)
to operate the number of years to amortize the original additional investment
of $17,000 is more than the anticipated life of the vehicle.
4. Cost of Maintenance: It is anticipated that cost of maintenance of a new eight
ton dump truck will be considered less than we are currently spending on the
eight year old vehicle. Cost of general preventative maintenance will not be
any greater than currently.
I. Project Description: Replace three (3) 1970 Plymouth Sedans and one (1)
1971 Chevrolet with three (3) late model used compact cars. The estimated
cost of these three vehicle including tax is $6,000 each or $18,000. The average
resale value of the four (4) we would be selling at public auction should be
$400. This will amount to a net cost to the City of approximately $16,500.
II. Needs Assessment: The four (4) cars which we will be selling have all long
past their scheduled replacement date. They all have high repair to original
cost ratios, and they all are of high fuel usage models.
Although Number 21 has only 64,500 miles, it is probably in the worst condition
and currently in need of repair of its "differential" estimated to cost $600 to
$800. Reduction of personnel has allowed us to eliminate one vehicle.
III. Cost of Current Operation: The average repair cost for the next three years is
estimated at $1,500 each. At $1.45 per gallone, fuel will cost approximately $10,000
over the next three years assuming average of 10,000 miles per year.
IV. Estimated Cost of Maintaining a New System: Repair costs for the next three years should
be negligible. At $1.45 per gallon, fuel will cost approximately $5,000 over the
next three years.
W
Repair Cost
Original
Repair
to Original
Estimat(
Number
Description
Cost
Mileage
Cost
Cost Ratio
Miles /G,
19
1970
Plymouth
$1,721
87,000
$2,326
135%
11 -13
20
1970
Plymouth
$1,721
122,000
$1,940
113%
11 -13
21
1970
Plymouth
$1,721
64,500
$1,675
97%
11 -13
23
1971
Chevrolet
$3,000
71,000
$1,836
61%
12 -14
Although Number 21 has only 64,500 miles, it is probably in the worst condition
and currently in need of repair of its "differential" estimated to cost $600 to
$800. Reduction of personnel has allowed us to eliminate one vehicle.
III. Cost of Current Operation: The average repair cost for the next three years is
estimated at $1,500 each. At $1.45 per gallone, fuel will cost approximately $10,000
over the next three years assuming average of 10,000 miles per year.
IV. Estimated Cost of Maintaining a New System: Repair costs for the next three years should
be negligible. At $1.45 per gallon, fuel will cost approximately $5,000 over the
next three years.
W
Side Discharge Deck for Toro Mower $2,150
I. Project Description
Replacement of the rear discharge deck of the Toro Mower with a side discharge
deck for $2,150.
11. Needs Assessment
It was throught at the time the rear discharge would be a safety feature and keep
the clippings in a confined area. This is not the case. It is creating a window
effect that is very unslightly and causes burning of the grass. It also makes it
difficult for users to fully utilize fields for athletic purposes safely with these
piles of surplus grass. A side discharge distributes the grass evenly and if surplus
grass is created, an additional pass of the mower will reduce the volume so it sifts
down through the blades of grass.
III. Cost of Operating the mower with either deck is the same. There is a possibility
we may be able to receive a trade -in but the cost would be amortized over the original
replacement scheduled for 1985.
Radio for Truck 31 ! $1,300
I. Project Description
Installation of a radio in Truck 31, which was transferred from the Inspection Services
Department without a radio, by County Communications for the sum of $1,300.
H. Needs Assessment
Truck 31 is the only vehicle in the Service Yard without a radio and if we are to
retain continuity in communications, it should be installed. With it in the truck, should
we replace this vehicle, it could be moved to a new truck or replaced.
Gas Powered Hedge Trimmer, Snapper Mower & Echo Blower $1,285
I. Project Description
Three new and replacement units for the Division to continue to be able to perform
our daily routine functions for the amount of $1,285.
