HomeMy WebLinkAboutCity Council Resolution 21-030 resolution TDARESOLUTION NO.21-030
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SARATOGA
REQUEST TO THE METROPOLITAN TRANSPORTATION COMMISSION FOR THE
ALLOCATION OF FISCAL YEAR 2021-22 TRANSPORTATION DEVELOPMENT
ACT ARTICLE 3 PEDESTRIANBICYCLE PROJECT FUNDING
WHEREAS, Article 3 of the Transportation Development Act (TDA), Public Utilities
Code (PUC) Section 99200 et siM., authorizes the submission of claims to a regional
transportation planning agency for the funding of projects exclusively for the benefit and/or use
of pedestrians and bicyclists; and
WHEREAS, the Metropolitan Transportation Commission (MTC), as the regional
transportation planning agency for the San Francisco Bay region, has adopted MTC Resolution
No. 4108, Revised, entitled "Transportation Development Act, Article 3, Pedestrian/Bicycle
Projects," which delineates procedures and criteria for submission of requests for the allocation
of "TDA Article 3" funding; and
WHEREAS, MTC Resolution No. 4108, Revised requires that requests for the allocation
of TDA Article 3 funding be submitted as part of a single, countywide coordinated claim from
each county in the San Francisco Bay region; and
WHEREAS, the City of Saratoga desires to submit a request to MTC for the allocation
of TDA Article 3 funds to support the projects described in Attachment B to this resolution,
which are for the exclusive benefit and/or use of pedestrians and/or bicyclists;
NOW, THEREFORE, BE IT RESOLVED, that the City of Saratoga declares it is
eligible to request an allocation of TDA Article 3 funds pursuant to Section 99234 of the Public
Utilities Code, and
BE IT FURTHER RESOLVED, that there is no pending or threatened litigation that
might adversely affect the project or projects described in Attachment B to this resolution, or that
might impair the ability of the City of Saratoga to carry out the project; and
BE IT FURTHER RESOLVED, that the City of Saratoga attests to the accuracy of
and approves the statements in Attachment A to this resolution; and
BE IT FURTHER RESOLVED, that a certified copy of this resolution and its
attachments, and any accompanying supporting materials shall be forwarded to the congestion
management agency, countywide transportation planning agency, or county association of
governments, as the case may be, of Santa Clara County for submission to MTC as part of the
countywide coordinated TDA Article 3 claim.
BE IT FURTHER RESOLVED, the above and foregoing resolution was passed and adopted at
a regular meeting of the Saratoga City Council held on the 19"' day of May 2021 by the
following vote:
AYES: Mayor Yan Zhao, Vice Mayor Tina Walia, Council Members Mary -Lynne
Bernald, Kookie Fitzsimmons, Rishi Kumar
NOES:
ABSENT:
i_ W_►
Yan Zhao, Mayor
City of Saratoga
Attest: 6�� DATE:
Debbie Bretschneider, City Clerk
Resolution No. 21-
Attachment A
Page 1 of 1
Re: Request to the Metropolitan Transportation Commission for the Allocation of Fiscal Year 2021-22
Transportation Development Act Article 3 Pedestrian/Bicycle Project Funding
Findings
1. That the City of Saratoga is not legally impeded from submitting a request to the Metropolitan Transportation
Commission for the allocation of Transportation Development Act (TDA) Article 3 funds, nor is the City of
Saratoga legally impeded from undertaking the project(s) described in "Attachment B" of this resolution.
2. That the City of Saratoga has committed adequate staffing resources to complete the project(s) described in
Attachment B.
3. A review of the project(s) described in Attachment B has resulted in the consideration of all pertinent matters,
including those related to environmental and right-of-way permits and clearances, attendant to the successful
completion of the project(s).
4. Issues attendant to securing environmental and right-of-way permits and clearances for the projects described
in Attachment B have been reviewed and will be concluded in a manner and on a schedule that will not
jeopardize the deadline for the use of the TDA funds being requested.
5. That the project(s) described in Attachment B comply with the requirements of the California Environmental
Quality Act (CEQA, Public Resources Code Sections 21000 et seq.).
6. That as portrayed in the budgetary description(s) of the project(s) in Attachment B, the sources of funding
other than TDA are assured and adequate for completion of the project(s).
7. That the project(s) described in Attachment B are for capital construction and/or final design and engineering
or quick build project; and/or for the maintenance of a Class I bikeway which is closed to motorized traffic
and/or Class IV separated bikeway; and/or for the purposes of restriping Class II bicycle lanes; and/or for the
development or support of a bicycle safety education program; and/or for the development of a comprehensive
bicycle and/or pedestrian facilities plan, and an allocation of TDA Article 3 funding for such a plan has not
been received by the City of Saratoga within the prior five fiscal years.
8. That the project(s) described in Attachment B which are bicycle projects have been included in a detailed
bicycle circulation element included in an adopted general plan, or included in an adopted comprehensive
bikeway plan (such as outlined in Section 2377 of the California Bikeways Act, Streets and Highways Code
section 2370 et seq.) or responds to an immediate community need, such as a quick -build project.
9. That any project described in Attachment B bicycle project meets the mandatory minimum safety design
criteria published in the California Highway Design Manual or is in a National Association of City and
Transportation Officials (NACTO) guidance or similar best practices document.
10. That the project(s) described in Attachment B will be completed in the allocated time (fiscal year of allocation
plus two additional fiscal years).
11. That the City of Saratoga agrees to maintain, or provide for the maintenance of, the project(s) and facilities
described in Attachment B, for the benefit of and use by the public.
