HomeMy WebLinkAboutCity Council Resolution 21-036 SB1 funded road projectsRESOLUTION NO.21-036
RESOLUTION ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2021-22 FUNDED BY
SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill I (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5,
Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to
address the significant multi -modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the
residents of our City of Saratoga are aware of the projects proposed for funding in our community and
which projects have been completed each fiscal year; and
WHEREAS, the City of Saratoga must adopt by resolution a list of projects proposed to receive
fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1,
which must include a description and the location of each proposed project, a proposed schedule for the
project's completion, and the estimated useful life of the improvement; and
WHEREAS, the City of Saratoga, will receive an estimated $613,840 in RMRA funding in
Fiscal Year 2021-22 from SB 1; and
WHEREAS, this is the fourth year in which the City of Saratoga is receiving SB 1 funding and
will enable the City of Saratoga to continue essential road maintenance and rehabilitation projects, safety
improvements, repairing and replacing aging bridges, and increasing access and mobility options for the
traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City of Saratoga used a Pavement Management System to develop the SB 1
project list to ensure revenues are being used on the most high -priority and cost-effective projects that
also meet the communities priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City of Saratoga maintain and rehabilitate
various streets and roads throughout the City of Saratoga this year through the Annual Roadway
Improvements program and several similar projects into the future; and
WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with
a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting -
edge technology, materials and practices, will have significant positive co -benefits statewide.
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the City Council
of the City of Saratoga, State of California, as follows:
The foregoing recitals are true and correct.
2. The following list of proposed projects will be funded in -part or solely with fiscal year 2021-22
Road Maintenance and Rehabilitation Account revenues:
Project Description
Location
Estimated Useful Life
Year of
Construction
Pavement maintenance project
Saratoga Avenue,
5 — 25 years.
FY 2021/22
to rehabilitate city roadways to
Quito Road, El
improve Pavement Condition
Camino Grande,
Index (PCI) and safety through
and Via Colina
AC overlay, micro -surfacing,
repair failed street sections,
traffic loops, curb and gutter,
ADA ramps, and re -striping
traffic lanes.
The above and foregoing resolution was passed and adopted at a regular meeting of the Saratoga City
Council held on the 2nd day of June 2021 by the following vote:
AYES: Mayor Yan Zhao, Vice Mayor Tina Walia, Council Members Mary -Lynne
Bernald, Kookie Fitzsimmons, Rishi Kumar
NOES:
ABSENT:
ABSTAIN:
an Zhao, Mayor
ATTEST:
DATE:
ZDZ
Debbie Bretschneider, CMC, City Clerk