II. Needs Assessment
The gas powered trimmer would give us the versility and ability to perform trimming
functions where no electricity is available. The new mower and blower is to replace
equipment no longer cost effective due to tremendous usage and down time.
19
Acquisition of Speed Buffers
1. Description: Purchase of two speed floor buffers for use in the Community Center,
City Hall, Civic Theatre, Service Yard and Hakone Gardens. Estimated cost of two
buffers, $1,200, suggested source of funds, Revenue Sharing.
2. Need: It is recommended that we buy two speed buffers, primarily so they do
no have to undergo the potential damage of moving from building to building.
One buffer would be located in City Hall - Civic Theatre Complex the other buffer
located in the Community Center for use at the Community Center and Service Yard
as well as for transportation to use at Hakone Gardens. In the last year we had
increased our square footage of floor to be maintained by approximately 4,500
square feet, including the Community Center Addition and the floor of Hakone's
Lower House. Our current buffer is a very old - fashioned heavy piece of equipment,
does not have a high rate of speed on turning and past the point of repair. The
Speed Buffers will turn approximately twice as fast as the current buffer which
creates a heat which hardens the wax so that it will last two to three times longer
than wax applied with a slow non -heat buffer. The new buffer is needed in order
to help the current staff accept the added maintenance of both the floor at Hakone
as well as the massive flooring in the Community Center Addition.
3. Cost of Operation: Currently we are using inappropriate methods to keep the
buffer operating until new equipment can be purchased. Also because it runs at a
very slow speed the staff time used to operate the floor buffer is currently
considered to be above that of normal. The new floor buffers will run at a higher
rate of speed, the job can be accomplished better and more efficiently time wise.
4. Cost of Maintenance: It is anticipated that the cost of maintaining this equipment
will be reduced if new equipment is purchased. It is also estimated that wear
and tear on the machines from moving it from building to building will be reduced
if we purchase two machines instead of just one.
One -Half Ton Pick Up Truck for Signing
1. Description: Replace the one half ton pick up truck which is used predominantly
for placement of signs and painting of street markings. Estimated cost - $8,500
with $7,000 from replacement fund and $1,500 from Revenue Sharing.
2. Need: Currently vehicle number 2, which is a one half ton pick up truck being
used predominantly for the signing and street painting program, is a 1971
International Truck. It has over 77,000 miles on it and we have at this point
spent over 1060 of the original cost on repair. Replacement of this vehicle meets
both established guidelines of replacing a vehicle after five years or 50,000 miles
or not spending more than 75% of the original cost on repair.
3. Cost of Operation: Not only is the cost of maintaining the current vehicle
exceeding the original cost, but the constant repair and down time created by the
? need for repair has shown that the vehicle should be replaced in order to save
City funds in the long run. It is anticipated that acquisition of a new vehicle
would reduce repair costs considerably, thereby saving City funds.
4. Cost of Maintenance: Cost of maintenance of the new truck would be considerably
less than we are spending to maintain the present truck, gas mileage of the new
truck is anticipated to be higher than that of the present truck.
20
TYPEWRITER
I. Project Description - The typewriter at the Community Center
needs to be replaced. The cost is $995. If the old type-
writer is traded in, $300 will be credited to the price of
a new machine. $990 was in the Replacement Fund for this
item and it was scheduled to be replaced this fiscal year.
II. Needs Assessment - The present typewriter is almost eight
years old. It does not have the correction tape, sporadically
skips spaces and has several minor problems.
CARD TABLES
I. Project Description - Several of the Community Center's
card tables need to be replaced. The cost of the new tables
is $350. These tables were in the Replacement Fund and
scheduled to be replaced this fiscal year.
II. Needs Assessment - The Community Center uses card tables for
their classes and building rentals. Most of the tables are
in very poor condition. The vinyl table tops are torn and
many of the card table legs are broken.