Resolution No. 21-
Attachment B
Page 1 of 2
RE: Request to the Metropolitan Transportation Commission for the Allocation of Fiscal Year 2021-22
Transportation Development Act Article 3 Pedestrian/Bicycle Project Funding
TDA Article 3 Project Application Form
Fiscal Year of this Claim: 21-22 Applicant: City of Saratoga
Contact person: Macedonio Nunez
Mailing Address: 13777 Fruitvale Avenue Saratoga CA 95070
E-Mail Address: mnunez(a)saratoga ca us Telephone: (408) 868-1218
Secondary Contact (in event primary not available) John Cherbone
E-Mail Address: iherbone a()saratoga ca us Telephone: (408) 868-1241
Project Title (Short Description): Saratoga Ave Pathway Project
Amount of claim: $31 040
Description of Overall Project:
Along Saratoga Ave, between Big Basin Way and Scotland Drive. Project includes reconstruction and
improvement to handicap ramps, reconstruct and rehabilitate deteriorating asphalt concrete (AC) pathways.
Installation of continuous curbs and Lyutters. concrete sidewalks.
Project Scope Proposed for Funding: (Project level environmental, preliminary planning, and ROW are ineligible uses of TDA funds.)
The Funding will be used for the construction and inspection of the project.
Project Budget and Schedule
Resolution No. 21-
Attachment B
Page 2 of 2
TDA Article 3 Project Application Form
Project Eligibility:
YES?/NO?
A.
Has the project been approved by the claimant's governing body? (If "NO," provide the approximate date approval is
NO
anticipated).
6-2-21
B.
Has this project previously received TDA Article 3 funding? If "YES," provide an explanation on a separate page.
YES
C.
For "bikeways," does the project meet Caltrans minimum safety design criteria pursuant to Chapter 1000 of the California
YES
Highway Design Manual? (Available on the internet via: http://www.dot.ca.gov).
D.
Has the project been reviewed by the Bicycle and Pedestrian Advisory Committee? (If "NO," provide an explanation).
YES
E.
Has the public availability of the environmental compliance documentation for the project (pursuant to CEQA) been
YES
evidenced by the dated stamping of the document by the county clerk or county recorder? (required only for projects that
include construction).
F.
Will the project be completed before the allocation expires? Enter the anticipated completion date of project (month and
YES
year) June 2022
G. Have provisions been made by the claimant to maintain the project or facility, or has the claimant arranged for such
YES
maintenance by another agency? (If an agency other than the Claimant is to maintain the facility provide its name:
Project Eligibility:
B. This project has been previously funded in several cycles. See the attached TDA article 3 application for fiscal
year of claim 03/04.
D. This project is ongoing and has been reviewed in the past. See the attached TDA article 3 application for fiscal
year of claim 03/04
Resolution No. 21-
Attachment B
Page 1 of 1
TDA Article 3 Project Application Form
Fiscal Year of this Claim: 03/04 Applicant: City of Saratoga
Contact person: Morgan Kessler
Mailing Address: 13777 Fruitvale Avenue, Saratoga CA 95070
E-Mail Address: mkessler(a saratoga.ca.us Telephone: (408) 868-1218
Secondary Contact (in event primary not available) John Cherbone
E-Mail Address: iherbone@saratoga.ca.us Telephone: (408) 868.1241
Short Title Description of Project: Saratoga Avenue Pathway Project
Amount of claim: $17,254.00
Functional Description of Project:
Asphalt concrete & Portland cement concrete walkway along Saratoga Avenue, between Herriman Drive & Big Basin Way
Financial Plan:
List the project elements for which TDA funding is being requested (e.g., planning, environmental, engineering, right-of-way,
construction, construction management, contingency). Use the table below to show the project budget. Include prior and
proposed future funding of the project. If the project is a segment of a larger project, include prior and proposed funding
sources for the other segments (make certain the use of the currently requested funding is made clear in the "Project
Elements" section below, and include any other clarifying information on the next page).
Project Elements: Final design specification, construction, inspection.
Fundin Source
All Prior FYs
Application FY
Next FY
FollowingFYs
Totals
TDA Article 3
$103,926.00
$17,254.00
$17,254.00
list all other sources:
1.
2.
3.
4.
Totals
$103,926.00
$17,254.00
$121,180.00
Project Eligibility:
YES?/NO?
A.
Has the project been approved by the claimant's governing body? (If "NO," on the next page provide the approximate date
YES
approval is anticipated).
B.
Has this project previously received TDA Article 3 funding? If "YES," provide an explanation on the next page.
YES
C.
For "bikeways," does the project meet Caltrans minimum safety design criteria pursuant to Chapter 1000 of the California
Highway Design Manual? (Available on the internet at: http://www.dot.ca.gov/hq/oppd/hdm/chapters/t1001.htm).
D.
Has the project been reviewed by a Bicycle Advisory Committee? (If "NO," provide an explanation on the next page).
YES
E.
Has the public availability of the environmental compliance documentation for the project (pursuant to CEQA) been
YES
evidenced by the dated stamping of the document by the county clerk or county recorder? (If "NO" provide and explanation
on the next page; and note that MTC cannot allocate funds to a project which lacks environmental clearance).
F.
Will the project be completed within the three fiscal year time period (including the fiscal year of funding) after which the
YES
allocation expires? Enter the anticipated completion date of project (month and year)
G. Have provisions been made by the claimant to maintain the project or facility, or has the claimant arranged for such
YES
maintenance by another agency? (If an agency other than the Claimant is to maintain the facility provide its name: