HomeMy WebLinkAboutRinconada Reliability Saratoga Council Presentation 10-7-15 v3The purpose of this presentation is to
inform you about the Rinconada Reliability
Project
•Provide Project Background
•Describe the Phases of the Project
•Explain how you can stay informed
•Original Rinconada WTP finished in 1968
•Sole District Water supply to West Valley
Service Area
•Current Project
Planning completed June 2012
Design completed January 2015
Construction started July 2015
Construction completion July 2020?
•Replace facilities and components that are
near the “end of their useful life”
•Meet increasingly stringent water quality
standards
•Comply with current seismic codes
•Improve plant safety
•Increase Water Production Capacity from
•80 MGD to 100 MGD
•Provide new facilities
•Raw Water Ozonation
•Flocculation and Plate Settler Clarification
•Dual Media Filtration
Residuals
Ops Bldg Seismic
Quito Bridge
Rinconada Reliability Improvement Project Construction Phases
Phase
1 Phase 2 Phase 3 Phase 4 Phase 5
Coordinating Schedule
with Other Activities
Stay Informed:
•Visit the District’s website and blog at
www.RinconadaReliabilityProject.com
•Contact District’s Public Affairs Representative Tony
Mercado
Telephone number: 408-426-1039
E-mail address: Tmercado@valleywater.org