POOL TABLE
I. Project Description - The cost of a new regulation size
pool table is $1,550. The Center can trade in one of the
old tables for $100. The net cost to the City would be
$1,450.
II. Needs Assessment - The Community Center has three pool tables
and two of them are not regulation size plus being in very
poor condition. The senior citizens who use the tables on
a regular basis have requested the purchase of at least one
new pool table.
21
COMPUTER /WORD PROCESSOR
I. Project Description — Purchase of a computer /word — processor.
Total amount being requested would include funds for an in—
depth analysis of what type of system would be required and
benefits of long -term lease vs. outright purchase. The
estimated cost of the project is $25,000.
II. Needs Assessment - Currently the City is required to retype
any draft and any document which is amended or modified by
the Council or Commission. The retyping of an entire
document is costly and not efficient. A word processor would
allow much more effective use of a secretary's position.
The computer aspect of a system could be useful for accounting
functions, file retrieval system, database and permit control.
A complete cost - effectiveness analysis would be completed
before any purchase of equipment.
Saratoga Village Sign
1. Description: Replace the "Saratoga Village" sign which was in Blaney Plaza
estimated cost - $2,500, recommended source of funding being Revenue Sharing.
2. Need: The Rotary Club and the Village Merchants Association approximately
three years ago raised $1,500 to buy a Saratoga Village sign to be placed in
Blaney Plaza. The sign was approximately 16 feet long, 2 feet high and made out
of redwood planking. The sign was destroyed approximately nine months ago by '
an errant vehicle, neither the driver of the vehicle nor the owner of the vehicle
had insurance, an although a court case is pending against the driver of the
vehicle, no definite action has been taken and no monies received for replacement
of the sign and other damage done. The Village Merchants Association and the
Rotary Club, as well as various individuals, have requested that the sign be
replaced.
3. Cost of Operation: The only cost the City will incur other than purchasing the
sign will be its placement on the appropriate redwood posts in Blaney Plaza. The
previous posts were taken down for appearance reasons.after the original sign
was destroyed.
4. Cost of Maintenance: No additional maintenance costs are anticipated.
22
COMPdUNITY ACTIVITY SUPPORT
Civic Theatre Lighting Booth
1. Description: Addition of a light control booth in the upper back wall of the
Civic Theatre. Involved in this request are the three major groups who use the
Theatre, the Saratoga Drama Group, West Valley Light Opera, and the Saratoga -
Los Gatos Community Players. The addition of the rear light control booth would
provide the theatre groups with the ability to control stage lighting from the
rear of the theatre rather than the temporary booth which is built on the side
wings and is frequently in the way of the theatre groups and City meetings as well
as difficult for people to use effectively.. The amount requested by the theatre
groups is $2,700 for materials and architectural fees, it is recommended they be
taken from Revenue Sharing Funds and the theatre groups have volunterred to do the
construction according to City Building Codes.
2. Need: The light control booth in the rear of the auditorium would be a tremendous
asset to all theatre groups who use the building. Currently the theatre groups
are very handicapped by the lighting control unit being directly in the wing of
the stage and the controller is unable to see large portions of the stage and the
lighting and action taking place during any production. The insurance company
of the City has on frequent occasions recommended that the dimmer controls and
lighting controls be removed from stage right so that they do not pose an electrical
hazard. The affect of the light control booth will remove a great number of the
dimmer controls and units which are located separate from the power unit which is
installed permanently. Originally the Civic Theatre was designed so that a
balcony and /or light control booth could be placed in the rear of the theatre,
there is access to this area from the closet space opposite the women's restroom
and as stated above the lighting booth will be designed to meet Building and Fire
Codes. The only noticable change from the interior of the Civic Theatre will be
a window above the seating level, in the back wall of the theatre.
3. Cost of Operation: Following initial capital outlay there will be no change in
the cost of operation from the current method but there will be an added value to
the theatre by having a standard lighting control booth. As stated, the theatre
groups have volunterred to provide labor and Munson Theatrical Supplies will donate
the low voltage cable which will run from the stage to the lighting booth.
