HomeMy WebLinkAboutQuito Bridge Project POWERPOINT 11-20-19Quito Bridge Replacement Project
2014
Design Phase
Complete
2016 -2020
Right of Way
Current Phase
2021
Construction
(12 to 18
months)
2022
Project
Completion
2
2012
Environmental
Complete
Bridge 113 (Vessing Road)
3
Both Bridges Built 1915
Functionally Obsolete
Structurally Deficient
Poor Condition Rating by Caltrans Inspection Report
Bridge 114 (Old Adobe Road)
4
5
•$5.0 MillionTotal Project
•$4.1MillionFederal Highway
Bridge Grant
•$900,000Local Match
•$300,000/ each Saratoga, Los Gatos,
SCV Water District
6
Public Input
Kick-off meeting on
11/05/2013
Public Meetings Held
4/28/2014
7/29/2014
City Staff will
continue community
outreach throughout
the project
7
Number of parcels affected
Two private parcels
Right-Of-Way Takes 2,524 SF
Permanent Easements 3,204 SF
Temporary Construction Easements 13,387 SF
8
APN ROW Take Permanent
Easement
Temporary
Construction
Easement
397-05-028 2,139 SF 3,204 SF 11,137 SF
397-05-014 385 SF 0 2,250 SF
Total =2,524 SF 3,204 13,387 SF
A request for obligation with Caltrans for
construction must be submitted by November
1st to be illegible for construction the
following Spring.
The project will be illegible to request for
construction by November 1st, 2020
for a construction start in Spring of 2021.
9