HomeMy WebLinkAboutFinal Saratoga Adaptive Presentation 2-6-19Traffic Signal Adaptive Project
along
Saratoga Avenue
City Council Meeting
2-6-2019
Project Funding
VTA –Local Program Reserve Grant, ITS Program:
Grant Amount:
Local Match:
Project Total:
$400,000
$100,000
$500,000
This Contract:
Remaining Funding:
$122,967
$377,033 -For Video Detection Equipment
and Adaptive Technology
-Additional Funding Request Anticipated
up to $100,000 pending Bid Responses
Project Locations
15 Traffic Signals
Citywide
Monitoring &
Communication
6 Locations with
Adaptive Tech
along Saratoga Ave
& Fruitvale Ave
Project Elements
Equipment:
1)Video Detection
•6 Adaptive Intersections
2)Adaptive Technology –6 Locations
•Traffic Signal Controllers
•Cabinet Auxiliary Equipment
•City Hall Server and Network
3) Monitoring –15 Locations
•Smart City Signals Technology
Consulting:
A) Field Inventory
•Traffic Signal Cabinets
B) RFP Development
•Adaptive Equipment
Procurement
C) Project Management
•Adaptive System Build-Out
Project Elements
The City of Saratoga will be the first city in California to launch
Smart City Signals
1)Traffic Signal Cabinet Monitoring
•Red, Yellow, Green, Loop Detection, Pedestrian Buttons
•Alarms (Failure, Police Control, Railroad)
2)Cellular Communications
•Cloud Platform Monitoring
3) Maintenance Support
•Preemptive Support vs Responsive
•Contractor Monitoring
Project Locations 15 Traffic SignalsTraffic Signal Intersections & Agencies
NEXT STEPS
RFP Development
1)Develop and Release RFP
•Advertise: March 2019
•Award: May 2019
2)Video Detection Equipment Installation
•Install: May 2019
3) Smart City Signals Monitoring
•Install: March 2019