Approximate value of the donated labor is $3,000.
4. Cost of Maintenance: There will be no increased cost of maintenance.
23
Community Garden Irrigation System
1. Description: Purchase of materials and equipment for installation of a spray
and drip irrigation system for a portion of the Saratoga Community Garden.
Estimated cost of materials and equipment - $1,500, recommmended to be taken
from Revenue Sharing Funds.
2. Need: The Community Garden currently has a severe problem in staffing because
of the elimination of CETA funding as well as the elimination of considerable
support from the City of Saratoga approximately four years ago. Currently,
tasks such as hand watering of flower and herb areas and shrub borders cause
excessive consumption of time. There are no fixed watering devices. The installation of
a spray and drip irrigation system will not only reduce the necessary staff time
for handwatering, but will provide a more efficient use of water. The Community
Garden has already contacted a landscape contractor, Patrick Ferris, who has
donated his time to design the system and the Community Garden has agreed to do
the installation. The only cost to the City will be for the materials and supplies
necessary.
3. Cost of Operation: It is estimated that the Community Garden staff are - spending
approximately 15 hours per week doing this watering alone during the dry months.
The installation of the appropriate irrigation system will save approximately
560 work hours per year and it is estimated that it will provide approximately
10% savings of water used over a period of one year. This in turn will save the
City money since the City has, since the Community Garden's inception in 1972,
supported the Garden by assisting.with the cost of water.
4. Cost of Maintenance: The cost of maintaining the new system will be minimal,
i.e., replacement of shrub heads and any broken irrigation lines, but it is
estimated that no major repair would be necessary for a minimum of five years.
Cost of this maintenance is the responsibility of the Community Garden.
24
CITY WIDE PROJECTS
PHONE SYSTEM
I. Project Description - Replace the existing phone system with
a City -owned system. Total estimated cost of replacing the
current system is $45,000.
II. Needs Assessment - The City currently rents the phone system
at a cost of $800 per month. There are a limited number of
lines in and out of the City which often presents a problem
for residents and employees. The new system would increase
the number of lines and allow the calls to be processed more
quickly.
III. Cost of Current Operation - The current phone system cost
the City approximately $800 in rent per month. It is
expected that there will be an increase in rental rates of
between 13% - 15% annually.
IV. Estimated Cost of New System - The initial cost of establish-
ing a new phone system will cost approximately $45,000. The
amount is for purchase of a more efficient system.
Based on saving $800+ per month in rental fees, the City
will pay for the system in four years.
COMMUNITY SERVICE OFFICER PROGRAM
I. Project Description - Establishment of a program which would
utilize Community Service Officers (CSO) within the City to
assist with routine traffic accidents, report writing, code
enforcement and other services which would not require a
deputized sheriff officer.
II. Needs Assessment - Currently the City spends approximately .
$900,000 for its sheriff's contract. A majority of the routine
calls could be answered by a non - deputized officer, thus
reducing the cost of the sheriff's contract.
There are numerous benefits associated with a CSO Program
to include: greater participation within the Community
(crime prevention presentations etc.); enforcement of ;Zoning
Ordinance parking limits and possible work with the Fire
District in terms of Fire Inspections.
III. Cost of Current Operation - The current sheriff's contract
costs the City approximately $900,000.
IV. Estimated Cost of New System - The initial cost of establishing
a CSO Program would involve velve purchase of vehicles, uniforms,
training, and assistance in recruitment. Once the program
is established, salary, auto maintenance and continual
training will be a part of the budget. Estimated cost to
establish program - $30,000.
25
rrZ. TTr r%V1 Pmr- VrQ7TAV1 -09 FAVr PTMTOM-A
REPORT TO MAYOR AND
CITY COUNCIL
DATE: 12/28/81
COUNCIL MEETING: 1/06/82
SUBJECT: Condition of Park Division International Harvester One Ton Dump Truck
The following is 'an outline of the damage to the truck which needs to be repaired
as a result of the accident as well as comments on the general condition of the
truck.
Damaged parts which need to repaired as a result of the accident include:
radiator, complete realignment of the bed, sub -bed and sides of the truck bed,
repair of frame braces, replacement of exhaust pipe and hangers, front end
alignment, front fender, grill and bumper, both doors and left vent window,
parking brake cable and linkage, paint and other minor items.
The truck is seven years old, was originally due for replacement in 1981, and
has been considered a "lemon" since its acquisition. It has been driven over 50,000
miles and in addition to the repair necessitated by the theft and accident the
truck was scheduled for major electrical system and carburetor repair at an
estimated cost of $550. The truck was purchased for $5,800 in 1974 and the
current estimate of complete repair almost equals the original cost of the truck.
This is the main reason the staff are recommending that this truck not be repaired
and that it be replaced.
It is likely the truck has a salvage value of $750 to $1,000 and the bid would
request consideration of this salvage value.
Staff will be available to answer any questions you might have on this subject.
ms
26
5 �1,7
Barbara Sampson, Director
Maintenance Services
RESOLUTION NO.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SARATOGA
APPROVING THE 1981 -82 CAPITAL IMPROVEMENT BUDGET
ice+
CITY OF SARATOGA
AGENDA BILL NO.
DATE: December 10, 1981
DEPARTMENT: CITY ATTORNEY
Initial:
Dept. Hd.
C. Atty.
C. Mgr.
SUBJECT: AMENDMENT TO STIPULATION FOR SETTLEMENT BETWEEN FREMONT UNION HIGH
SCHOOL DISTRICT AND CITY OF SARATOGA
Issue Summary: On June 2, 1981, the City adopted Resolution No. 1013 accepting
and approving a settlement agreement between the City and the Fremont Union High
School District, the subject matter of which was the school district's
property located on Prospect Road within the Measure A area. Since that
date concern has been expressed by the District that Paragraph lA on page 4
of the Agreement does not set forth the specific zoning standards by which
the property may be developed. In addition, the City may wish to allow the
property to be the subject of a transfer of development rights if that con-
cept should be included in the implementing ordinances for the Measure A
area. The attached Amendment to the said Agreement stipulates that develop-
ment of the property shall be in accordance with R -1- 20,000 standards and that
the property shall be subject to a transfer of development rights should the
Recommendation : /City adopt those by ordinance in the future.
Adopt Resolution approving and accepting the Amendment
to the Agreement dated May 31, 1981.
Fiscal Impacts : None
Exhibits /Attachments : Resolution and attached Amendment to Agreement.
Council Action
12/16: Watson/Mallory moved to adopt Resolution 1051. Passed 4 -1 (Jensen opposed).
.. ti
12/10/81 •.
ABSENT:
ATTEST:
City Clerk
Mayor
RESOLUTION NO.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SARATOGA ACCEPTING AND APPROVING AN AMENDMENT TO
THAT CERTAIN STIPULATION FOR SETTLEMENT DATED
MAY 31, 1981, BY AND BETWEEN THE FREMONT UNION
'
HIGH SCHOOL DISTRICT AND THE CITY OF SARATOGA
WHEREAS, on May 31, 1981, the City of Saratoga ( "CITY ")
and the Fremont Union High School District ( "DISTRICT "). entered
into a Stipulation for Settlement settling litigation between the
CITY and the DISTRICT; and
f
WHEREAS, both the CITY and the DISTRICT desire to clarify
said Agreement by amending Section lA of said Agreement;
x�r3k'ciyrrrta =rF3v U'?
NOW, THEREFORE, the City Council of the City of Saratoga
( "Council ") RESOLVES as follows:
1. The City Council hereby accepts and approves the
Amendment to Stipulation for Settlement in the form attached hereto
marked Exhibit "A" and directs the City Manager to supervise the
execution thereof by all necessary persons.
2. The City Council further hereby authorizes and directs
that said Amendment to Stipulation for Settlement be recorded with
the Office of the Recorder of Santa Clara County.
The above and foregoing resolution was passed and adopted
at a regular meeting of the City Council of Saratoga held on the
day of 1981, by the following vote:
AYES:
.: >.:,.
NOES:
ABSENT:
ATTEST:
City Clerk
Mayor
v
t `
MIENDMENT TO STIPULATION
FOR SETTLEMENT
THIS AMENDMENT TO STIPULATION FOR SETTLEMENT is made
at Saratoga, California, this day of November, 1981, by
and between FREMONT UNION HIGH SCHOOL DISTRICT, a School District
( "Fremont "), on the one hand, and J. WAYNE DERNETZ as City Clerk
of the City of Saratoga ( "Dernetz "), MAYOR LINDA CALLON, Council -
members JOHN MALLORY, CHERIEL JENSEN, MARTHA CLEVENGER and DALE
WATSON (each of the last five (5) named individuals will herein-
after be referred to collectively as "City Councilmembers "), on
the other hand, and is made and entered into with reference to
the following recitals:
A. On May 31 1981, the parties hereto
entered into a Stipulation for Settlement, a copy of which is
attached hereto marked Exhibit "A" and incorporated herein by
reference as if and as though set out in full.
B. Said Stipulation for Settlement was approved by
resolution of the City Council of the City of Saratoga on
June 2, 1981, and was approved by resolution of the Board of
Trustees of the Fremont Union High School District on
C. Subsequent to the approval and execution of this
Agreement by all the parties hereto, the parties have agreed
that Section lA of said Stipulation for Settlement needs further
clarification in order to determine with particularity under
what residential zoning standards the property will be allowed
to develop.
-1-
11 /GD /251
D. In an effort to avoid further litigation and allow
future implementation of this Agreement, the parties hereto have_
agreed to amend the Stipulation for Settlement as set forth herein-
after.
WHEREFORE, the parties hereto hereby agree that Section
lA of said Stipulation for Settlement shall be and is hereby
amended to read as follows:
"A. 'The fifty -five dwellings': The fifty -five
single family dwellings to be built on Parcel
'A' in accordance with the City's Subdivision
Ordinance and, at the City's option, either the
planned community district_ ('P -C') provisions of
the City Zoning Ordinance or the R -1- 20,000 zoning
as per Paragraph 3 below. In addition, one single
family dwelling is to be built on Parcel 'B',
which is zoned R -1- 10,000 in accordance with the
Subdivision Ordinance. It is the understanding of
the parties hereto that no more than fifty -five
(55) units shall be permitted to develop on,the
property except that this Agreement will in no
way restrict or affect the ability of either party
to exercise transfer of development rights in the
future in accordance with City policies or ordinances
which might be in effect at such future time of
exercise."
In all other respects, the Stipulation for Settlement,
Exhibit "A" attached hereto, is reaffirmed by the parties.
Dated:
Dated:
FREMONT UNION HIGH SCHOOL DISTRICT,
a School District
By
President
By
ecretary
"Fremont"
J. WAYNE DERNETZ, as City Clerk of
the City of Saratoga
-2-
"Dernetz"
Dated:
Dated:
Dated:
Dated:
Dated:
APPROVED AS TO FORM:
Dated:
Dated:
Dated:
Mayor Linda Callon
Martha Clevenger
John Mallory
Cheriel Jensen
Dale Watson
"City Councilmembers"
C+RIST, GRIFFITHS, BRYANT, SCHULZ,
BIORN & CLOHAN
By
Frank Lee Crist, Jr.
Attorneys for Fremont
LAGORIO, HENEKE, MADDEN & TARBOX
By
Anthony A. Lagorio
PAUL B. SMITH
Saratoga City Attorney
By
Paul B. Smith